Record of Decision
Remedial Alternative Selection

Site Name and Location

Rose Disposal Pit
Lanesborough, Massachusetts

Statement of Purpose

This Decision Document presents the selected remedial action for
this site developed in accordance with the Comprehensive
Environmental Response, Compensation, and Liability Act of 1980
(CERCLA), as amended by the Superfund Amendments and
Reauthorization Act of 1986 (SARA), and to the extent practicable,
the National Contingency Plan (NCP); 40 CFR Part 300 gt seq..
47 Federal Register 31180 (July 16, 1982), as amended.

In accordance with CERCLA Section 121(f)(1)(E) and (G), EPA has
provided the Commonwealth of Massachusetts with the opportunity to
review and comment on the Remedial Investigation, the Feasibility
Study, and the Proposed Plan for Remedial Action.

Statement of Basis

This decision is based on the administrative record which was
developed in accordance with Section 113(k) of CERCLA and which is
available for public review at the information repositories (index
attached). The attached index identifies the items which comprise
the administrative record upon which the selection of a remedial
action is based.

Description of the Selected Remedy

The selected remedy for the Rose site is a comprehensive approach
for site remediation which includes both a source control and a
control/management of migration component.

The source control component entails the following:

Excavation and on-site incineration of approximately
15,000 yd3 of contaminated soil and sediment. Excavation
will be to 13 ppm of PCBs to the water table and will include
limited excavation in the saturated zone to remove the
subsurface free product portion of the disposal'area.

On-site incineration is a technology which has been proven to
be effective in the treatment of PCB and VOC-contaminated
soils. Extensive design work will be required, however, to
design a transportable incinerator that is suitable for the
Rose site.


-------
It is estimated that it will take approximately two (2) years
to treat 15,000 cubic yards of PCB and VOC-contaminated soil
and sediment. This estimate is for construction/operation
time only, and does not include the time for design, bidding
and awarding of the construction contract.

The control/management of migration component will be implemented
as soon as possible. This component entails:

Active restoration of the shallow overburden aquifer
contaminated with volatile organic compounds (VOCs) using on-
site treatment involving air stripping and carbon adsorption.
A bedrock well will be installed in the vicinity of the free
product area to prohibit migration into fractured rock.
Groundwater will be treated to reduce contaminants to levels
which will meet drinking water standards or other appropriate
guidelines. Rose's pond sediments and surface water will also
be treated and the pond will be restored to its original
wetlands character after remediation.

EPA has determined that remediation of sediments located in
the saturated zone of the disposal area is not cost effective
and would potentially entail unacceptable impacts on the
adjacent wetlands. However, treatment of VOCs will render the
PCBs relatively immobile, thus restricting subsurface PCB
contamination to below the water table in the disposal area.
Since PCBs will be present in groundwater in excess of the
cleanup level upon completion of groundwater remediation, it
will be necessary to implement institutional controls to
prevent groundwater use and excavation into the saturated zone
within the disposal area.

The estimated present worth cost for the source control component
is $5,200,000 and the groundwater remediation component is
$1,256,000. The total estimated cost for the selected remedy for
the Rose site is $6,450,000.

Declaration

The selected remedy is protective of human health and the
environment, attains Federal and State requirements that are
applicable or relevant and appropriate, and is cost-effective.

This remedy satisfies the statutory preference for treatment that
permanently and significantly reduces the volume, toxicity and
mobility of the hazardous substances, pollutants and'contaminants
as a principal element. It is determined that this remedy utilizes
permanent solutions and alternative treatment technologies to the
maximum extent practicable.

Regional Administrator, EPA Region I


-------
ROD Decision Summary
Rose Disposal Pit Superfund Site
Lanesborough, Massachusetts

September 23, 1988
U.S. Environmental Protection Agency
Region I


-------
ROSE DISPOSAL PIT
TABLE OF CONTENTS
Contents	Page N'unhpr

I.	SITE NAME, LOCATION AND DESCRIPTION ......	1

II.	SITE HISTORY AND ENFORCEMENT ACTIVITIES ....	1

A.	Response History 		1

B.	Enforcement History 		2

III.	COMMUNITY RELATIONS 		3

IV.	SCOPE AND ROLE OF OPERABLE UNIT OR RESPONSE
ACTION 		3

V.	SITE CHARACTERISTICS	4

A.	General	4

B.	Soil	4

C.	Groundwater 		5

VI.	SUMMARY OF SITE RISKS AND CLEANUP GOALS ....	6

A.	GE's Endangerment Assessment 		6

B.	EPA PCB Soil Cleanup Level	8

C.	EPA Groundwater Cleanup Goals 		8

VII.	DOCUMENTATION OF SIGNIFICANT CHANGES 		9

VIII.	DEVELOPMENT AND SCREENING OF ALTERNATIVES . .	11

A.	Statutory Requirements/Response Objectives . .	11

B.	Technology and Alternative Development and
Screening	12

IX.	DESCRIPTION/SUMMARY OF THE DETAILED AND
COMPARATIVE ANALYSIS OF ALTERNATIVES ....	14

A.	Source Management Alternatives Analyzed ...	14

B.	Management of Migration Alternatives Analyzed.	21

X.	THE SELECTED REMEDY	23

A.	Description of the Selected Remedy	23

B.	Rationale for Selection/Points of Compliance .	24

1.	Source Management 		24

2.	Management of Migration	26

XI.	STATUTORY DETERMINATIONS	. .	27

A.	The Selected Remedy is Protective of Human
Health and the Environment			27

B.	The Selected Remedy Attains ARARs 		28

C.	The Selected Remedial Action is Cost

Effective		 .	31


-------
D.	The Selected Remedy Utilizes Permanent
Solutions and Alternative Treatment Technolo-
gies or Resource Recovery Technologies to the
Maximum Extent Practicable ..... 	 32

E.	The Selected Remedy Satisfies the Preference

for Treatment as a Principal Element	32

XII.

STATE ROLE

33


-------
Rose Disposal Pit

Record of Decision Summary

LIST OF FIGURES

Figure Wnmh^r-

1.	Site Location Map

2.	PCB Soil Contamination Profiles in the Disposal Area

3.	Well Locations and Total VOCs in Shallow Groundwater

Wiimher-

1.	Summary of Field Investigations

2.	Site Contaminants and Contaminants of Concern

3.	Summary of Potential Exposure Routes

4.	Potential Exposure Routes with Potential Human Health Risks

5.	Potential Chemical-Specific ARARs, Guidelines and Cleanup

Goals for Groundwater

6.	Summary of Remedial Alternatives

7.	Potential Action-Specific ARARs; Federal

8.	Potential Action-Specific ARARs; State

LIST OF TABLES

APPENDICES

Responsiveness Summary 	

Administrative Record Index 	

State Correspondence 	

Calculation of Soil Volumes to be Excavated
Calculation of PCB Soil Cleanup Level . .
Calculation of Adjusted Cost Estimates . .

Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F


-------
ROD DECISION SUMMARY

I.	SITE NAME, LOCATION AND DESCRIPTION

SITE NAME:	Rose Disposal Pit

SITE LOCATION;	Lanesborough, Massachusetts

SITE DESCRIPTION: The Rose Disposal Pit Site (Rose site) is
located on Balance Rock Road in Lanesborough, Massachusetts
approximately four (4) miles north of Pittsfield. The Rose property
was the site of waste oil and solvent disposal from the General
Electric Company (GE) during the 1950's and possibly later. The one
and one-half acre disposal area occupies the northern section of a
14-acre residential lot and was formerly a trench into which the
waste oils and solvents were dumped. The property encompassing the
site is bounded on the north and northeast by the deciduous forest of
Balance Rock State Park, on the east and southeast by cropland and
pasture, on the west by mixed forest, and on the southwest by a
residential area. A small wetland exists west of the disposal area
and a larger forested wetland exists to the southeast of the property
on the southern side of Balance Rock Road. A small man-made pond is
located approximately 200 feet south of the disposal area. The site,
currently owned by Mr. F.T. Rose, is located on a small hill north
of the Rose*s house. The areal extent of the disposal area is
approximately 200 feet by 350 feet and the depth of contaminated
soil varies between 10 and 30 feet.

A more complete description of the site can be found in the Remedial
Investigation Report entitled "1986 Supplementary Investigation at
the Rose Site; February 1987M in Chapter 2 of Volume I. See Figure 1
for a site location map.

II.	SITE HISTORY AND ENFORCEMENT ACTIVITIES

A. Response History

The General Electric Company (GE) has performed the majority of the
technical activities at the site. After the preliminary assessment
(PA), site inspection (SI), and field investigation (FI) were
performed by EPA between 1980 and 1982, all subsequent site
activities have been conducted by GE. Subsequent to EPA's studies,
Geraghty and Miller (G&M) investigated the site further and produced
a Remedial Investigation report (RI) and Blasland &'bouck (B&B)
developed the Feasibility Study (FS) as consultants to GE.

GE provided a permanent potable water supply for the Rose household
in August 1983 by connecting the residence to the Lanesborough
Municipal Water System. In May 1984, EPA issued GE
an Administrative Order under Section 106(a) of the Comprehensive
Environmental Response, Compensation and Liability Act of 1980

1


-------
(CERCLA). In compliance with this Order, GE performed the
following activities in 1984:

secured the disposal area by installing a perimeter fence and
posted signs warning unauthorized persons to keep out;

covered the contaminated soil within the fenced-in disposal
area with a polyethylene film and stabilized this cover against
wind movement;

initiated recovery of a localized free oil layer found beneath
the surface of the disposal area through a recovery well; and

provided the adjacent (Allard) residence west of the site
property with a permanent potable water supply by connection to
the Lanesborough Municipal Water System. The former Balance
Rock Cafe located to the east of the site property also tied in
to the permanent water main provided for the Rose property by
GE.

B. Enforcement History

Three Administrative Orders (A.O.) have been issued to GE for this
site. In May 1984 a Unilateral A.O. was issued to GE by EPA to
conduct the removal activities as outlined in the previous Response
History section. GE performed all activities in compliance with the
A.O.

In November 1984 a Unilateral A.O. was issued to GE by EPA to
conduct a FS for the site. GE subsequently submitted an Initial
Screening of Alternatives and several revisions to this document, in
compliance with the A.O.

In March 1988 an A.O. on Consent was signed by GE and EPA for GE to
conduct a detailed FS for the site. With the passage of SARA,
several modifications to the November 1984 A.O. were needed. The
current A.O. includes several new items:

a schedule for submission of interim deliverables and a
complete detailed FS by 6/30/88;

references to SARA and current OSWER guidance; and

a requirement that GE reimburse EPA for oversight costs.

Other than GE, EPA has not formally notified any parties of
potential responsibility for the Rose site.

GE, as the generator, has been very active at the site. Other than
the preliminary investigations that were conducted by EPA, GE has

2


-------
conducted and financed all removal activities as well as the RI and
the FS for the Rose Site.

Special notice has not been issued in this case to date.

III.	COMMUNITY RELATIONS

Through the Site's history, community involvement has been minimal.
EPA has recently apprised the community and other interested parties
of the Site activities through an informational meeting, fact
sheets, press releases and a public hearing.

In July 1988, EPA released a community relations plan which outlined
a program to address community concerns and keep citizens informed
during remedial activities.

The Agency published a notice and brief analysis of the Proposed
Plan in the Berkshire Eaale on July 18, 1988 and made the plan
available to the public at the Lanesborough Town Library in the Town
Hall.

On July 20, 1988, EPA held an informational meeting to discuss the
results of the Remedial Investigation, the cleanup alterna- tives
presented in the Feasibility Study, and EPA's Proposed Plan. During
this meeting, EPA answered questions from the public. From July 21
to August 19, 1988, EPA held a 30-day public comment period to accept
public comment on the alterna- tives presented in the Feasibility
Study and the Proposed Plan and on any other documents previously
released to the public. On August 3, 1988, EPA held an informal
public hearing to accept any oral comments. A transcript of this
meeting and the comments and EPA's response to comments are included
in the attached responsiveness summary as Appendix A.

IV.	SCOPE AND ROLE OF OPERABLE UNIT OR RESPONSE ACTION

The selected remedy was developed by combining components of a
source control alternative and a control/management of migration
alternative to obtain a comprehensive approach for site remediation.
In summary, the remedy calls for excavation and on-site incineration
of approximately 15,000 yd3 of contaminated soil and sediment. (See
Appendix D for the calculation of the soil volume to be excavated.)
Excavation will extend laterally to remove all contamination down to
13 ppm PCBs, and vertically to the seasonal low watej: table (defined
below) and will include excavation to a deeper level into the water
table to remove the subsurface free product portion (also defined
below) of the disposal area. The remedy also includes active
restoration of the shallow overburden aquifer utilizing air stripping
followed by carbon adsorption for groundwater treatment. A bedrock
well will be installed in the vicinity of the free product area to
prohibit migration into fractured rock.

3


-------
V.

SITE CHARACTERISTICS

The significant findings of the Remedial Investigation are
summarized below.

A.	General

Field investigations conducted in 1981 and 1982 by the Region I
Field Investigation Team (FIT) contractor, Ecology and Environment
(EStE), revealed high concentrations of polychlorinated biphenyls
(PCBs) in surface and subsurface soils and indicated the presence of
volatile organic compounds (VOCs) in groundwater sampled from a
network of wells. Remedial Investigation studies conducted in 1983
and supplemented in 1986 by Geraghty and Miller (G&M), under
contract to General Electric, indicate that contaminated groundwater
is leaving the disposal site in two plumes. One plume is flowing
eastward toward Balance Rock State Park and one is flowing southward
toward Rose's pond. The G&M study also further delineated the extent
and magnitude of PCB contamination. It determined that the highest
concentration of PCBs is located in the primary disposal area. The
G&M study estimated that approximately 60,000 cubic yards of soil
contains greater than 50 ppm of PCBs.

This original estimate of 60,000 yd3 of soil includes soil both
above and below the water table. The water table depth fluctuates
seasonally. EPA estimates the soil volume above the seasonal low
water table to be approximately 8,000 cubic yards. This estimate
is based on the site topography and the depth to the water table as
was measured during the November 1986 sampling round. Appendix D
provides the estimates that were used and includes the calculation of
approximately 3500 cubic yards of material below the water table to
address the free product portion of the site. Since the 11,500 cubic
yard estimate does not include any side slope contingencies for
actual excavation nor the bottom sediments from Rose's pond, 15,000
cubic yards is used as the total soil volume estimate. Refer to
Appendix D for a complete explanation and calculations.

Although high levels of PCB contamination are found throughout the
disposal area, the highest levels of contamination are
generally found directly below the western portion of the
disposal area. An area of "free product" in the saturated zone
exists. This material continues to be recovered from one well
located in the disposal area. This "free product" is a mixture of
oil, water, and solvents. Recent analysis of the mixture shows
350,000 ppm of total PCBs and 57,000 ppm of trichlorpethane
in the oil fraction. GE sends this mixture to their stationary TSCA
incinerator located in Pittsfield for thermal destruction.

B.	Soil

Drilling logs indicate that up to 90 feet of glacial sediment
overlie bedrock on the Rose Site. On the basis of field

4


-------
observations, the majority of this material is described as dense,
basal till. Driving resistances within the basal till were
extremely high (blow counts of 50 to 100 per 1 to 6 inches).

Samples of this till were very tight and dense. Till extended
upward to a depth approximately 15 to 20 feet below the ground
surface. A less compacted mixture of sand, silt, and gravel
overlies the dense till. At the Rose Site, much of this overlying
layer may have been disturbed during disposal operations. A radar
survey indicated that a significant trench up to 25 feet deep may
have once occupied the western portion of the disposal area.
Historical aerial photographs support the existence of a trench. It
is the western portion of the trench that was historically the
deepest and this is the area in which the free product is found.

E&E (1982) analyzed soil samples from the Rose Site to determine the
character of PCB and VOC contamination. Analyses indicate that VOC
contamination is moving with groundwater above or along the upper
surface of the basal till. Some infiltration into the till has
occurred, but data from wells screened at different depths indicate
that this is not a primary route of contaminant transport.

G&M (1983) sampled subsurface soils at over 100 locations to more
accurately determine the extent and severity of PCB contamination.
G&M also sampled groundwater from an expanded network of monitoring
wells for the presence of VOCs (1983 and 1986). Analyses indicate
that the highest concentrations of PCBs and VOCs are still in the
immediate disposal area. There is a localized area of free product
in the western portion of the disposal area that GE continues to
recover through a recovery well. The VOCs, however, are migrating
from the disposal area, presumably contaminating soils below the
water table.

The PCB contamination generally has not migrated from the disposal
area. However, PCB contamination is found in the sediments in Rose
pond (and low levels of PCBs are found in the groundwater taken from
wells near the disposal area). EPA believes that the PCB
contamination in the pond spread from the disposal area by overland
transport via rain and snowmelt prior to the placement of the
synthetic cap over the disposal area in 1984. See Figure 2 for PCB
soil contamination profiles in the disposal area.

Regional mapping and limited on-site information from sample cores
indicate dolomitic marble underlies the Rose site. Bedrock was
encountered by eight borings on or near the site at depths between
34 and 100 feet below the ground surface. Much of the bedrock
recovered during drilling by E&E (1982) was significantly weathered.

C. Groundwater

E&E (1982) installed 8 wells and sampled for priority pollutants.
G&M (1984) conducted a more extensive investigation which included
the installation of 67 wells on or near the Rose property and

5


-------
conducted 3 sampling rounds for VOCs from selected locations. In
1986 G&M provided a supplement to the RI. This update included
sampling 34 wells for VOCs, 3 wells for full hazardous substance
list (HSL) analysis, and sediment and surface water sampling in the
western and southern wetlands and in Rose's pond.

Groundwater flow in the site area is largely controlled by
topography and the vertical and horizontal hydraulic conductivities
of the soil matrix. A groundwater mound is well defined in the area
of the source, with groundwater flowing radially from the source
disposal area. Although downward vertical gradients exist in nested
wells screened at varying depths in the area of the mound,
groundwater quality data indicate the majority of contaminant
transport is restricted to the upper 15 to 20 feet of overburden.
Dense, impermeable till, which is thought to exist at depths
approximately 20 feet below the ground surface appears to restrict
contaminant transport. Groundwater in the shallow overburden flows
radially from the source area, with the Rose pond as a discharge
area. At deeper depths, groundwater is likely to migrate under the
pond, ultimately discharging into the wetland located to the south or
possibly west into the Daniels Brook Basin.

Two plumes of VOCs emanate from the site. One plume flows eastward
toward Balance Rock State Park. The other plume flows southward and
discharges into Rose's Pond which has low levels of VOC
contamination. In addition, low levels of PCBs are present in the
groundwater. See Table 1 for a summary of field investigations and
Figure 3 for well locations and total VOCs in shallow groundwater.

The groundwater contamination is concentrated in shallow
overburden soils and does not pose a threat to the municipal
wells located approximately two miles east of the site.

Specific information on residential wells within one-half
mile of the site is not available, but records for other
wells in the area and discussions with a local well driller
suggest that all private wells obtain water from the bedrock
aquifer.

A complete discussion of site characteristics can be found in the
Remedial Investigation Reports.

VI.	SUMMARY OF SITE RISKS AND CLEANUP GOALS

A. GE's Endangerment Assessment

GE performed an Endangerment Assessment (EA) to estimate the
probability and magnitude of potential adverse human health and
environmental effects from exposure to contaminants associated with
the site. Seven (7) contaminants of concern, listed in Table 2, were
selected for evaluation in the EA. These contaminants constitute a
representative subset of the more than nineteen (19) contaminants
identified at the Site during the Remedial Investigation. The 7

6


-------
contaminants were selected to represent potential on-site hazards
based on toxicity, level of contamination, and mobility and
persistence in the environment.

Potential human health effects associated with the contaminants of
concern in soils and groundwater were estimated quantitatively
through the development of several hypothetical exposure scenarios.
Incremental lifetime cancer risks and the potential for
noncarcinogenic adverse health effects were estimated for the
various exposure scenarios. Exposure scenarios were developed to
reflect the potential for exposure to hazardous substances based on
the characteristic uses and location of the site. Factors of
special note that are reflected in GE's Endangerment Assessment are
that although the site area is residential, GE treats it as a rural
area without a large amount of pedestrian traffic on the property.

GE's EA examined potential risks to public health and the
environment posed by the presence of PCBs in soil as well as VOCs in
groundwater at the site. The study found that dermal contact with
and ingestion of PCB-contaminated soil in the disposal area poses an
unacceptable lifetime maximum cancer risk of approximately 6.9 X 10"" 2
and a lifetime average cancer risk of 2.6 X 10--3. GE's calculations
assumed a PCB cancer potency factor of 4.34 (mg/kg/day)-1 and a
"lifetime" exposure of 52 years. GE assumed 36 visits per year. The
cancer potency factor that is now used by EPA is 7.7 (mg/kg/day)"1
which would increase the above risk numbers.

The CPF used by GE was formerly used by EPA, but the Agency has
revised the factor based on the results of studies on the cancer-
causing potential of PCBs, reflecting the Agency's conclusion that
the cancer-causing potential is greater than previously believed.
EPA's Drinking Water Quality Criteria Document for PCBs sets forth
the data which supports this factor. Even using the CPF used by GE,
the risks posed are unacceptable.

According to GE's calculations, ingestion of contaminated
groundwater in the vicinity of the disposal area poses an
unacceptable lifetime average cancer risk of 1.4 X 10~2. This
vicinity also has a hazard index for non-carcinogenic effects of
greater than 1.0. GE's EA also found that VOCs in Rose's pond
present an unacceptable lifetime cancer risk of 7.3 X 10"4 to
animals with a hazard index of 1.8 for potential non-carcinogenic
effects.

The fencing and temporary cover on the site temporarily reduce the
risk posed to humans and to animals by contact with soils in the
disposal area. No contaminated shallow groundwater'is presently
used as a drinking water supply since municipal water was extended
to the immediate area in 1984. However, there is residential use of
groundwater within one-quarter mile of the site and groundwater
contamination is migrating off-site.

7


-------
Table 3 presents a summary of potential exposure routes and Table 4
is a summary of potential human and animal health risks for the
corresponding potential exposure routes and are taken from GE's EA.
A complete discussion of site risks can be found in the End&ngerment
Assessment.

B.	EPA PCB Soil Cleanup Level

PCBs are the most significant component of soil contamination at the
Rose site. A PCB soil clean-up level is developed using exposure
scenarios based on potential human exposures to contaminated soils by
direct contact and ingestion. The exposure scenarios reflect
hypothetical future site use. That is, they represent the level of
soil cleanup that would be acceptable without the need for long term
management of contamination at the site.

The assumptions that were used by GE have been revised by EPA to
develop the site-specific cleanup goal. At this site the zoning is
residential and the use of the area is residential. Although the
area is not densely populated at present, EPA expects that
residential and recreational use of the area will grow in the
future. See Appendix E for the assumptions used by EPA in the
calculation of the 13 ppm PCB cleanup goal.

The source management component of the selected remedial action
entails excavation and treatment of soils contaminated with PCBs at a
concentration of 13 ppm or greater located in the unsaturated zone.
This clean-up level corresponds to a 10-5 risk level for the average
case under future site use conditions. EPA is establishing the
clean-up goal for PCBs in the unsaturated zone. However, the area
containing free product in the western portion of the saturated zone
will also be excavated to facilitate groundwater cleanup. During the
excavation and treatment of soil, air quality will be monitored to
ensure that site specific ambient.action levels are not exceeded.

In applying this approach to estimate health-based soil clean-up
levels, it is important to recognize the inherent uncertainties.
Uncertainties are associated with the value of each exposure
parameter and the overall set of exposure assumptions. EPA believes
that the assumptions used to estimate the cleanup level are
reasonable, and that it is necessary to use this approach, in spite
of its uncertainties, in order to assure that the cleanup goals will
be adequately protective of public health. See Appendix E for EPA's
calculation and references for the PCB soil cleanup level.

C.	EPA Groundwater Cleanup Goals

VOCs are the most significant component of groundwater contamination
at the Rose Site. Groundwater cleanup goals for certain contaminants
have been set at or below U.S. EPA Maximum Contaminant Levels (MCLs),
where available. These contaminants include: vinyl chloride; 1,1-
dichloroethylene; trichloroethylene; benzene; and p-dichlorobenzene.

8


-------
For compounds without MCLs, EPA's proposed Maximum Contaminant Level
Goals (MCLGs) have been used to define groundwater cleanup goals for
the following contaminants: t-l,2-dichloroethylene; o-
dichlorobenzene; ethylbenzene; toluene; and xylenes. For
chlorobenzene, the Lifetime Health Advisory (LHA) of 300 ppb is used
which reflects the current data being considered by the Agency. For
m-dichlorobenzene, the LHA of 620 ppb is the cleanup goal. The
proposed MCLG for PCBs and tetrachloroethylene is zero (0), which is
not considered to be technically measurable.

The cleanup goals for methylene chloride, tetrachloroethylene, and
1,1,2-trichloroethane are set at 5, 1, and 1 ppb respectively,
corresponding to a 10~6 cancer risk, assuming lifetime exposure.

Based on EPA's 1987 Drinking Water Criteria for PCBs, the health-
based cleanup level is 0.005 ppb which corresponds to a 10~6 cancer
risk.

It is likely that the groundwater treatment system for the Hose Site
will be able to reduce groundwater contaminant concentrations to
levels lower than the cleanup goals. Groundwater treatability tests
were conducted by GE for the Hose site in November 1987. Effluent
concentrations from two air stripper tests were lower than the
groundwater cleanup goals for 11 of the 16 contaminants listed in
Table 5. These results were for a single air stripper with a 10-foot
packing height. In the full-scale groundwater treatment system,
packing height will be increased to increase collection efficiency.
In addition, the air stripper will be followed by two granular
activated carbon (GAC) beds in series to remove contaminants passing
through the air stripper. As a result, the effluent concentrations
are anticipated to be lower for the full-scale air stripper-GAC
system than for the treatability test.

Refer to Table 5 for a summary listing of potential contaminant-
specific ARARs, guidelines, and cleanup goals for groundwater.

VII.	DOCUMENTATION OF SIGNIFICANT CHANGES

EPA issued a Proposed Plan (preferred alternative) for remediation
of the site in July 1988. The source management portion of the
preferred alternative included excavation and on-site incineration
of soils in the disposal area both above and below the seasonal low
water table. The management of migration portion of the preferred
alternative included groundwater treatment by air stripping followed
by carbon absorption. All costs and soil volumes were taken directly
from GE's draft FS and were not modified.

The proposed plan did not specify the PCB cleanup goal and
approximated the extent of excavation required. The ROD defines
these. The ROD sets a PCB cleanup goal of 13 ppm for PCBs above the
seasonal low water table. Extensive soil borings which were
analyzed for PCBs (data presented in the 1984 RI report) in and

9


-------
around the disposal indicate that there is not a significant
difference between the extent in areas contaminated to the 13 ppm
and 50 ppm levels. Therefore, the areal extent of contamination is
assumed to be approximately equal to the portion of the disposal area
that is fenced and covered (see Appendix D).

Rose's pond shows PCB contamination in the sediments that exceed 13
ppm (one sample taken from the pond bottom contained 65 ppm of
PCBs). Rose's pond will be drained and the water will be treated by
the groundwater treatment system if this surface water does not meet
the groundwater cleanup goals. Once the pond is drained, the bottom
sediments will be excavated for treatment and it will be backfilled
to restore the area to its original (wetland) condition.

Extent of PCB Removal

The depth to the water table varies across the disposal area. EPA
estimates the volume of soil above the water table to be excavated is
8,000 yd3. In addition to soils in the unsaturated zone, the free
product area in the western portion of the saturated zone will also
be excavated and is estimated to be 3,500 yd3 of saturated soil. A
total soil volume of approximately 15,000 yd3 (which includes side
slopes) will be excavated. See Appendix D for calculation of the
soil volumes to be excavated.

Actual soil volumes will be determined during remedial design,
particularly the extent of the free product area. If this free
product area is found to extend beyond the area originally assumed,
additional saturated soil may need to be removed.

Another change from the proposed plan concerns the approach taken to
PCBs in the groundwater in the disposal area. Both PCBs and VOCs are
found at high concentrations in the saturated zone in the disposal
area. Each class of chemicals has distinct characteristics. VOCs
are highly soluble in groundwater, whereas PCBs are of extremely low
insolubility and have a tendency to adsorb onto soils. Although PCBs
may desorb from saturated zone soils and solubilize in groundwater,
PCBs have a chemical tendency to adsorb onto the next available and
less contaminated soil particle since the soil-water partitioning
coefficient for PCBs favors soils. The solubility of PCBs is
enhanced, however, in the presence of VOCs and appears to increase as
the concentration of VOCs increase. Although significant
concentrations of PCBs will remain in the saturated zone, VOCs will
be reduced by the groundwater treatment system. This reduction of
VOC levels will reduce the solubility and mobility of PCBs in the
groundwater.

Nevertheless, PCBs will still be present at low concentrations in
the groundwater in the disposal area and are assumed to be in excess
of the 0.005 ppb health-based level for a 10~6 cancer risk for PCBs.
However, if the VOCs in groundwater are remediated to the cleanup

10


-------
goals, the PCBs remaining in the saturated zone following remediation
in effect will not migrate.

In order to attain a PCB level of 0.005 ppb in groundwater within
the disposal area, essentially all PCBs in the saturated zone would
need to be excavated. This would require the excavation and
treatment of approximately an additional 45,000 cubic yards (and
possibly more) of PCB contaminated soil in the saturated zone.
Excavation to achieve the groundwater PCB goal in the saturated
zone would be technically difficult, costly, and for all practical
purposes, infeasible. In addition, a large dewatering effort could
potentially have unacceptable impacts on the adjacent wetland by
significant lowering of the water table. In light of these
implementation problems, EPA has determined that it is technically
impracticable and not cost-effective to remediate the PCBs that
will remain below the water table in the disposal area. Instead,
to achieve a protective remedy in the disposal area, EPA has
concluded that dermal exposure and ingestion of PCBs in the
saturated zone can and will have to be prevented through capping
of the disposal area and institutional controls.

In addition, because PCBs will still be present in groundwater
within the disposal area in excess of the cleanup goal,
institutional controls will be required for this area to prevent
ingestion of groundwater. However, for the reasons
stated above, EPA has determined that this remedy will be
protective.

VIII.	DEVELOPMENT AND SCREENING OF ALTERNATIVES

A. Statutory Requirements/Response Objectives

Prior to the passage of the Superfund Amendments and
Reauthorization Act of 1986 (SARA), actions taken in response to
releases of hazardous substances were conducted in accordance with
CERCLA as enacted in 1980 and the revised National Oil and
Hazardous Substances Pollution Contingency Plan (NCP), 40 CFR Part
300/ dated November 20, 1985. Until the NCP is revised to reflect
SARA, the procedures and standards for responding to releases of
hazardous substances, pollutants and contaminants shall be in
accordance with Section 121 of CERCLA and to the maximum extent
practicable, the current NCP.

«

Under its legal authorities, EPA's primary responsibility at
Superfund sites is to undertake remedial actions that are
protective of human health and the environment. In addition,
Section 121 of CERCLA establishes several other statutory
requirements and preferences, including: a requirement that EPA's
remedial action, when complete, must comply with applicable or
relevant and appropriate environmental standards established under
federal and state environmental laws unless a statutory waiver is

11


-------
granted; a requirement that EPA select a remedial action that is
cost-effective and that utilizes permanent solutions and
alternative treatment technologies or resource recovery
technologies to the maximum extent practicable; and a statutory
preference for remedies that permanently and significantly reduce
the volume, toxicity or mobility of hazardous wastes over remedies
that do not achieve such results through treatment. Response
alternatives were developed to be consistent with these
Congressional mandates.

A number of potential exposure pathways were analyzed for risk and
threats to public health and the environment in the Endangerment
Assessment and the Wetlands Assessment (Appendix A of the FS).
Guidelines in the Superfund Public Health Evaluation Manual (EPA,
1986) regarding development of design goals and risk analyses for
remedial alternatives were used to assist in the development of
response actions. As a result of these assessments, remedial
response objectives were developed to mitigate existing and future
threats to public health and the environment. These response
objectives are:

prevent exposure to contaminated soils and groundwater

protect uncontaminated groundwater and surface water for
current and future use

restore contaminated soils and groundwater for future
use

B. Technology and Alternative Development and
Screening

CERCLA, the NCP, and EPA guidance documents including, "Guidance
on Feasibility Studies Under CERCLA" dated June 1985, and the
"Interim Guidance on Superfund Selection of Remedy" [EPA Office of
Solid Waste and Emergency Response (OSWER)], Directive No.

9355.0-19 (December 24, 1986) set forth the process by which
remedial actions are evaluated and selected. In accordance with
these requirements and guidance documents, treatment alternatives
were developed for the site. These alternatives range from an
alternative that, to the degree possible, would eliminate the need
for long-term management (including monitoring) at the site, to
alternatives involving treatment that would reduce the mobility,
toxicity, or volume of the hazardous substances as their principal
element. In addition to the range of treatment alternatives, a
containment option involving little or no treatment and a no-action
alternative were developed in accordance with Section 121 of
CERCLA.

Section 121(b)(1) of CERCLA presents several factors that at a
minimum EPA is required to consider in its assessment of

12


-------
alternatives. In addition to these factors and the other
statutory directives of Section 121, the evaluation and selection
process was guided by the EPA document "Additional Interim .
Guidance for FY '87 Records of Decision" dated July 24, 1987.

This document provides direction on the consideration of SARA
cleanup standards and sets forth nine factors that EPA should
consider in its evaluation and selection of remedial actions. The

nine

factors are:



1.

Compliance with Applicable or Relevant
Requirements (ARARs).

and Appropriate

2.

Long term Effectiveness and Permanence.



3.

Reduction of Toxicity, Mobility or Volume.

4.

Short term Effectiveness.



5.

Implementabi1ity.



6.

Community Acceptance.



7.

State Acceptance.



8.

Cost.



9.

Overall Protection of Human Health and

the Environment

The Initial Screening of Alternatives Report identified, assessed
and screened technologies based on engineering feasibility,
implementability, effectiveness, and technical reliability.

These technologies were combined into source control (SH for
••source management") and control/management of migration (GW for
"groundwater") alternatives. Section 5 of the Feasibility Study
presented the remedial alternatives developed by combining the
technologies identified in the previous screening process in the
categories required by OSWER Directive No. 9355.0-19. The purpose
of the initial screening was to narrow the number of potential
remedial actions for further detailed analysis while preserving a
range of options. Each alternative was then evaluated and screened
in the initial screening report. In summary, of the over 100
original source management technologies and management of migration
technologies screened in the initial report, 10 source management
options and 4 groundwater options were retained for 'detailed
analysis. Table 6 identifies the alternatives that were retained
through the screening process. The initial screening report lists
those alternatives that were eliminated from further consideration.

13


-------
IX.	DESCRIPTION/SUMMARY OF THE DETAILED AND COMPARATIVE

ANALYSIS OF ALTERNATIVES

This section presents a narrative summary and brief evaluation of
each alternative according to the evaluation criteria described
above. A detailed assessment of each alternative can be found in
Section 6 of the Feasibility Study.

A. Source Management (SM) Alternatives Analyzed

The source management alternatives analyzed for the site include a
no action alternative (SM-O), as well as 10 other alternatives.
For alternatives where soil volume is a cost consideration,
estimates of costs are lower than those in the draft FS. which are
based on the original soil volume estimate of 60,000 yd3. Actual
soil excavation will be limited to approximately 15,000 yd3 and
corresponding volume-sensitive cost estimates are lower. Since the
cost estimates in the draft FS were not specific enough to allow
for calculation of exact values, it was assumed that for purposes
of comparison of the alternatives, the relative cost reductions of
the different alternatives are essentially the same. Pro-rated
cost estimates are included here based on the unit costs that were
provided in the draft FS, to the extent possible. See Appendix F
for calculation of these adjusted cost estimates.

SM-0

No Action

This alternative for soil contamination is included in the FS to
serve as a basis for comparison with the other remedial
alternatives considered. A no action alternative is selected only
if the site poses little or no risk to public health and the
environment. For the Rose site, the no action alternative would
entail leaving contaminants untreated on site, maintaining the
existing synthetic cover and fence, continuing the ongoing program
to recover the product layer located beneath the disposal site, and
monitoring surface and groundwater for 30 years.

The no action alternative would not provide overall protection of
human health and the environment, and it would not comply with
ARARs. It is not a permanent remedy that would have long term
effectiveness since it would not reduce the toxicity or mobility
of the contaminants. This alternative would require, a 5-year
review since contaminants would remain on-site.

Estimated Time for Construction and Operation: Minimum of 30 Years
Estimated Capital Cost: $0

Estimated Present Worth of Operation and Maintenance Costs:

$210,000

Estimated Total Cost: $210,000

14


-------
SM-1

In-Situ Containment vith Impermeable Cap and Barriers

"In-situ" refers to a technique the occurs "in place" without
excavating the disposal area. This alternative would require the
construction of an upgraded cap of synthetic material to cover the
1.5-acre site. Capping helps minimize the movement of
contaminants by reducing the amount of precipitation (i.e., rain
and snow melt) that could filter through the wastes and allow
contaminants to migrate from the site. In addition, this
alternative would require construction of a groundwater cutoff
wall to limit groundwater from coming in contact with contaminated
soils. Construction of the cutoff wall would entail digging a
trench around the entire disposal area and creating a wall of
impermeable material inside the trench.

Capping is a widely-used technique that reduces the mobility of
contaminants, but it does not reduce toxicity or volume. Because
capping would contain the contamination untreated on site, future
site use would have to be restricted. Capping does not meet the
statutory preference for a permanent remedy. This alternative
would require a 5-year review since contaminants would remain on-
site.

Estimated Time for Construction: 13-18 months

Estimated Period of Operation: 30-year lifetime for cover and

cutoff wall

Estimated Capital Cost: $710,000

Estimated Present Worth of Operation and Maintenance Costs:
$200,000

Estimated Total Cost: $910,000
SM-2

In-Situ Soil Flushing with fal Incineration or (b) Biodeqradation
of Recovered Liquids

This alternative would involve pumping a solvent or surfactant
solution through the contaminated soil. As the solution
percolates through the ground, PCBs and VOCs are released from the
soil and carried with the solution to a groundwater collection
system that would be installed surrounding the site. Once the
groundwater is collected, the chemical solution and contaminants
would be extracted from the water and then either (ij incinerated
at an approved hazardous waste incinerator, or (2) treated by
biodegradation. EPA does not consider this alternative to be a
feasible project for the Rose site because of the low soil
permeabilities for in-situ application and the long time frame
required for development. GE states that a 4 to 6 year period is
required to develop the process prior to any design or
implementation activities.

15


-------
Short tern impacts would be minimal since no excavation would be
required, and long term environmental or health impacts were not
determined in the draft FS. This alternative has been tested on
an experimental level only; extensive additional laboratory and
on-site testing would be required to determine the cost, cleanup
duration and overall effectiveness of this technology. EPA
concludes that this alternative does not meet the criteria for
implementability and effectiveness.

Estimated time for Construction and Operation: Undetermined
Estimated Total Cost: Undetermined

SM-3

KOHPEG Dechlorination

This alternative consists of excavating contaminated soil and
sediments and mixing them in a stainless steel chamber with a
combination of chemicals forming a reagent, KOHPEG, capable of
destroying PCBs. The mixture is heated (to approximately 150*C)
to increase the rate of destruction of PCBs, and to drive off
VOCs in the soil. The VOC vapor is then captured with carbon
filters. Decontaminated soils would be replaced on site.

KOHPEG dechlorination would provide long term protection of public
health and the environment, compliance with ARARs, and would reduce
the toxicity, mobility and volume of site contamination
permanently. Implementation of KOHPEG dechlorination would require
construction of a mobile treatment unit. This alternative would
require the use of engineering controls to prevent the emission of
contaminants during the excavation of contaminated soil and
sediments and during the actual treatment process. The
implementability and effectiveness of this technology at full-scale
is unproven at this time.

Estimated Time for Construction: Uncertain
Estimated Period of Operation: 2 years
Estimated Total Cost: $4,000,000 - $7,200,000

SM-4

On-Site Incineration

This alternative has been chosen as the remedy for the site.

Please see Section X for details.

SM-5

Off-Site Incineration

16


-------
Under this alternative, contaminated soil and sediments would be
excavated and transported to an off-site hazardous waste
incinerator. Several incinerators currently licensed to received
PCB-contaminated wastes include: Calumet, Illinois; El Dorado,
Arkansas; and Deer Park, Texas. Similar incineratipn and
pollution control processes that are used off-site would be used
at an on-site incinerator. The GE incinerator in Pittsfield is
licensed to receive PCB-contaminated liquid wastes only and cannot
be used to destroy PCB-contaminated soil from the Rose site.

While off-site incineration would remove the risk of contamina-
tion at the site, permanently destroy the contaminants, and would
meet ARARs, this alternative would present increased risk to human
health and the environment through increased traffic and off-site
shipment of contaminated wastes. These impacts will not occur with
on-site incineration. This alternative also would require
engineering solutions to prevent the emission of contaminants
during excavation and transportation of contaminated soil and
sediments over long distances.

It is possible that the limited capacity and high demand for the
existing off-site incinerators could result in a longer-term
operation than would on-site incineration. Costs associated with
this alternative would be much higher due to both transportation
and off-site charges. Therefore, EPA concludes that this
alternative is less cost effective than on-site incineration.

Estimated Period of Operation: 2 years
Estimated Total Cost: $44,000,000

SM-6

On-site Disposal in an Approved Hazardous Waste Landfill

This alternative would require construction of a federally-
approved TSCA hazardous waste landfill on the Rose property. The
landfill would include a synthetic liner as well as a leachate
collection system to prevent potentially contaminated liquids from
migrating from the area. Contaminated soil and sediments would be
excavated and placed in the landfill. Groundwater monitoring would
be conducted to ensure the integrity of the landfill and leachate
collection system.

Landfilling is a proven technique for containing PCBs and other
hazardous wastes. Although mobility of the wastes is reduced,
landfilling does not reduce the toxicity or volume of the wastes.
Also, should the disposal facility fail, this alternative would
present a risk to public health and the environment. This al-
ternative, therefore, would not provide long-term effectiveness
nor meet the statutory preference for a permanent remedy. TSCA
regulation 761.75(b)(3) requires that the bottom of a landfill be
at least 50 feet above the groundwater table. This requirement

17


-------
could not be met at the Rose site, therefore, it would not provide
compliance with ARARs. This alternative also would require
engineering solutions to prevent the emission of contaminants
during excavation of contaminated soil and sediments and during
placement of the contaminated material into the landfill.

Estimated Time for Construction: 2 years
Estimated Time of Operation: 30 years
Estimated Capital Cost: $3,450,000

Estimated Present Worth of Operation and Maintenance Costs:
$255,000

Estimated Total Cost: $3,700,000
SM-7

Off-Site Disposal in an Approved Landfill

This alternative would involve excavating contaminated soil and
sediments, reducing the moisture content, and disposing of the
waste at an approved off-site TSCA hazardous waste landfill.

There are currently several facilities in the United States
approved for disposal of PCB-contaminated wastes including: Model
City, NY; Niagara Falls, NY; Cincinnati, OH; Emelle, AL; Deer
Park, TX; and Grassy Mountain, UT. After the contaminants are
removed, clean soil would be hauled in to fill in the excavated
areas.

Off-site disposal removes the risk of contamination at the site.
However, since contaminants remain untreated, it is not a
permanent remedy. In addition, off-site disposal of untreated
wastes is the least favored alternative under CERCLA. This
alternative would present a risk to public health and the
environment due to increased traffic and off-site shipment of
contaminated wastes, or if the off-site disposal facility were to
fail. Off-site disposal would not provide long term
effectiveness. This alternative would require engineering
solutions to prevent the emission of contaminants during
excavation and transportation of contaminated soil and sediments
to the off-site facility.

Estimated Time for Removal: 2 years
Estimated Total Cost: $7,000,000

SM-8

# *

Chemical Fixation/Stabilization of Excavated Wastes

This alternative involves a process in which contaminated soil and
sediments would be excavated and mixed with a material such as
cement, flyash, or various polymers to bind or "fix" the
contaminants into a solid material. After stabilization of the

18


-------
soil and sediments, the material would be used to regrade the
site.

This alternative has the potential to greatly reduce the mobility
of the contaminants (with resultant increase in volume),
minimizing long term environmental effects. The toxicity,
however, would not be affected and the stabilized material would
still be a hazardous substance since the contaminants would not be
destroyed.

A number of stabilization technologies for soils with varying
levels of organic contamination are currently under development
under EPA's Superfund Innovative Technology Evaluation (SITE)
program. (Descriptions of these development programs and the EPA
SITE program are included in the Administrative Record and are
discussed in Response 24 of the responsiveness summary.) On the
basis of the information that is currently available, EPA is
unable to determine that this alternative would satisfy the
statutory preference for a permanent remedy since the
effectiveness of stabilization has not been demonstrated for the
levels and type of contamination found at the Rose site. For
these reasons, EPA finds that stabilization does not meet the
criteria of implementability and long term effectiveness for the
Rose site.

This alternative would require engineering solutions to prevent
the emission of contaminants during excavation and treatment of
contaminated soil and sediments. In addition, air emissions of
the fixed material may be of concern and would require monitoring.
This alternative would require a 5-year review since contaminants
would remain on-site.

Estimated Period of Operation: 2 years
Estimated Total Cost: $3,000,000

SM-9

Chemical Extraction with Incineration of Recovered Liquids fSoil
Washing)

This alternative is similar to alternative SM-2 in that
contaminants are extracted chemically from the soil and sediments.
In this alternative, however, excavation would be required prior to
treatment. Excavated materials are mixed in a chamber with
acetone, a solvent that releases PCBs and VOCs from the soil.

Steam is then injected into the system, separating the
acetone/contaminant mixture from the soil. At this point, the
cleaned soil is returned to the site. The acetone/contaminant
water mixture is then combined with kerosene, which draws the VOCs
and most of the PCBs out of the acetone and water. Contaminated
kerosene is removed from the site and incinerated. The
acetone/water mixture remains in the system and is distilled to

19


-------
recycle the acetone for reuse in the treatment process. All vapor
emissions would be treated prior to release to the atmosphere.

This alternative may be used in combination with selected remedy to
enhance the efficiency of the incineration process.

This alternative has been proven effective in laboratory testing.
Field testing would be required to determine the cost,
implementability, and short and long term effectiveness at the
Rose Site. GE's consultants estimate that testing and development
of the full-scale treatment system would take 3 to 5 years. It
would need to be demonstrated that ARARs and long term environ-
mental and public health protection would be met by this
alternative. This alternative would require engineering solutions
to prevent the emission of contaminants during excavation and
treatment of contaminated soil and sediments. Additional
precautions for handling kerosene and acetone, both of which are
flammable, also would be required. EPA may give this alternative
further consideration as a demonstration project.

Estimated Time for Construction and Operation: Undetermined
Estimated Total Cost: Undetermined

SM-10

On-Site Biodecrradation

A biodegradation process uses naturally-occurring or laboratory-
tailored bacteria to degrade, or break down, organic compounds
such as PCBs and VOCs into harmless materials such as carbon
dioxide, water, and humus. In essence, this alternative is a
specialized form of composting. While biodegradation has been
shown to be effective treating other types of hazardous waste, the
effectiveness and implementability of this alternative for
destruction of PCBs at the Rose site has not been demonstrated.

This alternative has not been retained by EPA for further
consideration for a demonstration project because long times
frames are anticipated in GE's research and development program
that would be applicable at the Rose site.

This alternative has been tested on an experimental level;
additional laboratory and on-site testing would be required to
determine the cost, cleanup duration, and short and long term
effectiveness of this technology at the Rose site. This
alternative also would require engineering solutions to prevent
the emission of contaminants during excavation and treatment of
contaminated soil and sediments. Because the effectiveness has
not been demonstrated, EPA cannot determine that this alternative
would destroy contaminants, meet ARARs, or satisfy the other
selection criteria.

Estimated Time for Operation: Undetermined
Estimated Total Cost: Undetermined

20


-------
B. Management of Migration (GW) Alternatives Analyzed

Management of migration alternatives address contaminants that
have migrated from the original source of contamination. At the
Rose site, VOC contaminants (and PCBs to a lesser extent) have
migrated from the disposal area, predominantly via groundwater.
The management of migration alternatives evaluated for the Site
include a minimal no action with monitoring alternative (see
Alternative SM-O), as well as 4 other groundwater alternatives.

Massachusetts DEQE has stated that it will require Best Available
Control Technology (BACT) on the air stripper as a new source,
regardless of the size of the (new) groundwater treatment
equipment, based on 310 CMR 7.00. Therefore, a carbon filter will
have to be placed on the air stripper. This addition adds to both
the capital and operating and maintenance costs that the draft FS
estimated for any alternative which includes an air stripper (GW-l
and GW-lA).

The estimated time for construction and operation is stated as 10
years, the estimate used in the draft FS. The 10-year period was
an estimate only to provide a basis for cost comparison of the
various GW alternatives. It should be noted, however, that the
actual time required for groundwater treatment to meet the cleanup
goals is directly related to removal/treatment of the source area
and particularly the free product which exists in the saturated
zone. EPA estimates that if no action is taken to remediate the
source area than the groundwater treatment system would have to
operate indefinitely.

GW-l

Air Stripping/Carbon Treatment

This alternative has been chosen as the groundwater remedy for the
site; see Section X for details.

GW-lA

Air Stripping/Carbon Treatment with Hydrogen Peroxide Pretreatment

This alternative would utilize the same process as alternative GW-l
with the addition of hydrogen peroxide (H2(>2) pretreatment. In
this process, extracted groundwater would be mixed with H202 and
then passed through a sand filter. Use of this pretireatment
process would remove approximately 75% of the VOCs in the
groundwater rather than depending predominantly on the air
stripper for VOC removal. After pretreatment, groundwater would
follow the same treatment path described in alternative GW-l in
Section X. Spent carbon would be handled in a manner similar to
that as described in alternative GW-l in Section X.

21


-------
Air stripping is a proven technology for the removal of volatile
organic compounds of the types that have been found at the Rose
site. Air stripping with pretreatment has been used successfully
at several hazardous waste sites. This technology would provide
overall long term effectiveness and compliance with ARARs. It
would provide permanent reduction in the site contamination.

Short term effects, such as air emissions, could be minimized
through engineering controls. Spent carbon would be handled in a
manner similar to that described for GW-1.

This technology, although considered to be comparable to GW-1 in
cost and effectiveness, could be more difficult to implement due
to the additional step required. In addition, the cost estimate
for GW-1 is considered to be the most accurate; see the discussion
in Appendix F on this issue.

Estimated Time for Construction and Operation: 10 years
Estimated Capital Cost: $503,000

Estimated Present Worth of Operation and Maintenance Costs:
$615,000

Estimated Total Cost: $1,118,000
GW-2

Ultraviolet Light - Ozonation with Hydrogen Peroxide Pretreatment

This alternative would consist of the same pretreatment process
described in alternative GW-la. Following both H202 pretreatment
and filtering through sand beds, the groundwater would be treated
with ozone in the presence of ultraviolet (UV) light to destroy
PCBs and any remaining VOCs. Because ozone is a highly reactive
gas and toxic in high concentrations, any off-gases from the
process would be passed through an ozone decomposer to change the
ozone into oxygen prior to release.

UV-Ozonation is a relatively new technology, but has been proven
effective in treating hazardous wastes containing VOCs and PCBs.
This technology is currently a demonstration project under the EPA
SITE program. This technology would comply with ARARs, and it
would have long term effectiveness and provide a permanent
reduction in site contamination. Short term effects could be
minimized through engineering controls. This technology would
potentially be more difficult to implement than GW-1 due to its
stage of development.

Estimated Time for Construction and Operation: 10 years
Estimated Capital Cost: $585,000

Estimated Present Worth of Operation and Maintenance Costs:
$560,000

Estimated Total Cost: $1,145,000

22


-------
GW-3

Carbon Treatment with Hvdroaen Peroxide Pretre?<~™«>"<'

This alternative also would utilize the same hydrogen peroxide
pretreatment as in alternatives GW-1A and GW-2. H2O2 pretreatment
would be utilized to remove 80% to 90% of the VOCs. Carbon
filtering would then be utilized to remove the PCBs and the
remaining VOCs. Spent carbon would be handled in a manner similar
to that as described in alternative GW-1 in Section X.

Additional testing would be required to prove the effectiveness of
hydrogen peroxide in removing high levels of VOCs, and its ability
to meet ARARs, prior to construction of the treatment facility.

This alternative would reduce the volume, toxicity, and mobility of
the contaminants permanently and would utilize engineering controls
to minimize short term impacts.

Estimated Time for Construction and Operation: 10 years
Estimated Capital Cost: $370,000

Estimated Present Worth of Operation and Maintenance Costs:

$880,000

Estimate Total Cost: $1,250,000

X.	THE SELECTED REMEDY

The selected remedy is comprehensive since it includes both a
source management and a management of migration component.

A. Description of the Selected Remedy

After evaluating all of the feasible alternatives, EPA is
selecting a two-part.cleanup plan to address soil and groundwater
contamination at the Rose site.

1.	Air stripping and carbon treatment is selected to prevent
the spread of contamination through the groundwater and to restore
contaminated groundwater. The Rose Pond would be drained and the
water treated in the same manner if the levels continue to exceed
the groundwater cleanup goals.

2.	On-site incineration is the selected alternative for
addressing soil and sediment contamination.

In an effort to encourage development of alternative technologies
for treatment of hazardous waste, however, EPA is considering
allowing GE to conduct a demonstration project for application at
the site during the design of the on-site incinerator. This
alternative is chemical extraction with incineration of extracted
liquids (SM-9). This alternative would be considered for use if it
is demonstrated to meet the criteria for evaluation for remedy

23


-------
selection. If the alternative is not proven to be effective by the
end of the incinerator design phase, construction and operation of
the incinerator would begin immediately upon completion of design.
This demonstration project would be conducted in parallel with the
remedial design for the on-site incinerator.

To minimize further spread of contaminants from the disposal area,
EPA is requiring that groundwater treatment begin immediately and
continue until the groundwater cleanup goals are achieved.

Recovery of the subsurface free product will continue. This
oil/water/solvent mixture will continue to be shipped off-site for
thermal destruction at an approved TSCA incineration facility.

B. Rationale for Selection/Points of Compliance

The rationale for choosing the selected alternative is based on
the assessment of each criteria listed in the evaluation of
alternatives section of this document. In accordance with Section
121 of CERCLA, to be considered as a candidate for selection in the
ROD, the alternative must have been found to be protective of human
health and the environment and able to attain ARARs unless a waiver
is granted. In assessing the alternatives that met these statutory
requirements, EPA focused on the other evaluation criteria,
including short term effectiveness, long term effectiveness,
implementability, use of treatment to permanently reduce the
mobility, toxicity and volume, and cost.

EPA has determined that incineration is the only available
technology which satisfies all of these criteria, particularly
permanence, and that on-site incineration is more cost effective
than off-site incineration for the Rose site. Additionally, the
short term impacts associated with off-site incineration of
increased truck traffic and the transportation of contaminated
materials untreated over long distances are considered to be less
acceptable than the construction impacts associated with on-site
incineration. Further, many of the potential source remedies were
not considered by EPA to be implementable because the technology
has not yet been developed. In addition, the groundwater treatment
is deemed necessary to comply with EPA's Groundwater Protection
Strategy and the RCRA Subpart F and G requirements.

EPA also considered nontechnical factors that affect the
implementability of a remedy, such as state and community
acceptance. Based upon this assessment, taking into.account the
statutory preferences of CERCLA, EPA selected the remedial
approach for the Site.

1. Source Management

The source management portion of the remedial action is designed
to permanently destroy the source area soil and sediment
contamination.

24


-------
Under this alternative, contaminated soil and sediments will be
excavated and then burned in a transportable thermal destruction
facility that will be set up at the site. Three different types
of incinerators were evaluated: rotary kiln, circulating fluid-
ized bed, and infrared processing. The extremely high tempera-
tures in any of these thermal destruction facilities would destroy
virtually all of the organic contaminants. The TSCA regulations
require that the destruction and removal efficiency of PCBs by
incineration be 99.9999% and the ash (decontaminated soil) must
contain less than 2 ppm PCBs. Exhaust gases will be passed through
air pollution control devices before being released into the
atmosphere. All soil will be tested to ensure that the PCB cleanup
goals have been met and that acceptable levels of metals are
present. Decontaminated soil will be replaced on site.

On-site incineration will provide long term protection of human
health and the environment. Organic contamination is destroyed;
no mobility, toxicity, or volume concerns remain, so that the
remedy will comply with ARARs. This alternative is a proven
technology and it will require engineering controls to prevent the
emission of contaminants during excavation of contaminated soil and
sediments and during actual thermal treatment, to minimize short
term impacts and to meet site specific air quality ambient action
and emissions limits. These controls will be developed during the
design process.

On-site incineration will utilize a transportable (mobile) unit.
Such systems are commercially available at the present time. It
should be noted, however, that full scale operation of these
transportable units has been limited, and periods of downtime have
been experienced.

The extent of excavation will be to the seasonal low water table
for the majority of the disposal area. EPA has determined that
extensive dewatering would not be practicable at this site for the
reasons explained in Section VII of this ROD and is not necessary
to be protective since PCBs will be effectively immobilized by
groundwater treatment. Of equal importance, the potential impacts
on the nearby wetland from a large dewatering effort which could
lower the water table significantly are unacceptable.

Deeper excavation will be required only in the free product area
that is believed to be localized. Since the time fpr groundwater
treatment is directly dependent upon the volume of the source
area, this source area will be removed and treated.

The deep saturated soils which will remain on site contain PCBs up
to a maximum of approximately 5000 ppm. Leaving these soils in
place will require imposition of institutional controls for the
disposal area to prevent groundwater use and excavation in the

25


-------
saturated zone. In addition, capping the site will prevent any
direct contact with the remaining PCBs in the saturated zone.

Potential waste streams that will be generated by the incineration
process requiring disposal include material collected by the air
pollution control device(s). This material will need to be
disposed of in accordance with the land disposal ban and all other
applicable requirements.

Estimated Time for Construction and Operation: 2 years
Estimated Capital Cost: $208,400

Estimated Present Worth of Operation and Maintenance Cost:
$5,000,000

Estimated Total Cost: $5,200,000

Zj. Management of Migration

The management of migration portion of the remedial action is
designed primarily to treat contaminated groundwater that is
migrating from the site.

EPA will address groundwater contamination at the Rose site by
utilizing a combination of air stripping and carbon treatment.
The treatment system will entail construction of trenches or wells
to collect shallow groundwater from the 2 plumes of contamination.
In addition, a well will be installed in bedrock in the vicinity of
the free product area to prohibit migration into fractured rock.
Collected groundwater will be pumped to an air stripping tower. As
air is forced up through the tower, VOCs are removed from the
groundwater into the air stream. This air stream containing VOCs
is passed through an activated carbon filter to remove contaminants
before being released into the atmosphere.

Following air stripping, the groundwater will be passed through
activated carbon filter beds to remove PCBs and any residual
contaminants. Treated water will then be discharged into an area
where it will be returned to the aquifer. Water from the Rose's
pond will be treated in the same manner, if necessary, after being
pumped from the pond.

Air stripping is a proven technology for removing volatile organic
compounds of the type that have been found at the site. EPA has
used air stripping and carbon treatment successfully at numerous
hazardous waste sites. This technology will provide'overall
protection of human health and the environment and compliance with
ARARs. It will provide permanent reduction in the site
contamination and will provide long term effectiveness. Short term
effects can be minimized through engineering controls, such as the
use of carbon filters. EPA believes that air stripping followed by
carbon treatment is the easiest management of migration alternative
to implement.

26


-------
The draft FS did not include the costs of a carbon filter on the
air stripper. Because Massachusetts DEQE requires Best Available
Control Technology (BACT) for all new sources, EPA has estimated
the additional costs of a carbon filter and has added them here.
See Appendix F for these cost calculations.

Spent carbon will be generated from the (used) carbon filters.
These spent filters will be disposed of either by manufacturer
regeneration, incineration, or an alternative disposal method
which will comply with the land disposal ban and the RCRA
regulations.

Estimated Time for Construction and Operation: 10 years
Estimated Capital Cost: $466,000

Estimated Present Worth of Operation and Maintenance Costs:
$790,000

Estimated Total Cost: $1,256,000

XI.	STATUTORY DETERMINATIONS

The remedial action selected for implementation at the Rose site
is consistent with CERCLA and, to the extent practicable, the NCP.
The selected remedy is protective of human health and the
environment, attains ARARs and is cost effective. The selected
remedy also satisfies the statutory preference for a permanent
solution and for treatment which reduces the mobility, toxicity or
volume as a principal element. Additionally, the selected remedy
utilizes alternate treatment technologies to the maximum extent
practicable.

A. The Selected Remedy is Protective of Human Health and
the Environment

The remedy at this site will permanently reduce the risks
presently posed to human health and the environment by:

preventing exposure to contaminated soils by excavation
and incineration of the contaminated soils above the
water table;

protecting uncontaminated groundwater and 'surface water
for current and future use by intercepting and treating
contaminated groundwater and by removing the free
product layer below the water table, thereby eliminating
the source for potential future contamination; and

restoring contaminated groundwater for potential future
use and elimination of this source of contamination of

27


-------
Rose's pond and surrounding wetland areas, thereby
removing the threat to wildlife.

B. The Selected Remedy Attains ARARs

This remedy will meet or attain all applicable or relevant and
appropriate federal and state requirements that apply to the site.
Federal environmental laws which are applicable or relevant and ap-
propriate to the selected remedial action at the Rose site are:

Resource Conservation and Recovery Act (RCRA)

Clean Water Act (CWA)

Safe Drinking Water Act (SDWA)

Executive Order 11990 (Protection of Wetlands)

Toxic Substances Control Act (TSCA)

Clean Air Act (CAA)

Occupational Safety and Health Act (OSHA)

Table 8 lists potential action-specific State ARARs and presents a
brief synopsis of the requirements. Note that via the state
programs authorization process, Massachusetts' hazardous waste
regulations under Chapter 21C are essentially equivalent to the
federal counterpart found at 40 CFR Subpart F (releases from solid
waste management units, including groundwater monitoring
requirements) and Subpart G (closure and post-closure).

Table 5 lists the chemical-specific ARARs for groundwater. Table
7 lists potential action-specific Federal ARARs. A brief
narrative summary of the ARARs follows.

The Resource Conservation and Recovery Act (RCRA) closure
regulations require closure by removal of waste, waste residues
and contaminated subsoils which is equivalent to closure as a
surface impoundment or waste pile (40 CFR 264 Subpart K and L); or
closure as a landfill by capping and appropriate post-closure care
(40 CFR 264 Subpart N). The selected remedy for the Rose site
attains the general RCRA closure performance standards as specified
in 40 CFR § 264.111:

The owner or operator must close the facility in a manner that:

(a)	Minimizes the need for further maintenance;

#

(b)	Controls, minimizes or eliminates, to the extent
necessary to protect human health and the environment,
post-closure escape of hazardous waste, hazardous
constituents, leachate, contaminated run-off, or
hazardous waste decomposition products to the ground or
surface waters or to the atmosphere; and

28


-------
(c) Complies with the closure requirements of Subpart G
including, but not limited to, the requirements of §§
264.178, 264.197, 264.228, 264.258, 264.280, 264.310 and
264.351.

Excavation and treatment of PCB-contaminated soils above 13 ppm
above the water table will result in the removal of a large
portion of wastes and waste residues and it will eliminate the
direct contact threat from those contaminants, as well as their
contribution to groundwater contamination. The management of
migration groundwater treatment option will minimize and eliminate
to the extent necessary the migration of contaminants from the
site. The restriction of on-site groundwater use, in conjunction
with the RCRA closure and post-closure requirements in §§ 264.115,
264.116, 264.117, 264.119 and 264.120, will provide the necessary
long term protection for public health and the environment.

Regarding management of migration measures, the specific relevant
Federal regulations are the RCRA Releases from Solid Waste
Management Units, including the groundwater monitoring
requirements (40 CFR 264 Subpart F), the Clean Water Act (40 CFR
Part 122) and the Safe Drinking Water Act (40 CFR 141 Subpart B).
The groundwater protection regulations require the setting of
groundwater protection standards which must be protective of
public health and the environment. The groundwater cleanup goals
were set at MCLs, proposed MCLGs, LHAs, or site-specific levels
that EPA has determined will adequately protect public health at a
lifetime cancer risk of 10~6 (see Section VI).

A groundwater monitoring system will be implemented consistent
with 40 CFR § 264.100(d) to determine the effectiveness of the
groundwater remediation system.

The remediation of groundwater is consistent with the U.S. EPA
Groundwater Protection Strategy (August 1984) which classifies the
aquifer at the Rose site as Class IIA (current usage) and requires
the restoration of these aquifers.

The Safe Drinking Water Act (SDWA) is only applicable to public
drinking water supplies (i.e. a water supply serving 25 or more
people). However, EPA considers the MCLs established under the
SDWA to be relevant and appropriate. Table 5 lists the relevant
MCLs for the Rose site. EPA finds that it is technically
infeasible to reduce PCB levels in groundwater within the 1.5-
acre disposal area to the 0.005 ppb health-based level and
institutional controls will be required for the disposal area.

This is discussed in Section VI and VII of this ROD.

The remedy will comply with Executive Order 11990 - Protection of
Wetlands, the Clean Water Act § 404(b)(1) guidelines and the State
Wetland Protection Act (310 CMR 10.00). Rose's pond is an
artificial pond that was excavated by a previous landowner to

29


-------
drain the surrounding wetland area. The pond has been affected by
the site and it will be affected by the remedy. Because the pond
water exceeds the groundwater cleanup goals, it will be necessary
to drain and treat this water. Because the pond bottom sediments
exhibit PCB levels in excess of the PCB cleanup goal, these
sediments will be excavated for thermal treatment. EPA finds that
there is no practicable alternative to these actions since it is
the pond itself that is contaminated. Implementation of the remedy
will utilize measures to restore the pond to its original wetlands
character after remediation and to minimize any harm to the
surrounding wetlands. In addition, the operation of the
groundwater treatment system is intended to prevent contamination
from the shallow aquifer from impacting the wetlands, and this
system will operated to minimize any impacts on the surrounding
areas.

Under TSCA, soils contaminated with PCBs at concentrations greater
than 50 ppm that are disposed of after February 17, 1978 must be
disposed of in accordance with 40 CFR 761 Subpart D. Since
incineration is selected as the source treatment technology,
treatment and disposal of the 15,000 cubic yards of the PCB-
contaminated waste will be in accordance with the criteria of 40
CFR 761.70.

The 50 ppm TSCA regulatory threshold referred to in GE's draft
Feasibility Study is not a cleanup standard. The establishment of
this regulatory limit was based on economic and administrative
considerations as well as human health and the environment. As
such, on a site-specific basis, it does not necessarily achieve the
objective of Section 121 of CERCLA. In this case, EPA developed a
site-specific health-based cleanup standard for PCBs based upon a
risk assessment that considered future use of the Rose site.

The TSCA PCB Spill Cleanup Policy (TSCA Section 761.120 Subpart G;
April 2, 1987) provides cleanup guidelines based on access to the
site that were considered in determining the site-specific cleanup
level. The PCB cleanup level of 13 ppm for the Rose site is
considered to be consistent with the cleanup guideline of 10 ppm
suggested in this policy.

During the excavation and treatment of PCB and VOC-contaminated
soils, and during the groundwater treatment, air emissions will be
monitored and all relevant Federal and State standards will be
attained. Specifically, the National Ambient Air Quality
Standards (NAAQS) will be met through specified techniques for
excavation activities, as well as required air monitoring for the
incinerator and during excavation, to ensure that site-specific
ambient action levels are not exceeded.

During the excavation and treatment of contaminated soils and
during groundwater treatment, OSHA regulations will be followed.
In particular, 29 CFR 1910.120 specifies standards for handling

30


-------
hazardous wastes and 29 CFR 1910.1000 sets allowable ambient air
concentrations for activities which involve release of VOCs in the
workplace. Techniques such as limiting the extent of excavation,
use of suppressant foams, and use of air purifying and filtering
devices will be utilized to provide compliance not only with OSHA
regulations but also any federal and state air quality standards.

C. The Selected Remedial Action is Cost Effective

Once EPA has identified alternatives that are protective and
attain ARARs, EPA analyzes those alternatives to determine a cost-
efficient means of achieving the cleanup.

The estimated cost of on-site incineration may be somewhat higher
than several of the other source management alternatives.

However, EPA believes that the remedy is cost effective due to the
fact that only incineration will permanently destroy the organic
contamination at the site. Future remedial action with associated
costs may be needed if wastes are left on site. When comparing
equivalently protective alternatives that provide permanent
remedies, KOHPEG and on-site incineration were considered to have
approximately the same cost. However, because of the lack of full-
scale implementability of the KOHPEG process, EPA considers
incineration to be preferable for the Rose site.

The actual costs for on-site incineration are difficult to
estimate precisely. However, the $380 per cubic yard estimate for
on-site incineration is well within the range provided by guidance
and vendor quotes. EPA believes that the remedial on-site
treatment market is becoming more competitive. The cost of
remedial services may decline due to factors such as increased
market competition, more efficient design and operation of
treatment equipment, improved materials handling capability, and
increased availability of equipment and treatment capacity.

The costs for GW-1 and GW-1A are considered to be approximately
the same due to the level of detail in the estimates (+50/-30%)
for feasibility studies. Further, the cost estimate for
alternative GW-1 is considered to be the most accurate. GW-l
technology has been implemented full-scale at several Superfund
sites, while the other GW alternatives have not been used as
extensively. See Appendix F for further discussion of the accuracy
of the GW cost estimates.

The addition of the GAC filter on the air stripper increased both
the capital and O&M costs for the GW-l and GW-1A alternatives. The
design of the actual groundwater treatment system will determine if
a pretreatment phase is desirable to reduce the O&H costs. See
Appendix F for calculation of the adjusted cost estimates.

31


-------
D. The Selected Remedy Utilizes Permanent Solutions and

Alternative Treatment Technologies or Resource Recovery
Technologies to the Maximum Extent Practicable

Incineration is an alternative treatment technology that will
provide a permanent solution to the PCB problem at the site.
Excavation of the PCB-contaminated soils in the unsaturated zone
to 13 ppm and treatment by incineration will reduce the risks
posed to human health from direct contact with on-site soils by
virtual complete destruction of the organic contaminants, as well
as elimination of the potential risk of release of PCBs from this
zone into groundwater. This soil treatment process will also
provide the added benefit of treating a large quantity of VOCs in
the unsaturated zone, thus assisting in the cleanup of
groundwater. In addition, eliminating a significant source of
contamination to the groundwater by removal of the free product
below the water table will substantially reduce the time required
to meet the groundwater treatment goals.

Treatment of the groundwater will permanently and significantly
reduce the volume, toxicity and mobility of the volatile organics
as well as reduce the mobility of the PCBs present in the
saturated zone soil matrix. Restoration of the aquifer will
permit the groundwater beyond the disposal area to be used for
drinking water purposes in the future. However, EPA will require
that institutional controls restricting groundwater use be
implemented for the disposal area.

Further, restoration of the groundwater will eliminate the threat
posed to public health and the environment from the current and
future extent of contaminant migration in groundwater and surface
water.

E. The Selected Remedy Satisfies the Preference for
Treatment as a Principal Element

The principal element of the selected remedy is the excavation and
on-site incineration of contaminated soil and sediments. This
element addresses the threat at the site of contamination of soil
and sediments with PCBs and VOCs. The selected remedy also
satisfies the statutory preference for treatment as a principle
element by requiring groundwater treatment.

However, some PCB contamination will remain in the saturated zone.
Only the VOC contamination in this zone will be treated to
immobilize the PCBs. The basis for this is discussed previously
in Section X.

32


-------
XII.	STATE ROLE

In accordance with CERCLA Section 121(f)(1)(E) and (G), EPA has
provided the Commonwealth of Massachusetts' Department of
Environmental Quality Engineering a reasonable opportunity to
review and comment on the Remedial Investigation, the Endangerment
Assessment, and the Feasibility Study. EPA has also provided
notice to the State and an opportunity to comment on the Proposed
Plan for remedial action at the Site. A copy of the State's
correspondence is attached as Appendix C.

33


-------
FIGURE 1

SITE LOCATION MAP


-------
J

O II6i\

SgP^ROSE PROPERTY -s
BOUNDARY

U-

¦]: \ '	/ "C ?!

xik's'B'0 K'yi g

Xj . -I ) A\ r w>rp r1-	^

\/' -"I i. ' L '\,v: ^ A|
V \i i ^ f^9b"topivc Lafc* *«*#•- •*

S"-^'1 . OO '¦(/• (	"~V' Counfrv Cub* 'tor ** */

X'r

^V;

J::', P

SCALE .miles

Vij^

quadrangle location


-------
FIGURE 2

PCB SOIL CONTAMINATION PROFILES IN THE
DISPOSAL AREA


-------
I

I

to.';
ton.
IX?
IOO*
too*
toool-
•>*

¦

986 "
H&t -

SV*0 IOJ

0 ">9
OOll
: 6

<0.05
0 15

HORIZONTAL SCALf |":40
VERTICAL SCALE i" = IS'
VERTICAL EXAGGERATION' J.I.

JS <	BORING NUM BE R

«	LANO SURFACE

MOO*	CONCENTRATION OF TOTAL

A ROCLORSlPARTS *>ER MILLION!

	LINE of EOUAL CONCENTRATION

(PARTS PER MILLION)

Horth-south cross-section through the disposal pit.


-------
I

I

WEST -

iiMOr
lOM> ¦

- lOSjf-

. i
fe<

Z twe-

J

2

' 
o

3 <017 f-

2	'«**-

Ik

S	ioo4-

2	iooc -
>

H	1H

•M

W*1-

hOOIZONTAL SCAlC'I'KO'
veimcAL JC4te »"»»3*
VtWTlCAL tXAGCC*ATK>« • S.I ¦

East-west cross-section through the disposal pit (page 1).


-------
I

1040

1036

1032 f-

J 1028
>

IO
.J

<

W
tn

z 1020

<
w

>	I0t6

U*

>

2 »0t2

CO
4

•" 100*1
w

1024 -

1004

1000

> 996

992

968

W
O
4

a
a

?

3
Z

~-
X

o

o

964

EAST

•9 »

120

2.8
10

-1000^ «j/

•200 '

- —

3.9

2.3

190

30j

0.02
~

1.9

EX P|. ANATIQn

36 BORING NUMBER

LAND SURFACE

2600 CONCENTRATION 0*
TOTAL AROCIORS
I PARTS PER MILLION I

/

— LINE or EQUAL CONCENTRATION

(PARTS PER MILLION)

East-west cross-section through the disposal pit (page 2).


-------
FIGURE 3

WELL LOCATIONS AND TOTAL VOCs
IN SHALLOW GROUNDWATER


-------
(

DALANCE ROCK STATE PARK

o	100 rr.

*PPf»OX. SCALE

SW-B

290-83	:

BASED ON I9B6 DATA
SOURCE: REFERENCE 6

LEGEND:

MARSH

•	i LOCATION OF MONITOR WELL

. LOCATION OF SURFACE WATER

•	STATION

5 CONCENTRATION OF TOTAL VOi
IN MICROGRAMS PER LITER

100v LINE OF EQUAL CONCENTRATIO
\ IN MICROGRAMS PER LITER

GENERAL ELECTRIC COMPANY
ROSE SITE

TOTAL VOCs IN
SHALLOW GROUNDWATER
(A WELLS)


-------
TABLE 1

SUMMARY OF FIELD INVESTIGATIONS


-------
EPA/DEQE/ECE

CE/CtM

TOTAL

\ssessment of Soils

1. Soil Borings

a.	Number of Borings

b.	Linear footage of borings

c.	Number of analyses

See Monitoring Wells
See Monitoring Wells
102 (from monitoring
well boreholes)

Misc. Soil Samples

a.	Pond Sediment (Adjacent Site)

b.	Garden Soils (Adjacent Site)

c.	Surface Soils (At Site)

d.	Swamp/brook soils (Adjacent Site)

0
0
3
6

3. Geophysical Surveys
A. Dates of Investigations

Ground Probing Radar
8/80-9/82

110
1132 ft.
311

7
5
0
2

Magnetometer
1/82-7/83

no

1132 ft.
D13

7
5
3

8

Assessment of Ground Water

1.	Monitoring Wells

a.	Number of Wells

b.	Linear footage of wells

2.	Ground-Water Level Monitoring

Ground-Water Level Monitoring
a. Number of Analyses

il. Drinking Water Monitoring
a. Number of Analysis

5." Dates of Investigations

8 wells
362 feet

67 wells
1835 ft.

3 Rounds (8 Wells) 3 Rounds (67 Wells)

23
12

11/81-4/82

160

3/83-8/83
11/86-12/86

75 wells
2197 ft.

183

15

Assessment of Surface Water

1.	Number of Analyses

2.	Dates of Investigations

7

3/81

12
11/86

19

3/88


-------
TABLE 2

SITE CONTAMINANTS AND CONTAMINANTS OF CONCERN


-------
Site Contaminants and Contaminants of Concern



Site Contaminants

Contaminants of Concern;





Indicator ComDounds



A. Volatile Oraanics

•

1.

vinyl chloride

1. vinyl chloride

2.

methylene chloride

2. t-1,2-dichloroethylene

3.

1,1-dichloroethylene

3. trichloroethylene

4.

t-1,2-dichloroethylene

4. tetrachloroethylene

5.

trichloroethylene

5. toluene

6.

benzene

6. ethylbenzene

7.

1,1,2-trichloroethane

7. PCBs

8.

tetrachloroethylene



9.

toluene



10.

chlorbenzene



11.

ethylbenzene



12.

xylenes



13.

dichlorobenzenes





B. Semi-Volatile Oraanics



1.

1,2-dichlorobenzene



2.

1,3-dichlorobenzene



3.

1,4-dichlorobenzene



4.

2,4-dimethylphenol



5.

1,2,4-trichlorobenzene



C. PCBs


-------
TABLE 3

SUMMARY OF POTENTIAL EXPOSURE ROUTES


-------










Future Probability







Current

of Exposure

Route of

Physical and Chemical



Receptor

Probability

Without Remedial

Exposure

Features \
. -<•"	\

Environmental

Population

of Exposure

Action

£

&

zr

5*
2

3

n

Dermal contact
with soil within
the disposal area.

Dermal contact
with soil outside
the disposal area.

Dermal contact
with Rose Pond
sediments.

Dermal contact
with surface
water in the
Rose Pond.

Dermal contact
with stream
surface waters.

Dermal contact
with ground water.

Inhalation of
fugitive dust.

PCBs an adsorbed strongly
to soil particles. VOCs
exhibit limited capacity
to adsorb to soil.

PCBs strongly adsorb to -
soil particles. WCs
adsorb less strongly and
were not reported in soil
samples.	'

PCBs strongly adsorb to
Rose Pond sediments. VOCs
will generally remain
mobile in an aquecxis
system.

PCBs have limited
solubility in water.

VOCs ware detected in
surface-water sanples.

VOCs were detected at
lew concentrations.

PCBs are not easily
mobilized in ground
water. VOCs may be
transported via
ground water to shallow
water-supply wells.

The protective plastic
cover at the disposal site
and the surrounding trees
and vegetation do not
promote the generation of
fugitive dust.

Area within the disposal	The disposal area is near

site is covered with	approximately 30 hones

plastic* and the perimeter	although no evidence of

has warning signs and	trespass is evident,
fencing.

Dermal oontact outside
the disposal area Is
limited by the vegetative
cover. Surrounding area
is not secured to prevent
hunan and animal traffic.

Hading in the Rose Pond
could result in exposure .
to the stream sediments.

The pond is accessible
to local residents. ,

The stream is accessible
to local residents.

Ground water is used in
eight households within a
1/4-mlle radius of the
site. Residential supply
wells are located in the
unaffected deeper aquifer.
All other wells are on
municipal supply.

The site is accessible to
pedestrian traffic from
the nearby residential
area.

Residents near the
disposal area, visitors
to the state park, and
gardeners on the Rose
property represent
potential receptors.

Local residents who
use the Rose Pond for
recreation.

Exposure to local residents
could occur for brief
intervals (total body
imnersion) and.longer periods

for hand and/or foot contact.

/ ¦*.

> \

Exposure to local residents

could occur f<3c bcief ¦

periods oE'tlme ovdc small

portIons of fche body.

Local residents or private
ground-water supply wells
for bathing facilities.

Absent

Moderate

Lew to
moderate

Moderate

Low

Low

Low

Absent

Moderate

Moderate

Moderate

Low



v

The receptor population is
anticipated to be amall-to-
absent as evidenced by Its
obscure location.

Absent

Low


-------
Route of
Exposure

Physical artd chemical
Feature*

Environmental

Receptor
Population

Current
Probability
of Exposure

Future Probability

of Exposure
Without Remedial
Action

f?

£

=r

<3
2

Inhalation of

organic

chemicals.

Ingestion of soil
within the
disposal area.

Periodic olfactory A
detection of organic}
vapors has been
recorded.

PCBs are strongly adsorbed
to soil particles.

Air monitoring results
suggest the presence of
organic vapors.

Dm disposal area is
'fenced, and circum-
stances at the disposal
area do hot encourage
plcnibs or opportunities

hand-to-mouth transfer
Events.

Local residents that	low

live near the site.

Nearby receptor populations Lew
would not use this area
for food consumption or
recreational purposes.

Moderate

Lw

3

o

Ingestion of soil
outside the
disposal area.

PCBs are strongly adsorbed
to soil particles.

Ingestion of
ground water.

Ingestion of fish.

PCBs in ground water have
not been detected 1,000 ft
beyond the disposal area.
\TOC contamination is
limited to the surficial
aquifer.

PCBs are accumulated in
stream sediment. Bio-
concentration and
biomagnification is
possible. Fish greater
than sifc inches in length
have not been seen in the
pond.

Gardening could result
In the accidental ingest-
ion of raw, partially
cleaned vegetables (e.g.,
carrots).

The surficial aquifer is
not used for residential >
water supplies. Extension
of the municipal water
supply to area hemes has
limited private well use.

Analytical results shew
that PCB transport via
sediments does not extend
beyond the Balance Rock
Road culvert. Extensive
distribution of PCBs beyond
this point is unlikely.

The receptor population	lew	Moderate

most likely to consume
vegetables grown In con-
taminated soils at the site
is the Rose family. PCB
sdil contamination beyond
property boundary has not
.been demonstrated.

/

( Ground-water supply wells	Absent	Low

used by local residents
located outsidd.the
disposal afea and within
the Rose property. \

s\ \

**	'N	V-1'

The Rose rondisrot	Absent	Absent*

fished local residents*

/


-------










Future Probability









Current

of Exposure

ftxite of

Physical and Chemical



Receptor

Probability

Without Remedial

Exposure

Featured.

Environmental

Population

of Exposure

Action









Ingestion of
agricultural
products.

PCBs strongly Adsorb,to
soil particles and 1
express limited mobility
In ground wat6r. /

Ingestion of game
and danestic food
animals.

The probability that PCBs
will be Introduced to the
agricultural field is low
since ground water is
not used to irrigate
and PCB-contam 1nated
adils are almost
ccrpletely bound to the
/ disposal site.

PCBs are strongly bio-"' Jtii cohered disposal site
accumulated from sed intents offers little benefit for

grazing, .brtvsing, or
i protective cover for
wildlife.

Corn, the predominant crop	Absent

in the agricultural field,
has an adventitious root
system not suited to inter-
cepting the ground-water
table.

The game, birds, and deer	Lew

hunted at the site are not
expected to have accumulated
significant quantities of PCB
or VOC contaminants.

Absent

Low


-------
TABLE 4

POTENTIAL EXPOSURE ROUTES WITH
POTENTIAL HUMAN HEALTH RISKS


-------
I

Route of Exposure

Disposal Area

Adult

Cancer Risk

	amr

Hazard Index
Adult	Child

s?

&

rr

fr
2

Dermal Contact/
Ingestion: Soil

Inhalation: Air
Total

6.9 x 1Q ,(Ml
2.6 x 10 (A)

1.6 x 10"?(M)
6.1 x 10 (A)

2.9 x 10

-11

5.1 x 10""

6.9 x 10 ,(M) 1.6 x 10 f(M)
2.6 X 10 (A) 6.1 x 10 (A)

4.7 x lof(M)

1.7	X 10 (A)

8.8	x 10"'

4.7 x lof(M)
1.7 X 10 (A)

1.4 x 10 (A)

1.7 x 10

,-2

3.7 x 10,(RT
1.4 x 10(A)

3

r>

Rose Garden

Dermal Contact/
Ingestion! Soil
Tbtal

6.9 x

579x

10
Iff

-7

7-

9.5 x 10'
4.3 x 16

7.2 x 10"2	x 1Q-1

7.2 x 101.6 x 10 1

Rose Pond

(PoodSedlmenta)
Dermal

3.1 x 10~Z(M) 4.3 x 10~Z(M)
7.8 x 10 (A) 1.1 x 10 (A)

5.0 x 10-}(M) 4.6 x 10_}(M)
1.3 x 10 (A) 1.2 x 10 (A)

Pond Surface Hater

Dermal Contact/
Ingestion: Hater

2.3 x

ID"10

2.3

X

io-6

4.0

X

1(T5

.4.3

X

10-1

Inhalation: Air

2.9 x

ioi

9.4

X

10~c

3.4

X

10"i

3.7

X

10"L_

Tbtal

3.4 x
1.1 x

• r-
o ©

r-4 f-i

2.7
2.4

X
X

10 ®(M)
10 (A)

5.0
1.3

X
X

10 }(H)
10 (A)

9.0
6.0

X
X

10 }(M)
10 A(A)

Stream

Dermal Contacti
Hater

Inhalation:'Air

(pond)

Tbtal

3.1 x 10"2(M) 4.2 x 10™Z(M)
7.8 x 10 (A) 1.1 x 10 (A)

2.9 x 10

-8

9.4 x 10

.-7,

„-7.

3.3 x 10 4(H) 4.2 x 10 1(M)
1.7 x 10 (A) 1.1 x 10 (A)

5.0

X

10""* (M)

1.3

X

10 (A)

3.4

X

10~3





10~*(M)

5.0

X

1.3

X

10 V)

3.7 x 10

,-3


-------
(continued)

~	"	Cancer Risk	Hazard Index"

Route of Exposure	Adult	"	Adult

Ground water

Ingestion	¦»

Area 1	2.3 »	8.7 * 10 ,

Area 2	7.0 x l(f,	1.1 x 10

Area 3	1.4 It 10,	1.2 .

Area 4	. .6.6 x 10~?	3.2 x 10 ,

Area 5		3.7 x 1P~"	, 1.2 x 10 _

Range	2.3 to 3.7 x 10 .	8.7 x 10 to 1.1 x 10

(M) Kaxlnun Reported Concentration
(A) Average Reported Concentration


-------
Geraghty & Miller, Inc.

Animal Health Risk Sunmary

Route of Exposure	Cancer Risk	Hazard Index

Rose Pond
Ingestion: Water

Stream
Ingestion: water

7.3 x 10

-4

1.4 x 10

-4

1.8

3.8 x 10

-1

658/37


-------
TABLE 5

POTENTIAL CHEMICAL-SPECIFIC ARARs, GUIDELINES
AND CLEANUP GOALS FOR GROUNDWATER


-------
TABLE 5

SUMMARY OF POTENTIAL GROUNDWATER ARAR'S, GUIDELINES, AND CLEANUP GOALS

(in parts ber billion)

ARARs

Other Guidelines/Criteria

Compound

MCL



AWQC

Proposed
MCLG

LHA(l)

RSD

Carcinogen
Class (2)

Proposed
Cleanup
Goal







Asute

Chronic











A.

Wlatile Organics

















1.

vinyl choride

2

-

—

-

-

-

A

2

2.

methylene chloride

-

-

-

-

-

4.6

B2

5

3.

1,1-dichloroethylene

7

11,600

-

-

-

0.06

C

7

4.

t-1,2-d ichloroethylene

-

11,600

-

70

70

-

-

70

5.

tr ichloroethylene

5

45,000

21,900

—

-

3.1

B2

5

6.

benzene

5

5,300

-

—

-

1.2

A

5

7.

1,1,2-trichloroethane

-

-

9,400

-

-

0.63

C

0.63

8.

tetrachloroethylene

-

5,280

840

0

-

0.67

C

0.67

9.

toluene

-

17,500

-

2000

2420

-

-

2000

10.

chlorobenzene

-

-

-

60

300

-

-

300

11.

ethylbenzene

-

32,000

-

680

680

-

-

680

12.

xylenes

-

-

-

440

440

-

-

440

13.

dichlorobenzenes:



















o-DCB

-

-

-

620

620

-

-

620



p-DCB

75

1,120

760

-

75

-

-

75



m-DCB









620





620

B.

PCBs



2

.0 0.014

0



0.005

B2

0.005


-------
Abbreviations:

ARAR = Applicable or Relevant and Appropriate Requirement
MCL = Maximum Cbntaminant level

AWQC = Ambient Water Quality Criteria (for Aquatic Species)

MCLG = Maximum Cbntaminant Level Ctoal
LHA = Lifetime Health Mvisory

RSD = Risk-Specific Dose; based on 10-6 risk for all carcinogens

Notes;

(1)	Lifetime Health Advisories are values established by the U.S. EPA office of Drinking Water in Health
Advisories issued March 31, 1987.

(2)	Carcinogen classes established by EPA: A = human carcinogen; B2 = probable hunan carcinogen;
C = possible human carcinogen.


-------
TABLE 6

SUMMARY OF REMEDIAL ALTERNATIVES


-------
I

SOURCE MANAGEMENT REMEOIAL ALTERNATIVES:
SUMMARY OF FEASIBILITY STUDY RANK INC

SM-1
SM-2

SM-3
SM-«i
SM-5
SM-6
SM-7
SM-8
SM-9

SM-10

Remedial Alternative
(In conjunction with
ground-water treatment)	

No Action

Containment (cap A cutoff wall)
In-situ Soil Flushinq

(2)

with leachate Treatment

KOIIPEG Dechlorination

On-Site Incineration

Off-Site Incineration

On-Site Landfill

Off-Site Landfill

Chemical Fixation/lnmobi1ization

Chemical Extraction with Incin-

(2)

eration of Recovered Liquids

On-Site Biodeqradation
(landfarming)	'

Technical
Feasi bi1i ty
Ranking	

high

high

requi res
Field Study

moderate

moderate

1 ow

high

high

moderate

requi res
Field Study

requi res
Field Study

Institutional
Ranking	

1 ow

low

high

high

moderate

moderate

low - moderate

low

high

high

high

Publi c
Health and
Envi ronmental
Ranking	

low/moderate

moderate

high

moderate-high

moderate

moderate

moderate

moderate

high

high

high

Estimated Costs
(Present Worth)

$210,000

$910,000

to be defined
by Field Study

$16-30 mi 11 ion

$ 19.2 Million

$ H8 Million

$ H.1 Million

$ 25.6 Mi 11 ion

$ 11.2 Million

to be defined
by Field Study

to be defined
by Field Study'

(1)

Constructic
or 0AM
Duration ^

30 years

30 years

to be defii
by Field 5'

5-9 years

5+ years

6 years

30 years

years

years

to be defi
by Field 5

to be defi
by Field 5

Notes:

(1)	Present worth costs are for duration indicated. Interest Rate of 10% assumed.

(2)

Requires implementation of Interim remedial measures.

^ of soil; see Appendix"? ^adjusted cosTestimates!1911131 estimate of 60,000 cubic yards


-------
I

GROUND WATER REMEDIAL ALTERNATIVES:
SUMMARY OF FEASIBILITY STUDY RANK INC

CW-1

GW-tA

Remedial Alternative
(in conjunction with
source management)	

Air stripping followed
by carbon absorption

Hydrogen peroxide
pretreatment, filtration
air stripping, and
carbon absorption

Technical
Feasibi1i ty
Ranking	

high

high

Institutional
Ranking	

high

high

Public
Health and
Envi ronmcntal
Ranking	

high

high

Present
Worth

Costs

(1)

$ 770,000 *
$ 875,000 *

GW-2

Hydrogen peroxide
pretreatment, filtration
and UV-Oionation

moderate-high

high

high

SI ,1<*5,000

GW-3

Hydrogen peroxide
pretreatment, filtration,
and carbon absorption

moderate-high

high

high

51,250,000

Notes:

(1) Based on 10 years of operation and maintenance, 10^ discount factor.

jjt The costs for Orf-1 and CW-1A do not include emission control costs-
see Appendix F for adjusted cost estimates.

6/8


-------
TABLE 7

POTENTIAL ACTION-SPECIFIC ARARs; FEDERAL


-------
I

FEDERAL

APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
(ARARS)

REGULATIONS
1. Mater Quality Regulations

(a)	*0 CFR 10%, Regulations on Public
Hearings on Effluent Standards for
Toxic Pollutants

(b)	SO CFR 116, Regulations on
Designation of Hazardous Sub-
stances

(c)	*0 CFR 122, National Pollutant
Discharge Elimination System
Permit Regulations

(d)	*0 CFR 125, Regulations on
Criteria and Standards for the
National Pollutant Discharge
Elimination System

(e)	*0 CFR 129, Toxic Pollutant
Effluent Standards

(f) SO CFR 1*1 and 1*2, National
Primary Drinking Hater Stand-
ards

(g) Ambient Water Quality Criteria

2. Solid and Hazardous Waste Regulations

(a)	*0 CFR 260-270, Regulations on
the Management of Hazardous
Wastes

(b)	*0 CFR 761, Regulations for
Manufacturing, Processing and
Use of Polychlorlnated Bfphenyls

1(»)

AUTHORITY i PURPOSE

Establishes requirements for conducting public
hearings of effluent standards for discharges of
toxic pollutants under the NPDES program.

Kb) Designates compounds Identified as Hazardous Sub-
stances under the Federal Water Pollution Control
Act (Clean Water Act).

1(c) Identifies permitting requirements for discharges
of any "pollutants" from any "point sources" into
'Siaters of the United States".

1(d) Establishes criteria and standards for identifying
and applying water treatment requirements for dis-
charge permits Issued under the Clean Water Act.

1(e) Establishes effluent standards for toxic compounds
Including Aldrin, DDT, DDO, DOE, Endrin, Toxaphene,
Benzidine and PCBs.

1(f) Specify maximum contaminant levels (MCLs) for

Trlchloroethylene, carbon tetrachloride, 1,2-dlch-
loroethane, benzene, 1,1-dichloroethylene, para-
dlchlorobenzene, 1,1,1-trichloroethane and vinyl
chloride In drinking water. The regulation also
specifies best available technology (BAT) upon
which the MCLs are based.

1(g) Criteria published by EPA pursuant to Section 30*
(a)(1) of the Clean Water Act establish levels
which reflect current scientific knowledge regard-
ing the effect of pollutants on aquatic life.

2(a) Provide for the management of hazardous wastes
under the Resource Conservation and Control
Act

2(b) Specifies controls over handling of PCBs and

PCB-contaminated materials under the Toxic Sub-
stances Control Act

ACTIVITY COVERED

Public Meetings on NPDES
01scharges

Identification of Hazardous
Compounds

Water Discharge Permitting
Requirements

Identification of Wastewater
Treatment Requirements

Pesticide t PCB Discharges

Drinking Water Standards

APPLI-
CABLE?

Yes*

RELEVANT
I APPRO-
PRIATE ?

No

Yes

Yes*

Yes*

No

No

No

No

No

Yes

Yes

Surface Water Discharge

Management of Hazardous Wastes

Identification of PCB Contam-
inated Material

Yes*

Yes

Yes*

Yes

No

Yes

^Applies to specIf1c actions only

6/88


-------
FEDERAL

APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
(ARARS)

REGULATIONS

(c) 40 CFR 761, Subpart Ci 2(e)

"Polychlorlnated BI phenyl* Spill
Cleanup Policy"

3. Air Quality Regulations

(a) *0 CFR 50, National Primary and
Secondary Ambient Air Ouallty
Standard*

AUTHORITY t PURPOSE

I dent I Me* standards for removal of PCS* from
soils and equipment surfaces.

3(a) Sets ambient air standards for sulfur dioxide
ozone, particulates, carbon monoxide, nitrogen
dioxide and lead.

ACTIVITY COVERED

PCB Clean Up Actions
due to spills

Inorganic Air Emissions

APPLI-
CABLE?

No

No

Yes

Yes*

(b)	40 CFR 60, Regulations on
Standards of Performance for
New Stationary Sources

(c)	40 CFR61, National Emission
Standards for Hazardous
Substances

3(b) Establishes air emission standards for specific
point sources which are primarily Industrial
fact IItle*.

3(c) Sets emission standards for hazardous pollutants
from specific sources

Industrial Air Emissions

Benzene and Vinyl Chloride
Emission* from Production
Fact 11 tie*

No
No

Ye**
Yes*

4. Occupational Safety and Health Admin-
istration Regulation*

(a)	29 CFR 1910.120, Harardout
Waste Operations and Emergency
Response

(b)	29 CFR 1910.1000, Toxic and
Hazardous Substances

5. Other Regulations

(a)

40 CFR 6, Regulation* on
Implementation of NEPA

Ma) Specifies standards for hazardous waste opera-
tions.

4(b) Sets allowable ambient air concentrations for
specific compounds.

5(a) Specifies procedures for complying with the
National Environmental Policy Act.

Hazardous Haste Handling

Any activity Involving
release of VOCs In the
workplace

Wetlands Impacts

Yes

Yes

No

No

No

Yes

~Applies to specific action* only


-------
TABLE 8

POTENTIAL ACTION-SPECIFIC ARARs; STATE


-------
i

REGULATIONS
1, 10$ CHR department Public Health

{») 105 CMH 670.000. "Right to Kr.o*'

301 CMR Executive Office of
Envi rorar-cntal Affairs

U) 301 CMR 11,00, Massachusetts

Envl ronmentri! Pol icy Act
Regul ^tions

HAS$ACIfUSETTS
APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
(ARAR5)

AUTHORITY 4 PURPOSE

1{a) tOS CHR 670.000 regulations are adopted by the
Department of Public Health purussnt to the
authority granted it fay M.C,L» c. 111F, Section 2.
The regulations establishes the Massachusetts Sub~
stance LI St end amendments of regulated substances,
trade secrets and research lab exemptions, The -via"
of the regulations is to protect public health by
providing and encouraging the greatest possible
transmission of health and safety information con-
cerning to*ic and hazardous substances.

2<«) 301 CHR 11.00 regulations govern the implementation
of the Massachusetts Envlronmental Policy Act, N.C*L.
c. 30, Sections 62-62H. These regulations pro**! qc a
substantive basis to use all feasible means or measures
to avoid or minimile adverse environmental irnact
in compliance with H.G.L. c. 30, Section 61»

ACTIVITY COVERED

Aval 1abi11ry of Information to
public regarding tonic and
hazardous substances.

APPLI-
CABLE?

Yts

RELEVANT
£ APPRO-
PRIATE ?

Mo

JmpliHJ'entation of, and standards
for compliance *»i th Applicable
Environmental Regulations.,

Yes

No

3, 3t0 CHR Oeoartiwent of Envlronmentol
Ouality Engineering Regulations

Is} 310 CHR 6*00, Ambient Air
Quality Standards for the
Coswonweal th of Massachusetts

1(a) 310 CHR 6,00 regulations are adopted by the Department
pursuant to the authority granted It by M.G.L. c»
HI, Section H2(d). The regulations set primary #n t
secondary air quality standards for certain pollutants.

Air Emissions of SO-, Particu-
lates, CO, Oj and 1 e ad.

No

Yes®

Cbl 310 CHR 7,00, Ar	on

Control

3(L) 310 CHR 7.00 regulations adopted by th* n*r>ir'

pursuant to the author I ty granted it *-y	. Ill

Sections I*i2( a) -T<»2( j) and M,G.L. c.	I rrs.

k and 6. The purpose of the regulat In & jr ft tc prevent
the occurrence of conditions of air pollution where such
do not exist and lo f w ! 111 >t^ thr	>f ci-f»~

ditions of air pollution where and when «.u- h o; •. isr »

Air Emi »s t ons of Toluene > Tri-
chloroethylene, Vinyl Chloride
and other VOCs frcnn stationary
sources.

Yes*

No

tel 310 CMS 9.00, Adn»)nUtr«tton	3(c) 310 CMS 9,00 reguldtlons are adopted by i hf Tiwi treent	Dredging of Streww	Ma	Ho

of Waterways Licenses	pursuant to the authority granted It under M.G.L. C.

21A, Section 2 to implement	c, 91, Sections 1-63

and M,G,1. c. 21 A, Sections 2, kt 0, and 1*». The
regulations establish procedures» criteria end stan-
for the uniform and coordinated administration of the
provision of M.C.L. c. 91, work (dredging etc.) that
takes place In a waterway {stream, river).

•AodI•es to spec Ific acti ons only


-------
I

(d>

(O

REGULATIONS

S• 0 OS 10.0

Protection

^ Wetlands

(¦) 310 CHR 19.£ . Disposal

of Sol Id Was « by
Sanitary tar 'HI

310 Cm 22 A , Drinking
Water ftegulr ions

(g) 310 CHR 27.00, Underground
Water Sourc Protection

Ch) 310 CHft 30,
Waste Regula

, Haiardeus
Ions

MASSACHUSETTS
APPUCAOLt OR RELEVANT AND APPROPRIAlt REQUtREHENtS

SARAHS)

AUTHORITY I PURPOSE

3(d) 310 CHR 10.00 regulation* are adopted by the Ocpai

aent pursuant to" the authority granted It under H.fi.L.
c. 131, Section iiO. The regulations establish pro-
cedures, criteria, »nd standard! for work In x —* 1 and
(dredglnq, altering, etc.) subject to the protocti n
under M.C.L. c. 131E Section iiO.

3(e) 310 €HR 19.00 regulations are adopted by the Depart-
ment pursuant to the authority granted It under
t, 111, Section 1S0A. The regulation? establish
rules and requlreneots for solid waste disposal
facilities.	<

3(f) 310 CMS 22.00 regulations are adopted by U.c Jiujrt-

ircnt pursuant to the authority granted It under M.C.L.
e. Ill, Section 160. the regulations establish
standards and rerjuirenants deefned necessary to prevent
pollution and to assure the sanitary protection of
water used at sources of pubtIc water supply and to
ensure the delivery of fit and pure water to all
consumers,

i(g) 310 CHR 27.00 regulations are adopted by t!>» Pru.irt-

«nt pursuant to the authority granted It ni-H« M.C.L.
c. 111, Section 160; c. 21, Section 1?. The regula-
tions govern any underground Injection of hazardous
~tastes, of fluids used for extraction of minerals,
oil, and energy and certain other fluids with
potential to contaminate qround water In order to
protect under**; mrM sr^i* n* '.Mhksn'i >• v. <<•.

3(h) i kO LMH 30.00 reyylations «if*e aikipteU by the 0i:y*irfc~

j»0 Lnrt JU.UU reyut«iiui<& sjfe dOv>picv> oy u>e ut^ri-
rr»ent pursuant to the authority granted \ t under M»C.L.
c. 21C, Sections 'J 3rd 6 find M.C.L. c. 2IE, Section €.
Trie regulations establish rules and rcqul rement? for
torapc?, col lection, transportation,
,a1 # use, reuse, and recycling of

« e. •< _	» .. .. ..		4	u r- t

c I) 310 am 33.00, lapleirntatlon of

M.C.L. C, 1' IT, Employee and
Cooisunity "Right to XrW

Cj) 310 CHR *0.00, Contingency Plan
Regulations (OKAfT)

Tne regulat

the generation,

t r e#tr*en t, disposal, u ae, i oisc, »«ru ss... j <

haiardous materials. In Massachusetts under M.i;.t
e. 2IC, and M.C.L. c. 21E,

3(1) 3'0 CHR 33.00 regulations are adopted by the Di^jrt"

r»ent pursuant to the authority granted It under M.C.L.
c. T!1 F. The regulations establish rules and require-
ments for the dI sserolnation of Information r e 1 & > ^ d to
toxic and baiardous substances to the public.
3( j) 310 CHft 40,00 regulations ore adapted lay the Depart-
ment pursuant to M.C.L. c. 31E,

ACTIVITY COVERED

Work In Wetlands

Oi3001*1 of Wastes !n
Sanitary iindf111s

Protection of Public
Water Supply

Mo

Ho

No

Rft f'MHT
A APPRO*

PR I ATE 1

Yes

Tes*

Vet

Underground Injection of Fluids

Ho

No

Hazardous Waste Treatment
and Disposal

«es

No

Avallebl1 Ity of !nformit ion to

Put In Regarding Toxic and
H«i»fdous Substances

Releases of Hajardous
Material»

Yes

Yes

NO

Ho

~Aoplits to spec!fIc actions only

6/88


-------
I

MASSACHUSETTS
APPLICABLE OR RELEVANT AMD APPROPRIATE REO

(ARARS)

mmmn

REGULATIONS

3H CHE Massachusetts Water Pollution
Control Regulations

la)

Ilk CMR 3,00, Surface Water
Otschargi? Permit Program

Cb) 3H Cm *.00t Surface Water
Oualf ty Standards

it) 3H CHR 5.00, Ground-Water

Discharge Permit Program

Cd> 31* CMR 6.00, Cround-Water
Ouality Standards

AUTHORI TV & PURPOSE

' (a) 3H CNR 3.00 regulations care adopted by the Depart-
ment pursuant to the authority granted It m*1'* M.G.t»

c. 21 r Sections 27 and *3, The regulation- 	 j M i sh

requlregents for discharges of pollutants tn - > face
waters of the Commonwealth. In addition > •* r , I &t ing
these di scharges, M, C. L, c. 21, Section 't \
requires the Department to regulate the < f- h-i ¦> ( f
such discharges and any treatment works >n» I • » f d
*»i th these discharges.

t(b)

HO

31* CHR *,00 regulations are adopted by \n°	t~

went pursuant to the authority granted i \ «u- *-• M,G»L,
e» 21, Sections 27(5), 27(6), and 27(12), Ho regu-
lations establish Surface Water Quality in i»r - to
meet the goal of entrancing the quality rM \ .1 ^ of
the resources of the Cwmorwea 1 th»

31* CHR 5.00 regulations are adooted by ': i 1 *r < -1
standards consist of ground-wa¥ e< t h'.UfU.ii I>
which designate and assign the > > s <*•» t>¦>< wM. u -
various ground waters of the Commonwealth shall
maintained and orotected; water quality criterl
necessary to sustain the designated uses; and r
tions necessary to achieve the designated uses
maintain the existing groundwater quality.

«rt-
H.C.U

i atlons

be

egula-

vr

ACTIVITY COVERED

Surface Water Di scharges

APPLI-

CABLE?

Yes*

RELEVANT
4 APPRO-
PRIATE ?

No

Surface Water Quality Mainten-
ance

Ground Water Discharges

Yes*

No

No

Yes*

Ground Water Quality Mainten-
ance

Yet

Mo

*Applies to spec!fIc actions only

f/88


-------
MASSACHUSETTS

WPtlCABlE OR REtEVAHl A MO APPSOPRIATE
(ARARS)

JtREHEMTS

"(f)

KGUUHONS

(e) 31 El CKR 7.00, Se«er SystM
{•tension and Conwtttion
Pernlt Progr*«

(f) 3U CMB 9.00, Certlf lc«tlon for

Oredjing Material Oljotssal, and
F111 i ng I n Kitten

(9) 31% OW 1 2 .00, Coeration and
Maintenance and Pr*;tfestKtent
St»nd«rdj for Wastewater,
1 rotstnt Works, »nd i ndlrect

Diith«fgt$

S, W OB Department of tabor »nd Industries

(a) *11 CMR 21.80, Horker "light to Know 5(a)

6. Allo»*ble Ambient Level» (AALs)

7.

H.G.I, Chuoter 2)0 H*»i*Ce [>ca»rt-
ment pursuant to the author 1ty granted It imrtrr M.G.I,
c. 21, Section 1/(52). The reflation*	¦¦ ill

procedures , crIter I a, and standards for t he imtforni
and coordinated administration of water qoilliy cer-
tification of dredging and dredged material di syosal
and filling project* In the waters of th- ' • - .-wrcalth.

31 <» CMR 12.00 regulations as adopted by tl>r I'Tif t-
cient pursuant to the authority granted It gnJ-^r M.G.I,
c. 25, Sections 27(9), X7J12) and J5!. I he rr .Utlon.
establl sti requl regents that ensure the orooer ,ic r a t i on
and maintenance of wastewater facilities and ' «r
systems within the Ccw>on»ea 1 th.	-

Ml CKR 21.00 regulations ire adopted by the Orpar»-
stent pursuant to the authorlty granted It under M.C.L.
c. 111F. Th» fegulatloni establish requl re-f>t* for

worker "Right to Know."

The MU art generated f ton a comprehensive * •• ** e s s -
merit rrocedure con t a Ined In a docu**ent *nt111 r
  • «»»'*» »' Sepif lyilem AdxlnI»tr at I on and CertlfI cat ion of Or adglng Project! Maintenance and Operation of Wastewater Treatment Fact I Ity APR I - t,o No REtEVANI 4 APPRO- &nate : No NO Mo Availability of Information to Workers Regarding To*ic and K«itrdcu> Substances r»s Al lowable 2*-hour tl»e-welghted Wo average air to*let !»*f t««t) Siting of new hazardous watte facilities. Ho Yes* Kc No (see le« I Tes* •Aoollet to speciftc actions only 6/88

  • -------
    APPENDIX A
    
    RESPONSIVENESS SUMMARY
    
    

    -------
    Responsiveness Summary
    Rose Disposal Pit Superfund Site
    Lanesborough, Massachusetts
    
    September 23, 1988
    .S. Environmental Protection Agency
    Region I
    
    

    -------
    ROSE DISPOSAL PIT
    RESPONSIVENESS SUMMARY
    TABLE OF CONTENTS
    
    Paae
    
    PREFACE 		1
    
    I.	OVERVIEW OF REMEDIAL ALTERNATIVES CONSIDERED IN THE
    FEASIBILITY STUDY, INCLUDING THE PREFERRED
    ALTERNATIVE 		2
    
    II.	BACKGROUND ON COMMUNITY INVOLVEMENT AND CONCERNS. . .	4
    
    III.	SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC
    COMMENT PERIOD AND EPA RESPONSES
    
    Part I - Citizen Comments	6
    
    A.	Comments Regarding the Remedial Alternatives . .	6
    
    B.	Comments Regarding Groundwater Quality 		9
    
    Part II - Potentially Responsible Party Comments. . .	9
    
    IV.	REMAINING CONCERNS 	 48
    
    COMMUNITY RELATIONS ACTIVITIES CONDUCTED AT THE ROSE
    SITE
    
    TRANSCRIPT FROM THE INFORMAL PUBLIC HEARING
    
    EXHIBIT A -
    EXHIBIT B -
    
    

    -------
    PREFACE
    
    The U.S. Environmental Protection Agency (EPA) held a public
    comment period from July 21, 1988 to August 19, 1988 to provide an
    opportunity for interested parties to comment on the draft
    Feasibility Study (FS) and the July 1988 Proposed Plan prepared for
    the Rose Disposal Pit Superfund site (Rose site) in Lanesborough,
    Massachusetts. The draft FS examines and evaluates various
    options, called remedial alternatives, for addressing
    contamination of groundwater, surface water, soil and sediment at
    the site. EPA identified its preferred alternative for the
    cleanup of the site in the Proposed Plan before the start of the
    public comment period.
    
    The purpose of this responsiveness summary is to identify major
    comments raised during the public comment period and to provide
    EPA response to the comments. EPA has considered all of the
    comments summarized in this document before selecting a final
    remedial alternative for the contamination at the Rose site in
    Lanesborough, Massachusetts.
    
    This responsiveness summary is divided into the following
    sections:
    
    I.	Overview of Remedial Alternatives Considered in the Draft
    Feasibility Study. Including the Preferred Alternative -
    This section briefly outlines the remedial alternatives
    evaluated in the draft FS and the Proposed Plan, including
    EPA's preferred alternative.
    
    II.	Background on Community Involvement and Concerns - This
    section provides a brief history of community interest and
    concerns regarding the Rose site.
    
    III.	Summary of Comments Received During the Public Comment Period
    and EPA Responses - This section summarizes and provides EPA
    responses to the oral and written comments received from the
    public during the public comment period. In Part I, the
    comments received from citizens are organized by subject. In
    Part II, the extensive comments received from the PRP and
    EPA's responses follow the order of presentation by the PRP.
    A brief summary of PRP comments precedes EPA's detailed
    response.
    
    IV.	Remaining Concerns - This section describes issues that may
    continue to be of concern to the community during the design
    and implementation of EPA's selected remedy for the Rose
    site. EPA will address these concerns during the Remedial
    Design and Remedial Action (RD/RA) phase of the cleanup
    process.
    
    1
    
    

    -------
    Exhibit A - This exhibit is a list of the community relations
    activities that EPA has conducted to date at the Rose site.
    
    Exhibit B - This exhibit is a copy of the transcript from the
    informal public hearing that was held on August 3, 1988.
    
    I. OVERVIEW OF REMEDIAL ALTERNATIVES CONSIDERED IN THE DRAFT
    FEASIBILITY STUDY, INCLUDING THE PREFERRED ALTERNATIVE
    
    Using the information gathered during the Remedial Investigation
    (RI) and the Endangerment Assessment (EA), EPA identified several
    objectives for the cleanup of the Rose site. The response
    objectives are:
    
    1)	prevent exposure to contaminated soils and groundwater;
    
    2)	protect uncontaminated groundwater and surface water for
    current and future use; and
    
    3)	restore contaminated soils and groundwater for future use.
    
    GE, with EPA oversight, screened and evaluated potential cleanup
    alternatives for the Rose site. This evaluation, or feasibility
    study (FS) report, specifically describes alternatives for
    addressing contamination of groundwater and contaminated soil and
    sediment, as well as the criteria used to narrow the list to four
    potential remedial alternatives for groundwater contamination and
    eleven potential remedial alternatives for soil and sediment
    contamination. Each of these alternatives is briefly described
    below.
    
    Groundwater Alternative #1: Air Stripping/Carbon Treatment. For
    this alternative, contaminated groundwater is pumped to the
    surface or collected in trenches, and is then pumped to the top of
    an air stripping tower. Air is forced up through the tower and
    volatile organic compounds (VOCs) are removed from the groundwater
    into the air stream. This air stream is passed through an
    activated carbon filter to remove contaminants before being
    released into the atmosphere. Following air stripping, the
    groundwater is passed through a carbon filter to capture PCBs and
    any residual contaminants.
    
    In the Proposed Plan issued prior to the public comment period,
    EPA recommended this alternative as the Agency's preferred
    alternative for addressing groundwater contamination' at Rose site.
    
    Groundwater Alternatives fllA; Air Strippina/Carbon Treatment with
    Hydrogen Peroxide Pretreatment. In this alternative, air
    stripping/carbon treatment would be proceeded by a hydrogen
    peroxide pretreatment step. This would involve mixing the
    groundwater with hydrogen peroxide and passing the mixture through
    
    2
    
    

    -------
    a sand filter to remove approximately 75 percent of the VOCs before
    the water enters the air stripping tower.
    
    Groundwater Alternative #2: Ultraviolet Liaht-Ozonation with
    Hvdroaen Peroxide Pretreatment. This alternative would consist of
    the same pretreatment process described in Alternative #1A,
    followed by treatment with ozone and ultraviolet light to destroy
    PCBs and any remaining contaminants.
    
    Groundwater Alternative #3: Carbon Treatment with Hvdroaen
    Peroxide Pretreatment. This alternative would utilize hydrogen
    peroxide pretreatment to remove 80 to 90 percent of the VOCs.
    
    Carbon filtering then would be used to remove the PCBs and any
    remaining contaminants.
    
    Source Management; Wo Action Alternative. The no action
    alternative would entail leaving contaminants untreated on site,
    maintaining the existing synthetic cover and fence, continuing the
    on-going program to recover the pocket of oil located beneath the
    disposal site, and monitoring surface water and groundwater for 30
    years.
    
    Source Management Alternative #1: In-Situ Containment with
    Impermeable Cap and Barriers. This alternative would involve
    covering the disposal site with a waterproof cap to limit the
    amount of rain and snow that could filter through the wastes and
    carry contaminants away from the site. A groundwater cutoff wall
    also would be constructed around the disposal area to limit
    groundwater contact with contaminated soils.
    
    Source Management Alternative #2: In-Situ Soil Flushing with (a)
    Incineration or (b) Biodegradation of Recovered Liguids. This
    alternative would involve pumping a solvent or other solution
    through the contaminated soils to release PCBs and VOCs. The
    solution and contaminants then would be carried with the
    groundwater and captured by a groundwater collection system.
    
    After being separated from the groundwater, the contaminants would
    be either incinerated or treated by biodegradation.
    
    Source Management Alternative #3; KOHPEG Dechlorination. In this
    alternative, contaminated soils and sediments would be excavated
    and mixed in a chamber with a heated mixture of chemicals capable
    of destroying PCBs. VOCs released by this process would be
    captured with carbon filters prior to the treated air being
    released to the atmosphere. Decontaminated soils would be replaced
    on site.
    
    Source Management Alternative #4: On-site Incineration. Under
    this alternative, contaminated sediments and soils would be
    excavated and then incinerated in a mobile incinerator located at
    the site. Decontaminated materials would be replaced on site.
    All exhaust gases from the incinerator would be passed though air
    
    3
    
    

    -------
    pollution control devices prior to release into the atmosphere.
    As outlined in the Proposed Plan, EPA chose this alternative as
    its preferred alternative for treatment of contaminated soil and
    sediment.
    
    Source Management Alternative #5: Off-Site Incineration. Under
    this alternative, contaminated soil and sediment would be excavated
    and transported to an off-site hazardous waste incinerator.
    
    Source Management Alternative #6: On-Site Disposal in an Approved
    Hazardous Waste Landfill. This alternative would require
    construction of a federally-approved TSCA hazardous waste landfill
    on the Rose property. The landfill would include a waterproof
    synthetic liner as well as a leachate collection system to prevent
    potentially contaminated liquids from migrating from the area.
    Groundwater monitoring also would be conducted to ensure that the
    landfill and leachate collection system is functioning properly.
    Contaminated soil and sediment would be excavated and placed within
    the landfill.
    
    Source Management Alternative #7: Off-Site Landfilling. This
    alternative would involve excavating contaminated soil and
    sediment and transporting this material to a federally-approved
    off-site TSCA hazardous waste landfill.
    
    Source Management Alternative #8: Chemical Fixation-
    Stabilization of Excavated Wastes. In this alternative,
    contaminated soil and sediment would be excavated and mixed with a
    material such as cement or flyash to bind or stabilize ("fix") the
    contaminants into a solid material. Stabilized materials would be
    replaced on site.
    
    Source Management Alternative <9; Chemical Extraction with
    Incineration of Recovered Liguids. In this alternative,
    contaminated soil and sediment would be excavated and mixed with a
    combination of chemicals to extract the contaminants. The
    concentrated contaminants then would be transported off-site for
    incineration. Decontaminated soil and sediment would be replaced
    on site.
    
    Source Management Alternative #10; On-site Biodegradation. In
    this process, naturally-occurring or laboratory-tailored bacteria
    would be utilized to degrade, or break down, site contaminants
    into harmless materials such as carbon dioxide, water, and humus.
    
    II. BACKGROUND ON COMMUNITY INVOLVEMENT AND CONCERNS
    
    The Rose site, which consists of a disposal area approximately 1.5
    acres in size within a fourteen acre residential lot, is located in
    Lanesborough, Massachusetts. Beginning in 1951 and continuing
    through 1959 and possibly later, waste oils and solvents from the
    
    4
    
    

    -------
    General Electric Plant in Pittsfield, Massachusetts were disposed
    at the site in an open trench.
    
    The neighborhood surrounding the site is a mix of protected •
    natural areas, farms, and low density residential development.
    Reports on the possible presence of hazardous wastes at the site
    were first brought to the attention of town and state officials by
    a neighborhood resident in 1974.
    
    Community attention briefly focused on the site during the winter
    of 1980 when the Massachusetts Department of Environmental Quality
    Engineering (DEQE) conducted a site inspection. Following the
    investigation, at the request of DEQE, General Electric (GE)
    removed empty barrels from the site. Newspaper coverage of site
    activities continued during EPA's initial site investigation and
    the site's placement on the National Priorities List. Additional
    coverage occurred when GE provided municipal water to residences
    abutting the site and when EPA subsequently ordered GE to conduct a
    Remedial Investigation/Feasibility Study of the site.
    
    According to residents, there has been very little sustained
    community interest in the site. Until EPA held a public
    informational meeting in July 1988, concerns focused on the lack
    of information available on the site, potential health effects
    resulting from the site contamination, and confusion about the
    respective roles of EPA and GE, the Potentially Responsible Party.
    At the July 1988 public meeting, community concerns focused on the
    extent of the site contamination, EPA's preferred alternative, and
    other hazardous waste sites in Lanesborough. Specific concerns
    voiced by residents are outlined below.
    
    Roles of EPA, the State, and the PRP
    
    Citizens expressed confusion about who is ultimately responsible
    for cleaning up the Rose site. Citizens expressed their desire
    that EPA make the final decisions about the cleanup. Citizens
    also asked for regular information updates from EPA.
    
    Extent of Site Contamination
    
    Citizens expressed concern about what steps EPA was taking to
    prevent the spread of contamination from the site. In addition,
    citizens asked about potential contamination of private wells and
    about ways to have their wells tested for contamination.
    
    EPA's Preferred Alternative
    
    Citizens expressed concern about the potential impapt that
    operation of a hazardous waste incinerator might have on the
    community. Specific concerns focused on the noise associated with
    excavation and incineration, possible air pollution resulting from
    
    5
    
    

    -------
    excavation and incineration, and the potential for wastes from
    other communities being shipped to the site for treatment.
    
    Other Hazardous Waste Sites in Lanesborouah
    
    A number of citizens stated their concern that the owner of the
    Rose site at the time wastes were deposited at the site also owned
    other suspected or confirmed hazardous waste sites in the town.
    Citizens asked EPA to investigate the potential impacts of these
    sites on the community and on the municipal water supply.
    
    Future Use of the Site and Surrounding Areas
    
    Residents expressed concern that future development of the site
    could pose a health risk to the future residents. One citizen
    asked EPA about possible restrictions on development of land
    adjacent to the site.
    
    III. SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD
    AND EPA RESPONSES
    
    This responsiveness summary addresses the comments received by EPA
    concerning the draft FS and Proposed Plan for the Rose Superfund
    site in Lanesborough, Massachusetts. Three formal, sets of written
    comments were received during the public comment period (July 21 -
    August 19, 1988): one from a nearby resident in Lanesborough, one
    from an individual who operates a business adjacent to the site,
    and one set from General Electric. One oral comment was presented
    at the August 3, 1988 informal public hearing (which was reiterated
    in writing during the public comment period). A copy of the
    transcript is included as Exhibit B. Copies of the transcript are
    also available at the Lanesborough Public Library and the EPA
    Records Center at 90 Canal Street, Boston, Massachusetts, 02114 as
    a part of the Administrative Record.
    
    The comments from citizens, along with EPA responses, are
    summarized and organized into the following categories:
    
    A.	Comments Regarding the Remedial Alternatives
    
    B.	Comments Regarding Water Quality
    
    Part I - Citizen Comments
    
    A. Comments Regarding the Remedial Alternatives
    
    1. One commenter stated that their business, which operates
    
    adjacent to the Rose site, relies on telephone activities for
    their mail order operations. The commenter stated that they
    would like assurances from EPA that the impact of remedial
    
    6
    
    

    -------
    actions upon their business will be minimal. The commenter
    also asked to be notified whether personnel and equipment
    associated with the cleanup would be utilizing the commenter's
    property for access to the site.
    
    EPA Response: EPA is aware of the desirability to minimize
    impacts from the remedial activities. However, any
    construction activities will inherently be disruptive to some
    degree. The design and subsequent construction will attempt
    to minimize the short term impacts to reach the long term goal
    of overall protection of human health and the environment.
    Although the implementation of a permanent remedy will have
    greater short term impacts than a "no action" or minimal
    action alternative, the fact that contaminants will no longer
    be able to migrate from the site and that long term operation
    and maintenance will be greatly reduced and ultimately
    eliminated must be considered. During remedial design, local
    input will be solicited to ensure that specific concerns are
    addressed.
    
    Any remedial activity will generate some degree of noise.
    However, variables such as hours of operation for
    particularly noisy activities may be limited to certain times
    of the day. Techniques to minimize noise and other specific
    concerns will be examined during the remedial design process.
    
    All access needs will be primarily kept to the Rose property.
    In addition, EPA believes that the vast majority of the
    remedial activities can be conducted on the Rose property. As
    part of design, EPA will require site maps which will indicate
    all land and access needs and will include an overlay map with
    property boundaries. Should any land or access needs extend
    beyond the Rose property, appropriate agreements with those
    landowners will need to be negotiated.
    
    2. One commenter stated that they would like assurances from EPA
    that their property would be cleaned up should it become
    contaminated as a result of remediation activities at the
    Rose site.
    
    EPA Response; Remediation will be conducted to minimize
    impacts to surrounding areas. Should any releases occur
    during construction activities, however, the construction
    contractor would need to immediately address any such release.
    One of the items that will be required as a part of the design
    will be a "contingency plan" which will set forth the
    activities to be undertaken in the event of a release or other
    unplanned event. This contingency plan will be circulated for
    comment to ensure that local concerns are addressed. In
    addition to addressing noise and access (as noted in the
    preceding comment), EPA will utilize the following
    
    7
    
    

    -------
    activities, as necessary, in conjunction with the contingency
    plan:
    
    Releases to air - Air monitoring will be required to ensure
    that allowable levels of contaminants are not exceeded.
    Potential techniques to minimize air releases include the use
    of carbon filters on the air stripper, utilization of
    sophisticated air pollution control devices on the
    incinerator (stack), limiting the extent of soil excavation
    at any one time, and the use of suppressant foams that
    control the release of contaminants during excavation.
    
    Releases to water or surrounding soil - The groundwater
    interception and treatment system will be in place prior to
    initiation of soil excavation activities. Although no
    significant additional release of contaminants to the
    groundwater is expected during soil excavation, the
    interceptor trenches/wells will be in place so that any
    releases would be captured to prevent any offsite migration.
    
    Soil excavation activities will be controlled so that
    releases or unplanned movement of soils will not occur outside
    of designated areas. Work areas will be designated as either
    contaminated ("hot zone"), a decontamination zone, or as clean
    unrestricted areas. Site activities will be conducted such
    that these designations are maintained.
    
    One commenter urged EPA to utilize permanent, proven
    technologies to address the site contamination. The
    commenter further urged EPA to consider the welfare of the
    community and the environment in making decisions related to
    the cleanup before considering economic impacts upon GE.
    
    EPA Response: In evaluating the potential remedies for the
    Rose site, the statutory preference for a permanent remedy
    was a major factor in remedy selection. Air stripping and
    carbon treatment are proven techniques to permanently address
    groundwater contamination. Incineration is a proven
    technique to permanently destroy organic contamination in the
    soil and sediment.
    
    In addition, the nine criteria used to evaluate remedial
    alternatives include such items as overall protection and
    short and long term effects, as well as community concerns.
    Cost effectiveness is considered among alternatives that are
    considered to be equally protective. See Section VIII of the
    Record of Decision (ROD) for a discussion of these criteria.
    
    8
    
    

    -------
    B« Comments Regarding Groundwater Quality
    
    4. One commenter expressed concern that their private well
    
    currently could be contaminated by the wastes at the Rose
    site. An additional commenter asked EPA to test their well
    for contaminants at no expense to the property, owner.
    
    EPA Response: Review of the groundwater monitoring results
    indicate the extent of groundwater contamination based on a
    network of approximately 70 wells of varying depths in and
    around the site. The Rl reports provide the actual data from
    the various sampling rounds that have been conducted.
    
    The most recent groundwater data (November 1986) indicates
    the extent of the two contaminated shallow groundwater plumes
    and is shown in the ROD on Figure 3. Because the deep wells
    between the disposal area and the closest residential wells do
    not show any contamination, EPA has not required GE to conduct
    a residential well sampling program. Further, the groundwater
    contamination is generally restricted to the shallow
    overburden aquifer (to an approximate 25 foot depth), and it
    is believed that residential wells tap the deeper bedrock
    aquifer.
    
    As a part of the selected remedy, GE will be required to
    install a bedrock well in the vicinity of the disposal area
    (where the highest levels of contamination are found) to
    prevent the migration of contamination into the fractured
    bedrock. Should EPA obtain data that indicates that
    groundwater contamination may extend beyond the current areas
    of delineation, EPA would then conduct, or require GE to
    conduct, a residential well sampling program and appropriate
    monitoring.
    
    Part II. Summary of Potentially Responsible Party Comments
    
    EPA received and responded to extensive comments from the PRP,
    General Electric (GE). In brief, GE's main comments are: (1) GE
    contends that EPA is relying on a document (the draft Feasibility
    Study prepared by GE) that was never intended to, and does not,
    provide the technical information necessary to determine which
    source remedies meet the basic statutory criteria for treatment of
    wastes at Superfund sites; (2) GE contends that mobile
    incineration will not satisfy the statutory requirements of CERCLA
    and that it is not appropriate for the Rose site; (3) GE contends
    that mobile incineration will not be protective of human health and
    the environment, nor attain Applicable or Relevant and Appropriate
    Requirements (ARARs), nor be a cost-effective remedy, nor be a
    
    9
    
    

    -------
    permanent solution for metals contamination; (4) GE supports EPA's
    choice of a groundwater treatment alternative and recommends
    implementation of the groundwater treatment program; (5) GE
    suggests that a five-year testing period be conducted to develop
    and further evaluate alternative treatment technologies for soil
    contamination; and (6) GE suggests that if EPA requires immediate
    implementation of a soil and sediment treatment program, that
    chemical fixation/stabilization is an appropriate permanent
    solution for the Rose site. EPA's responses to GE's comments are
    provided in the following section.
    
    10
    
    

    -------
    Part II - Potentially Responsible Party Comments
    Comment 1
    
    GE is committed to a permanent remedy for the F.T. Rose Superfund
    Site that is protective of public health and the environment.
    
    Based on the data gathered to date, the Rose Site, located in
    Lanesboro, Massachusetts, may be contaminated with volatile
    organic compounds (VOCs), polychlorinated biphenyls (PCBs), and
    inorganic compounds. Additional site characterization work,
    however, is not yet complete. In fact, soil data as to VOCs is
    uncertain at best. Additional site characterization is necessary
    for all substances, but particularly soil data for VOCs and
    metals.
    
    Since beginning work on the Remedial Investigation/Feasibility
    Study (RI/FS), GE has worked closely with EPA to identify the
    nature of contamination at the Rose Site and to devise a remedial
    plan that would address the contamination in each environmental
    medium. In the course of winnowing a list of over 100 remedial
    alternatives originally identified, EPA and GE recognized early
    that mobile (on-site) incineration was not well-suited to the
    conditions of the Rose Site. Because of this, the data necessary
    to evaluate thoroughly an incineration remedy was never gathered.
    Up until June 1988, all indications were that EPA agreed with GE
    that further development of emerging innovative technologies would
    provide an effective remedy for the contaminated soil. (See
    discussion of EPA correspondence summarized infra.) Suddenly,
    however, EPA reversed its course and insisted on immediately
    selecting a permanent source remedy. Compounding the problems with
    its sudden reversal, EPA selected mobile incineration as its
    "preferred" remedial alternative, despite the fact that mobile
    incineration was not even among the top five remedies identified in
    the draft FS for the Rose Site.
    
    Response 1
    
    EPA is committed to a timely permanent remedy for the Rose
    Superfund Site that is protective of public health and the
    environment. Section 116(e) of CERCLA states the statutory
    mandate that substantial and continuous physical on-site remedial
    action commence at NPL sites in a timely manner. This section
    specifies that 175 remedial actions commence by October 16, 1989
    and an additional 200 commence by October 16, 1991.
    
    Based on the data gathered to date and available site history, the
    Rose site is contaminated with volatile organic compounds (VOCs),
    semi-volatile organic compounds (semi-VOCs), and polychlorinated
    biphenyls (PCBs). EPA believes that the site characterization work
    is adequate for remedy selection. Data necessary for remedy
    selection is distinct from that required for remedial design. EPA
    believes that the limited soil data on VOCs is adequate to select a
    
    11
    
    

    -------
    remedy from the technologies under consideration. The soil VOC
    data that is currently available is included in the October 1982
    Field Investigation Report prepared by EPA (see Tables 4 through 7,
    in particular). Additional site characterization is necessary for
    remedial design, particularly soil data for VOCs, semi-VOCs, and
    metals.
    
    Since beginning work on the RI/FS, EPA and GE have worked together
    to identify the nature of contamination at the Rose site and to
    devise a remedial plan that would address the contamination in each
    environmental medium. After brief examination of over 100
    technologies originally identified in the March 1985 report
    entitled "Initial Screening Feasibility Study Report" prepared by
    Blasland & Bouck for GE, EPA and GE recognized that mobile (on-
    site) incineration was potentially suited to the conditions of the
    Rose site and it was retained as a potential alternative for
    remediation. GE's reference to a different decision appears to be
    based on an inaccurate perception of EPA's statements; there is no
    record of any other decision. In fact, this alternative was
    retained for consideration from the initial screening through the
    June 1988 draft FS.
    
    The data necessary to design an incinerator was never gathered,
    nor was design data/treatability studies performed for other
    proposed source management alternatives (such as dechlorination or
    chemical fixation/stabilization). Treatability studies that were
    conducted by GE were focused on the groundwater alternatives. Up
    until June 1988, when EPA received the complete draft FS from GE,
    all indications were that further development of emerging
    innovative technologies could potentially provide feasible
    alternatives for the remediation of contaminated soil. Three such
    technologies were discussed for potential demonstration projects in
    the Proposed Plan issued by EPA in July 1988. In the absence of
    fully developed and implementable alternatives, EPA proposed mobile
    (on-site) incineration as a timely, permanent source remedy for the
    Rose site. EPA believes that incineration is the only currently
    implementable technology to permanently remediate the high levels
    of PCB contamination found at the Rose site.
    
    GE's reference to the "top five remedies identified in the draft
    FS" is misleading. GE's draft FS "recommended" five potential
    source management alternatives for use at the Rose site, three of
    which are still in the developmental phase. However, this did not
    lead to a decision by EPA to exclude incineration from
    consideration. EPA selects a remedial alternative on the basis of
    the Administrative Record and the statutory requirements and the
    response objectives. This selection process is explained in
    further detail in Section VIII of the ROD.
    
    12
    
    

    -------
    Comment 2
    
    B&B, the author of the draft FS, points out that the feasibility
    study has not been completed; the draft FS simply does not provide
    the technical basis for selecting any source remedy. With regard
    to mobile incineration, there are numerous, significant, unresolved
    issues that make its selection, at best, uninformed, and, at worst,
    arbitrary and capricious. These significant issues include, but
    are not limited to, the lack of soil contamination data (which
    affects a wide variety of implementability, safety, regulatory
    standard compliance and cost issues), potential emissions during
    excavation, the potential for
    
    generation of ash containing leachable metals and the limited
    availability of, and experience with, mobile PCB incinerators.
    
    Response 2
    
    EPA believes that the RI and draft FS provides an adequate basis
    for selecting a source remedy. The existing data indicates that
    high levels of soil PCB contamination exist throughout the
    disposal area. Figure 2 of the ROD (PCB soil contamination
    profiles in the disposal area) and the soil boring data presented
    in the RI show that contamination in most areas is above 50 ppm
    PCBs. Under the PCB disposal requirements of TSCA, 761.60(a)(4)
    states that any non-liquid PCBs at concentrations of 50 ppm or
    
    greater in the form of contaminated soil	shall be disposed of
    
    in either an incinerator (761.70) or a chemical waste landfill
    (760.75). EPA believes that incineration is an appropriate and
    feasible remedy for PCB contamination of soil.
    
    The Superfund Remedial Design and Remedial Action Guidance Manual
    (OSWER Directive No. 9355.0-4A) indicates in Section 2.3.2 that
    remedial actions involving on-site treatment or disposal of
    contaminated wastes may require additional studies to supplement
    the technical data available from the RI/FS so that the optimum
    treatment or disposal methods may be determined. Additional
    studies could include field work and/or bench and pilot scale
    studies. Since treatability studies during the RI/FS focused on
    groundwater only, these additional studies will need to be
    conducted as a part of remedial design/remedial action (RD/RA) for
    the source portion of the remedy. Obtaining such design data for
    all potential remedial alternatives would be extremely time-
    consuming and expensive. EPA regards the existing data as
    sufficient for comparison of the potential remedies.
    
    EPA acknowledges that there is additional work needed for the
    design of an incineration remedy at this site. This work
    includes:
    
    1. Soil VOC and semi-VOC data: This data is required for
    evaluating emissions during excavation, for design of air
    emissions control equipment for the incinerator, and for design of
    
    13
    
    

    -------
    precautions for overall safety. However, any soil VOC or semi-VOC
    contamination that exists in the PCB-contaminated soils that are to
    be excavated would be destroyed during the incineration process.
    Materials handling precautions will need to be tailored during
    design based upon the soil VOC levels.
    
    The soil VOC screening and analysis that was conducted in 1981
    generally indicates low levels of VOCs in the soil above the water
    table.
    
    EPA believes that there is adequate characterization of PCB soil
    contamination. PCBs are the major contaminant at the site. Over
    100 soils borings were taken in and around the disposal area with
    over 400 analyses conducted for PCB contamination.
    
    2.	Soils metal data: This data is required to evaluate the
    potential need for treatment of leachable metals which would be
    concentrated in incinerator ash and for design of appropriate air
    pollution control devices. EPA does not have any record of
    disposal of metal-bearing wastes at the Rose site. In addition,
    GE continues to recover contaminated liquids from the free product
    area and send this material to their Pittsfield incinerator for
    thermal destruction. Although EPA has requested data from GE on
    the analysis of this material in accordance with their Toxic
    Substances and Control Act (TSCA) permit, the only data received to
    date is on PCB and VOC content.
    
    Because there is no evidence that leads EPA to expect unusually
    high levels of metals in the soil to be incinerated at the site,
    EPA believes that the metals content of the soil will not be an
    obstacle to incineration. Metals analysis conducted on water
    samples represent naturally occurring levels of metals. EPA
    believes the metals that may be present can be managed with
    appropriate controls, including, if necessary, fixation-
    solidification of the ash.
    
    3.	Limited availability of, and experience with, mobile PCB
    incinerators: Both pilot and full-scale mobile PCB incinerators
    are available and have been used successfully at other hazardous
    waste sites. Experience with this technology is more extensive
    than that of the proposed demonstration technology(s). (The draft
    FS states that three of the promising technologies [in-situ soil
    flushing, chemical extraction, and biodegradation] all require
    field study to determine their effectiveness, particularly in light
    of the high levels of contamination found at the Rose site.)
    
    EPA owns a mobile rotary kiln incinerator which consists of
    specialized equipment mounted on 4 trailers. System performance
    is monitored through instruments and automatic safety shutdown
    controls. This mobile unit has demonstrated a greater than
    99.9999% destruction and removal efficiency at a trial burn on
    liquids and solids contaminated with dioxins. It has been
    operated over the past 2 years for cleanup of dioxin-contaminated
    
    14
    
    

    -------
    liquids and soils from numerous dioxin sites in Missouri. To
    date, over 2 million pounds of solids and 18,000 gallons of
    liquids have been processed.
    
    Ogden Environmental Services, Inc. owns and operates a mobile
    circulating bed combustor incinerator for the treatment of
    hazardous wastes. Test results from the company's pilot plant
    indicate that the TSCA requirement for 99.9999% destruction and
    removal efficiency was achieved for soil contaminated with 10,000
    ppm of PCBs.
    
    Under EPA's Superfund Innovative Technology Evaluation (SITE)
    program, a full-scale and a pilot-scale infrared system have been
    demonstrated. The full-scale system demonstration was conducted
    at the Peake Oil Superfund site in Florida. A total of 7,000
    cubic yards of waste material contaminated with PCBs and lead was
    processed. During the trial burn that was conducted, extensive
    sampling was included for the solid waste feed, stack gas, ash,
    scrubber liquid and water influent, scrubber effluent solids, and
    ambient air. The final technical report on the demonstration will
    document the entire mechanical operating history of the system and
    the problems that were encountered in operating this type of full-
    scale system. The pilot-scale system demonstration was conducted
    at the Rose Township - Demode Road Superfund site in Michigan.
    Approximately 10 cubic yards of contaminated soils were treated
    utilizing a blend of the most highly PCB- and lead-contaminated
    soils at the site. The final technical report will document
    information similar to the full-scale demonstration.
    
    Comment 3
    
    As a consequence of the deficiencies in the database underlying
    EPA's proposed remedy selection, and in view of the known and
    potential concerns regarding the mobile incineration of the
    contaminated soil at the Rose Site, EPA has clearly failed to
    establish that this remedy would satisfy the four fundamental
    criteria that Section 121 of the Comprehensive Environmental
    Response, Compensation, Liability Act (CERCLA) requires of a
    selected remedy, namely, that it:
    
    is protective of human health and the environment;
    attains all federal, state and local applicable or relevant
    and appropriate requirements (ARARs);
    
    * is cost effective; and
    
    utilize permanent solutions and alternative treatment
    technologies or resource recovery technologies to the maximum
    extent practicable.
    
    As detailed in the comments that follow, EPA's proposed selection
    of mobile incineration cannot be demonstrated to satisfy these
    statutory requirements. Indeed, presently available information
    indicates that the remedy may fail all four requirements. It is
    
    15
    
    

    -------
    these fundamental issues and concerns raised by EPA's remedy
    selection as it relates to remediation of soil contamination which
    are the focus of these comments.
    
    Response 3
    
    EPA believes that the existing database is adequate to support
    EPA's proposed remedy selection. Identified concerns regarding
    mobile incineration of contaminated soil at the Rose site are
    concerns that may be addressed during the remedial design process,
    and are not essential to remedy selection of mobile (on-site)
    incineration. See discussion under Response 2 above.
    
    Incineration is a proven technology which will meet ARARs and will
    be protective of human health and the environment. Incineration is
    considered to be the only technology currently available to meet
    the remedy selection criteria and the statutory requirements.
    
    Since on-site incineration is less expensive than off-site
    incineration, it is considered the most cost-effective
    alternative. Although design work is needed, there is no basis
    for any expectation that new information will change EPA's
    conclusion.
    
    EPA believes that the record establishes that this remedy does
    satisfy the four fundamental criteria of Section 121 of CERCLA,
    namely, that it:
    
    is protective of human health and the environment;
    attains all federal, state and local applicable or relevant
    and appropriate requirements (ARARs);
    is cost effective; and
    
    utilizes permanent solutions and alternative treatment
    technologies or resource recovery technologies to the maximum
    extent practicable.
    
    See Section XI of the ROD for a discussion of each of these
    issues.
    
    Comment 4
    
    GE does not reject every aspect of EPA's Proposed Plan. To the
    contrary, GE supports EPA's proposed groundwater remediation plan
    (air stripping and carbon treatment). Because this aspect of the
    cleanup can proceed independent of soil remediation, GE proposed
    that EPA divide groundwater remediation and soil remediation into
    separate operable units. EPA could then issue a Record of
    Decision (ROD) on the groundwater operable unit embodying the
    groundwater cleanup strategy described in EPA's Proposed Plan and
    implement that plan. An interim remedial measure — supplemental
    capping of the site — should also be implemented to minimize
    maintenance of the existing temporary cap while GE completes
    development of innovative technology to remediate the contaminated
    soils. With the completion of additional site characterization
    
    16
    
    

    -------
    work, and following a period of time necessary to significantly
    advance the promising emerging innovative technologies, EPA could
    issue a ROD on the second operable unit and a permanent solution to
    the soil contamination could be implemented.
    
    Response 4
    
    EPA does not believe that the groundwater aspect of the cleanup
    can successfully proceed independent of soil remediation. EPA has
    selected a permanent source remedy in conjunction with a
    groundwater remedy for this reason. EPA also does not believe
    that operable units are appropriate for this site; operable units
    are intended to address technically distinct portions of a site.
    At the Rose site, the groundwater contamination is directly related
    to the (source) disposal area. For example, the free product
    portion of the disposal area contains up to 57,000 ppm
    trichloroethylene (TCE) in the oil fraction, a component of the
    groundwater contamination. The groundwater cleanup goal for TCE is
    5 ppb. Clearly, with extremely high levels of TCE approximately 150
    feet from the potential location of the interceptor trenches/wells
    for the groundwater treatment system, the cleanup goals for
    groundwater may never be attained if a permanent remedy for the
    source area is not implemented concurrently. Although it is
    possible to prevent the plume from advancing with a groundwater
    treatment system in the interim, it is not possible to actually
    impact groundwater contaminant levels within the existing plume and
    effectively it would be a groundwater containment system. In
    keeping with EPA's and GE's commitment to a permanent remedy for
    the Rose site that is protective of public health and the
    environment, and consistent with the response objective of
    restoration of contaminated groundwater for future use and
    elimination of the source of contamination to Rose's Pond, EPA has
    selected a remedial approach which allows for timely remediation of
    the groundwater.
    
    Comment 5
    
    Splitting groundwater and soil remediation into separate operable
    units and delaying selection of the final source remediation is
    far better than blindly selecting mobile incineration now without
    the benefit of a better understanding of the Rose Site
    characteristics or the innovative technologies better suited to
    those characteristics. But if EPA feels compelled to select a
    final source remedy now, chemical fixation/stabilization is
    clearly more appropriate for the Rose Site conditions than mobile
    incineration. More importantly, unlike mobile incineration,
    chemical fixation/stabilization would satisfy the four fundamental
    criteria under CERCLA § 121.
    
    17
    
    

    -------
    Response 5
    
    As previously stated, EPA believes that the Rose site is
    sufficiently characterized to select mobile incineration. No
    innovative technologies can be judged to be better suited to the
    Rose site based on the information submitted to EPA by GE. These
    referenced technologies are assumed to be those discussed ih the
    draft FS and the Proposed Plan for potential site demonstrations.
    These technologies have not been proven in the field, nor on a
    pilot scale, nor at bench scale for the contaminant concentrations
    found at the Rose site. Mobile incineration is a proven technology
    on all levels.
    
    GE estimates that the timeframe necessary to sufficiently develop
    the innovative technologies is four to six years, excluding
    comparison of technologies and subsequent remedial design. This
    timeframe is unacceptable for remediation of the Rose site in light
    of the extremely high concentrations of contaminants. In addition,
    this 4 to 6 year timeframe inherently conflicts with the
    Congressional mandate to begin remediation at NPL sites, as stated
    in Section 116(e) of CERCLA (see Response 1 above).
    
    For discussion on this point concerning GE's proposal in
    Attachment 3 to GE's comments entitled "Research and Development
    Program for the Analysis and Destruction of F.T. Rose Site PCBs",
    see EPA's response to Comment 7 below.
    
    EPA does not believe that chemical fixation/stabilization is
    appropriate for the Rose site. GE has not provided any proof that
    existing fixation or stabilization processes are capable of
    immobilizing PCBs at the levels that exist at the Rose site. See
    Response 24 for detailed discussion of this issue.
    
    Comment 6
    
    Mobile Incineration Is Not Appropriate For The Rose Site
    
    Incineration is a viable and appropriate treatment technology
    under the right circumstances. In fact, GE operates a fixed-
    based liquid PCB incinerator at its facility in Pittsfield,
    Massachusetts, and a fixed-based rotary kiln hazardous waste
    incinerator at its facility in Waterford, New York. GE thus
    recognizes that incineration is an important treatment technology.
    GE's operational experience also allows it to perceive the
    limitations of incineration when not used in appropriate
    circumstances.
    
    Incineration is not appropriate at every site, or under any and
    all circumstances. An enormous number of factors — e.g.,
    variability of waste feed composition, nature of contamination,
    depth of contamination, even climate — must be considered and
    analyzed before one can determine if incineration can achieve the
    
    18
    
    

    -------
    desired result at a particular site, much less how much it would
    cost. It is this very type of information which EPA lacked when
    it decided that mobile incineration was the preferred remedial
    alternative.
    
    Response 6
    
    EPA agrees that incineration is not appropriate at every site. EPA
    considered a variety of factors in determining that incineration
    could achieve the desired clean-up goals at the Rose site. These
    factors include:
    
    1.	Variability of waste feed composition: Variability in
    particulate size will be addressed by design of appropriate
    pretreatment and materials handling processes. Variability in
    feed contaminant concentrations will be addressed by soil
    blending, particularly in cases where extremely high PCB
    concentrations are found. (It is possible that a successful
    demonstration of the soil washing alternative could address this
    factor.)
    
    2.	Nature of contamination: There is no historical evidence of
    disposal of metal-bearing wastes. Contaminants identified at the
    Rose site are predominantly organic and are suited to destruction
    by thermal treatment. As discussed in Response 2 above, EPA does
    not believe there are high levels of metals at the site.
    Appropriate design of air emissions controls and ash disposal
    practices can be imposed to address metals levels.
    
    3.	Depth of contamination: Soil excavation below the water table
    becomes complex and expensive and generally complicates material
    handling procedures. Soil moisture content affects the fuel
    consumption rate of the incinerator. EPA believes that limiting
    excavation to the water table for the majority of the site
    addresses a number of GE's technical implementation concerns.
    
    Because the PCB level in groundwater needed to satisfy the
    drinking water risk level is so low (0.005 ppb), virtual complete
    site excavation would be required. This is considered to be
    technically impracticable; see the ROD for a more detailed
    discussion of this issue.
    
    4.	Climate: A mobile incinerator may be more susceptible to
    climate considerations than GE's stationary incinerators located
    in close proximity to the site. However, appropriate
    weatherproofing (e.g. temporary structures to protect the
    incinerator, area of excavation, and/or materials handling and
    preparation area) would mitigate climactic impacts. EPA does not
    consider the weather to be an insurmountable obstacle to the
    implementation of on-site incineration.
    
    19
    
    

    -------
    Other factors which will need to be considered during remedial
    design include, but are not limited to: non-combustible fraction
    of solids, fraction of ash as particulate; combustible solids
    heating value; incinerator and afterburner operating temperatures;
    and residence time. Treatability testing will be required to
    determine appropriate operating parameters for the incinerator as
    well as ash/decontaminated soil handling procedures.
    
    Comment 7
    
    The Draft Feasibility Study Has Not Been Finalized
    
    GE and EPA had long contemplated that the most appropriate
    approach to remediating the PCBs in the soil at the Rose Site
    would most likely emerge from the innovative technologies which
    are being developed under GE's Corporate Research and Development
    (CRD) program. EPA Region I is quite familiar with this program,
    as GE has included regular written updates which have been
    submitted to EPA, which in turn have formed the basis for periodic
    technical review sessions between EPA and GE. A
    
    description of the CRD program, as it relates to the Rose Site, is
    attached (Enclosure 3).
    
    Response 7
    
    EPA made no remedial decision as to which proposed technology
    might be the most appropriate for remediating PCBs in the soil at
    the Rose site prior to the Record of Decision to which this
    responsiveness summary is an attachment. Technical alternatives
    retained for consideration in the FS were retained based on a
    screening process dictated by EPA RI/FS guidance; consideration of
    GE's CRD Program was incidental.
    
    EPA Region I is familiar with GE's CRD Program. GE has submitted
    regular written updates to EPA which have formed the basis for
    periodic discussions between EPA and GE. Submittals related to CRD
    prior to GE's submission of these comments have not been specific
    as to the Rose site. Previous submissions have focused on
    bioremediation and only recently have included surfactant
    extraction.
    
    Attachment 3 is the first site-specific submission purportedly
    describing research for the Rose site to EPA, particularly for the
    surfactant extraction process. EPA had received the identical
    (verbatim) submission which differed from Attachment, 3 only in
    references to site name. The report transmitted to.EPA by cover
    letter dated June 15, 1988 from GE entitled "Research and
    Development Program for the Destruction of PCBs" otherwise
    included identical text, soil sample levels, degree of extraction,
    and percentage of native soil lost as fines in the precipitate for
    the surfactant extraction process, but was written for GE's Oakland
    site in California. Laboratory documentation subsequently
    
    20
    
    

    -------
    submitted by GE upon request by EPA states that GE has not
    conducted any extractions on Rose site soils.
    
    GE has represented that the timeframe for development of
    innovative technologies would be an estimated 4 to 6 years. EPA,
    DEQE, and GE have now been investigating the Rose site for
    approximately 7 years. On-site incineration is a presently'
    available permanent remedy for organic contamination. EPA sees no
    basis in CERCLA on which an available permanent remedy could be
    rejected in favor of speculative, long term research, particularly
    when there is no firm basis for finding that the research is likely
    to yield an effective alternative within the time frame in which
    the available alternative could be implemented.
    
    Comment 8
    
    Several of the most promising of these innovative technologies
    were directly incorporated in the draft FS. As B&B states:
    
    It is this research which has formed the basis for the
    recommendations, in the draft Feasibility Study, for on-site
    pilot study of several of the promising innovative
    technologies at the Rose Site.
    
    B&B Comments, p. 15. It has been GE's opinion, from the outset,
    that emerging innovative technologies offered a better solution
    for the Rose Site than any of the "proven" technologies,
    particularly mobile incineration. This approach has been
    discussed by EPA and GE in their many meetings and communications
    addressing Rose Site source remediation, and it has been manifest
    in the draft FS submitted by GE in the past year.
    
    Response 8
    
    EPA acknowledges GE's opinion as having been expressed in meetings
    and in the draft FS. However, as indicated in Response 7, no
    remedial decision as to which proposed technology might be the most
    appropriate for the Rose site was made prior to the Record of
    Decision. In addition, EPA's commitment to a timely remedy for the
    site in accordance with the selection criteria conflicts with GE's
    development timeframes of 4 to 6 years for "emerging innovative
    technologies" that have not demonstrated the potential for
    effective implementation for the Rose site. See Response 7 for
    further discussion.
    
    Comment 9
    
    For its part, EPA has recognized and understood that this (see
    Comment 8) was GE's preferred approach. See, e.g.. EPA's letter
    of April 6, 1987 to Mr. Ron Desgroseilliers of GE (Enclosure 4),
    in which EPA discusses GE's proposal to separately address
    groundwater issued (through "short time frame" activities) and
    
    21
    
    

    -------
    source remediation (through "longer time frame" activities). More
    recently, EPA has not only acknowledged GE's approach, it has given
    every indication that the Agency concurred in it. No disagreement
    with GE's approach is expressed in EPA's undated draft comments on
    the draft FS (submitted to EPA on April 1, 1988) (Enclosure 5).
    Nor was there any mention of any disagreement with GE's approach in
    the Agency's formalized comments dated May 12, 1988 (Enclosure 6).
    And finally, in the Agency's undated comments on the next draft FS
    (submitted to EPA on June 3, 1988) (Enclosure 7), EPA never
    discussed mobile incineration nor disagreed with GE's approach.
    
    Response 9
    
    EPA's letter of April 6, 1987 to Mr. Ron Desgroseilliers of GE
    stated that ..."G.E. proposed a two-phased approach to continue
    conducting activities at the site....
    
    a)	'Short time frame' activities - G.E. indicated a desire to
    address the VOC contamination problem at the site on a separate
    and expedited schedule. G.E. believes that the VOC contamination
    of the (shallow) groundwater lends itself to treatment with proven
    technologies that are currently available, as well as
    accommodating SARA's preference for permanent treatment
    technologies.
    
    The following is the tentative implementation schedule that was
    presented at the meeting:
    
    March - April '87 — Review and update the initial screening
    
    of alternatives for the groundwater
    contamination problem.
    
    March - May '87 — Screen the alternatives in light of the
    
    SARA requirements.
    
    June - '87	— EPA issues an Administrative Order to
    
    G.E. to conduct the selected groundwater
    treatment alternative.
    
    July '87 - ?	— G.E. implements the remedial alternative.
    
    b)	'Longer Time Frame' Activities - G.E. indicated a desire to
    keep on the longer time frame for the ROD process that is required
    for the site as a whole. G.E. believes that the PCB portion of the
    contamination at the site does not lend itself as readily to a
    proven and available technology for remediation, as well as
    considering the preference for permanent remedies under SARA.
    
    As such, the following tentative implementation schedule was
    proposed:
    
    22
    
    

    -------
    March - June '87
    
    Review the initial screening of
    alternatives, and screen the alternatives
    in light of the SARA requirements.
    
    July - December '87
    
    Conduct the detailed FS.
    
    January - March '88
    
    EPA issues its Record of Decision
    
    April »88 - ?
    
    G.E. implements the remedial
    alternative...."
    
    EPA did not formally agree nor disagree with GE on any preferred
    remedial approach prior to the proposed plan issuance. In fact, a
    review of the schedule outlined in the EPA letter (excerpt above)
    shows a schedule for the detailed FS approximately six (6) months
    ahead of the current schedule.
    
    EPA acknowledges that the design of the groundwater treatment
    portion of the remedy may be accomplished sooner that the design
    of the incinerator. It is EPA's intention that the design and
    implementation of the groundwater treatment system be carried out
    expeditiously. The design of the incinerator portion of the
    remedy will require a longer time period than that for the
    groundwater treatment system.
    
    Comment 10
    
    The first signal from EPA of the need for a major shift in
    direction came at a June 14, 1988 meeting with GE, when EPA
    announced that its Region I "Management Committee" had decided
    that the Agency would select a remedy based on the limited data in
    hand, and that selection would be mobile incineration.
    
    Response 10
    
    In the June 14, 1988 meeting with GE, EPA and GE discussed the
    upcoming EPA issuance of the Proposed Plan for the Rose site. EPA
    developed the Proposed Plan based on the RI, the draft EA, and the
    draft FS which addressed remedial alternatives for both the source
    area and groundwater. The draft FS includes information pertinent
    to the selection of an overall site remedy which meets the intent
    of CERCLA. One of the alternatives retained in the draft FS was
    mobile incineration. Further, EPA proposed mobile incineration at
    this time; final remedy selection is made in the ROD to which this
    responsiveness summary is an attachment.
    
    Comment 11
    
    As the preparers of the draft FS documents, B&B is uniquely
    qualified to comment on the approach and intended scope of the
    documents prepared to date, and/or the technical problems
    associated with EPA's sudden insistence on selecting a final
    
    23
    
    

    -------
    source remedy from the data in the latest draft FS. Their
    overview of this issue is compelling:
    
    It is our belief that the Feasibility Study process should
    continue with the collection of additional site
    characterization data and finalization of the Feasibility
    Study Report. Only at that time can a defensible remedy be
    selected by the EPA and subsequently be implemented without
    significant delay.
    
    B&B Comments, p. 5.
    
    Response 11
    
    EPA cannot allow FSs to continue indefinitely, particularly when
    sufficient information exists to show that a feasible permanent
    alternative is currently available. B&B's belief that the FS
    process should continue with the collection of additional data
    seems to address the purposes of remedial design rather than
    remedy selection.
    
    Comment 12
    
    As a consequence of all of the above, EPA has failed to follow the
    statutory procedures for selecting a remedy. EPA is relying on a
    document that never intended to, and does not, provide the
    technical information necessary to determine which, source remedies
    meet the basic statutory criteria — much less which one is the
    best choice from among those that do.
    
    Response 12
    
    The ROD explains how the remedy selection of mobile incineration
    meets the statutory criteria of Section 121 of CERCLA. In
    addition, in the Administrative Order on Consent signed by EPA and
    GE dated March 22, 1988 (U.S. EPA Docket No. CERCLA-I-88-1010;
    paragraph 4), the stated purpose of the Consent Order is "In
    entering into this Consent Order, the mutual objectives of EPA and
    the Respondent [GE] are the following... To provide EPA with a
    Feasibility Study so that EPA can evaluate alternatives and
    determine the appropriate extent of the remedial action needed to
    prevent or mitigate the release or threatened release of hazardous
    substances, pollutants, or contaminants at or from the F.T. Rose
    site..." This Feasibility Study was to be completed by GE by June
    30, 1988. The draft FS and the administrative record provide EPA
    with sufficient information to support a remedy selebtion. See
    previous responses, including Responses 2 and 3, for further
    discussion.
    
    24
    
    

    -------
    Comment 13
    
    Mobile Incineration Will Not Satisfy The Statutory Requirements Of
    CERCLA
    
    On technical, policy and legal grounds, any final selection of
    remedy would be premature and would not meet CERCLA's
    requirements. Congress has mandated that EPA select a remedy that
    is protective of human health and the environment, attains ARARs,
    is cost-effective, and utilizes permanent solutions and
    alternative technologies or resource recovery technologies to the
    maximum extent practicable. CERCLA § 121(b). EPA cannot, on the
    basis of the information before it, determine whether mobile
    incineration satisfies any of these requirements.
    
    Response 13
    
    The ROD discusses how the mobile incineration and groundwater
    treatment remedy does, in fact, meet the statutory requirements of
    CERCLA. Refer to Section XI of the ROD for a discussion of these
    issues.
    
    Comment 14
    
    Mobile Incineration At The Rose Site Will Not Protect Human Health
    And The Environment
    
    The Endangerment Assessment Report identified the following long-
    term risks:
    
    (1)	human ingestion of or dermal contact with contaminated
    groundwater,
    
    (2)	human ingestion of or dermal contact with contaminated site
    soils, and
    
    (3)	animal ingestion of surface water.
    
    Endangerment Assessment, pp. 95, 100-01. For a remedy to be
    protective of human health and the environment, it must limit or
    eliminate each of the risks identified in the Endangerment
    Assessment Report. [GE believes that the risks identified above
    will have been successfully mitigated by the measures taken to
    date (e.g., fencing and capping) and by the installation and
    operation of the groundwater treatment system. Notwithstanding
    this, GE remains committed to a permanent source remedy at the
    Rose Site.]
    
    25
    
    

    -------
    Response 14
    
    GE's EA never identified metals contamination (in either soil or
    water) nor soil VOC contamination as a potential risk factor to be
    considered.
    
    As noted by GE in the previous comment, CERCLA Section 121(b)
    states that EPA will select a remedy that is protective of human
    health and the environment, attains ARARs, is cost-effective, and
    utilizes permanent solutions and alternative technologies or
    resource recovery technologies to the maximum extent practicable.
    Mobile incineration and groundwater treatment will protect human
    health and the environment by permanently eliminating each of the
    risks identified in the EA report.
    
    Measures taken to date at the site do not constitute permanent
    mitigation of site risks to the maximum extent practicable.
    
    The site cap consists of multiple pieces of 5 mil plastic sheeting
    held in place with wooden pallets and tree branches and the fence
    is a 4-foot high wooden snow fence. The property is zoned
    residential and there are no current restrictions on use of the
    property.
    
    It is assumed that the groundwater treatment system referred to is
    actually the oil recovery system that is currently in operation at
    the site. The oil recovery system extracts liquids from the free
    product portion of the site below the water table. This recovered
    product is sent off site for incineration at GE's Pittsfield TSCA
    incinerator. The primary intent of this recovery system is not
    groundwater treatment but rather reduction of the source volume.
    This system does not collect nor treat contaminated groundwater
    that has migrated east and south of the disposal area.
    
    Comment 15
    
    In addition, however, a remedy must not create new risks. As ERM
    notes in its comments, "it is essential to understand the risks of
    implementing the technology, given the possibility that the cure
    may be worse then the disease." ERM Comments, p. 3. EPA's
    proposed selection of mobile incineration poses just such a
    scenario. For example, mobile incineration potentially poses
    several health risks which EPA has not adequately considered,
    specifically, the impact that vapors, particulates, and/or dusts
    from excavating contaminated soils would have on workers, nearby
    residents, and the environment. Control of the emissions would be
    particularly critical since VOCs are believed to have contaminated
    the soil. While both B&B and ERM believe the emission controls can
    be engineered to minimize the impacts of these emissions, such
    control mechanisms have significant inherent risk of failure, as
    well as significant costs that have not been evaluated in the draft
    FS. B&B Comments, p. 7.
    
    26
    
    

    -------
    There is also the potential for the generation of ash containing
    leachable metals. As discussed infra. incineration does not
    destroy metals. Thus, following incineration of soils, metals
    will be concentrated in the ash. In this form, the metals may be
    more leachable than metals in soil and thereby present a greater
    risk to human health and the environment. EPA has not considered
    this issue. See B&B Comments, pp. 8-9, and ERM Comments, pp. 6-
    7. One final example (although by no means exhausting all of the
    potential risk issues) is the negative affect that mobile
    incineration could have on the surrounding environment. At EPA's
    August 3, 1988 public meeting, a local resident expressed her
    concern about the environmental impacts associated with operating
    a mobile incinerator 24-hours a day for a period of four or more
    years.2/ EPA has not considered the increased vehicular traffic
    and noise that will result or the impact on local wildlife
    (particularly in the wetlands area).
    
    2/ Comments of Dianne Nichols, an owner of property adjacent to
    the Rose Site.
    
    Response 15
    
    EPA has considered the "several health risks*' which GE has
    identified. A detailed approach on how to address these risks
    will be developed during remedial design:
    
    1. Impact of excavation: Excavation would be necessary for more
    than one of the alternatives proposed in the draft FS, including
    one or more of the demonstration projects. Anv remedy involving
    excavation to permanently remediate contaminated soils would need
    to address excavation concerns, and the costs and risks of
    excavation would be the same for all such remedies. As a part of
    safety precautions, an air monitoring program will be developed to
    permit rapid detection and early response to potential releases of
    air contaminants during excavation. (See Response 24 for a more
    complete discussion of this issue.)
    
    Emissions controls can be implemented and have been at other
    hazardous waste sites. The risk of failure and the cost are both
    minimized by the fact that the total areal extent of the site is
    relatively limited and that excavation would be phased to minimize
    the extent of open cuts at any given time. B&B failed to indicate
    that "significant cost" or "significant inherent risk of failure"
    were factors to consider in the evaluation of alternatives
    involving excavation discussed in the draft FS. Experience in the
    Superfund program to date does not indicate that emission controls
    for excavation for a site of this size for on-site treatment of
    contaminants found at the Rose site are subject to "significant
    inherent risk of failure". EPA believes that proper engineering
    design and implementation of appropriate safety precautions can
    greatly reduce the risk of failure.
    
    27
    
    

    -------
    Moreover, the cost information of concern is not included in any
    information submitted by GE to EPA. The reference to cost and to
    potential failure of excavation emission controls is vague and
    ambiguous.
    
    2.	Generation of ash containing leachable metals: As discussed
    in Response 2, EPA has no record of disposal of metal-bearing
    wastes at the Rose site. Metals as a potential site contaminant
    has never been studied by GE since GE's inception of work at the
    site in 1983, nor were they identified as a potential concern in
    the EA. Metals characterization sufficient to complete remedial
    design will need to be undertaken in conjunction with remedial
    design (see Response 6). Potential metals contamination of
    incinerator ash will need to be evaluated at that time. Without
    any site-specific treatability studies on incineration, it is
    uncertain whether or not any metals would concentrate in the
    decontaminated soil fraction at unacceptable levels. In any case,
    EPA believes that measures to prevent the potential release of
    metals, particularly from the ash, are available and feasible if
    needed. Air pollution control devices will capture metals that are
    attached to dust or soil particles carried with the gas stream.
    
    The November 1986 sampling results show low levels of metals in
    groundwater, including a sample from well 12A, one of the most
    contaminated wells at the site. All metals levels were below
    drinking water standards.
    
    At no time since 1984 when GE initiated incineration of the free
    product portion of the site (see previous Response 14 on oil
    recovery system) has GE provided information to EPA on metals
    analysis data nor suggested that metals are present at the site.
    
    3.	Vehicular traffic and noise: EPA has considered the impact of
    traffic associated with the site on the surrounding areas.
    
    Concern about increased vehicular traffic was a factor in
    selecting an on-site remedy. (Off-site incineration would result
    in the transportation of untreated highly contaminated soils over
    long distances.) B&B did not consider these controls to be of
    such concern previously as to include pertinent discussion in the
    draft FS. Further, the incremental costs and risks which are of
    such concern to B&B and GE are not presented in sufficient detail
    here to evaluate.
    
    EPA weighs the short and long term impacts of various remedial
    alternatives as a part of the overall remedial selection process.
    EPA acknowledges that increased traffic will necessarily result
    with any type of remedial construction activity. An on-site
    versus an off-site remedy will help to minimize these potential
    impacts. In addition, EPA believes that the benefits of the long
    term goals of overall protection through the implementation of a
    permanent remedy, thereby not allowing contaminants to migrate
    
    28
    
    

    -------
    from the site and the reduction and ultimate elimination of long
    term operation and maintenance, outweigh the short term impacts of
    remedy implementation.
    
    Comment 16
    
    Mobile Incineration Will Not Attain ARARs
    
    Protection of human health and the environment is achieved, at
    least in part, by identifying and complying with the "applicable
    or relevant and appropriate standard, requirement, criteria, or
    limitation" (commonly referred to as "ARARs") for the hazardous
    substances, pollutants, or contaminants that will remain at the
    site. CERCLA § 121(d)(2)(A). As EPA noted in its "Interim
    Guidelines on Superfund Selection of Remedy":
    
    Remedies must be protective of human health and the
    environment. This means that the remedy meets or exceeds
    ARARs or health-based levels established through a risk
    assessment when ARARs do not exist.
    
    Memorandum dated December 24, 1986 from J. Winston Porter,
    Assistant Administrator, U.S. EPA Headquarters, to Regional
    Administrators, EPA Regions I-X, p. 7 (emphasis in original). EPA
    has not shown, and cannot show on the available data, that mobile
    incineration of contaminated soils satisfies ARARs or health-based
    standards for those soils.
    
    In its "Interim Guidance on Compliance With Order Applicable or
    Relevant and Appropriate Requirements," 52 Fed. Reg. 32,496,
    32,497 (1987), EPA identifies three different types of ARARs:
    
    (1)	ambient or chemical-specific requirements,
    
    (2)	performance, design, or other action-specific
    requirements, and
    
    (3)	locational requirements.
    
    All three types of ARARs potentially apply to the selection of
    mobile incineration to remediate contaminated soil at the Rose
    Site. EPA states in the Proposed Plan that "PCBs, thirteen
    different VOCs, and six semi-vocs have been detected in the soil
    and groundwater at the F.T. Rose site." Proposed Plan, p. 4.
    Yet, in the same section, EPA admits that it has not established
    cleanup goals for the soil contaminants:
    
    EPA is also developing soil cleanup goals for the site based
    on EPA's PCB policies and other guidelines .... The
    groundwater and soil and sediment cleanup method selected by
    EPA must reduce the concentration of the contaminants at the
    F.T. Rose site to the designated cleanup goals.
    
    29
    
    

    -------
    As EPA has not yet established chemical-specific soil cleanup
    goals, it cannot state that mobile incineration satisfies those
    cleanup goals. EPA has thus concluded that mobile incineration is
    the "preferred" remedial alternative having never established the
    chemical-specific soil cleanup goals, the site conditions have not
    been adequately analyzed to determine whether mobile incineration
    at the Rose Site could achieve those cleanup goals.
    
    Because EPA has not fully characterized site conditions, EPA
    similarly could not determine whether mobile incineration would
    satisfy action-specific ARARs. For example, the draft FS contains
    no data on the metals content of the soil. Incineration of soil
    does not destroy metals. As a result, toxic metals may end up
    being concentrated in the burned soils, which could lead to one or
    both of the following results. First, concentrated metals can
    increase the leaching potential of those metals in the ash. If the
    metals were rendered more leachable by mobile incineration, it is
    difficult to characterize that remedy as being protective of human
    health and the environment or permanent. Second, if the
    incinerator ash concentrates the metals, the ash may fail the
    Extraction Procedure Toxicity Criteria, and be considered a
    hazardous waste. The standards established under the Resource
    Conservation and Recovery Act (RCRA) for handling hazardous wastes
    would then apply to the disposal of the hazardous ash from
    operations at the Rose Site, requiring either on-site construction
    of a RCRA landfill or disposal of the ash in an off-site licensed
    facility. See B&B Comments, p. 8, and ERM Comments, p. 7. EPA has
    ignored the potential applicability of such RCRA standards, and
    their potentially significant compliance costs, in its Proposed
    Plan.
    
    Although some of these risks may be mitigated through the design
    and engineering of additional controls,3/ EPA has not assessed
    the existence of such potential risks, the question of whether,
    and if so, how the risks may be mitigated, and the incremental
    costs and time that the mitigation measures will add to the
    project.
    
    Finally, EPA not has considered whether mobile incineration would
    comply with locational ARARs. Specifically, the draft FS
    identifies the Massachusetts Hazardous Waste Siting Act, M.G.L.,
    c.21(d), as an ARAR in Table 3-1. Further, mobile incineration
    was not among the top five source remediation alternatives in the
    draft FS because it is "potentially unacceptable due to the
    proximity of residential areas, Balance Rock State Park and
    Pittsfield State Forest." Draft FS, p. 7-3. Yet, in meetings
    prior to the issuance of its Proposed Plan, EPA informed GE that,
    in the Agency's opinion, the Massachusetts Siting Act is not an
    ARAR. Instead, EPA views the siting laws as analogous to a state
    permitting requirement, and, as such, not applicable to the F.T.
    Rose cleanup pursuant to SARA § 121(e), which states:
    
    30
    
    

    -------
    No Federal, State, or local permit shall be required for the
    portion of any removal or remedial action conducted entirely
    on-site, where such remedial action is selected and carried
    out in compliance with this section.
    
    This interpretation would suggest that because this section'
    relieves the person remediating a Superfund site from obtaining
    permits required under federal, state, or local law relating to
    hazardous waste handling, it logically follows that such federal,
    state, or local laws need not be considered in the remedy
    selection process. Such an interpretation, however, conflicts
    with CERCLA § 121(d) which expressly characterizes facility siting
    laws as ARARs that must be satisfied at the completion of a
    remedial action. See CERCLA § 121(d)(2)(A). Senator Robert
    Stafford (R-Vt.), one of the architects of SARA, made this exact
    point in the floor debate which followed passage of SARA: "This
    section requires the Administrator to meet the requirements of
    State facility siting laws . . . 132 Cong. Rec. S14,910 (daily
    ed. Oct. 3, 1986). EPA, in its own guidance on compliance with
    ARARs, recognizes as much. In providing examples of locational
    ARARs, which "set restrictions on activities depending on the
    characteristics of a site or its immediate environs," EPA included
    "[f]ederal and State siting laws for hazardous waste facilities."
    52 Fed. Reg. 32,497. Thus, it is clear from EPA's own guidance
    that facility siting laws are ARARs which must be substantively met
    in the remedy selection process.
    
    Given that EPA's Proposed Plan would place a mobile incinerator in
    the midst of a state park, a state forest, and residential
    communities, and given that this mobile incinerator would operate
    24 hours a day for a period of years, it is imperative that EPA
    consider the acceptability of such a plan under the Massachusetts
    siting law. The fact that EPA has not determined whether the
    location of a mobile incinerator next to irreplaceable state
    resources would be consistent with the standards of the
    Massachusetts Hazardous Waste Siting Act is just another
    indication that EPA has not demonstrated that mobile incineration
    would be protective of human health and the environment or would
    achieve all federal, state and local ARARs.
    
    3/ See B&B Comments, pp. 6-10, and ERM Comments, p. 3, for a
    
    more detailed discussion of potential risks not identified by
    EPA.
    
    *
    
    Response 16
    
    The ROD documents that mobile incineration of contaminated soils
    satisfies ARARs. The soil cleanup goal has been established by
    EPA and is set forth in the ROD. B&B did not present costs for
    
    31
    
    

    -------
    incinerator ash treatment for application should levels of metals
    (not an identified site contaminant) warrant treatment.
    
    CERCLA § 121(d)(2)(A) applies "With respect to any hazardous -
    substance, pollutant or contaminant that will remain on-site..."
    and it requires compliance with ARARs, including those promulgated
    under a state facility siting law "...at the completion of the
    remedial action." The mobile incinerator called for by EPA's
    selected remedy will thus not be subject to facility siting
    requirements as ARARs. The Massachusetts statute cited in the
    comment, M.G.L. c. 21(d) is applicable only to new facilities. In
    the regulations which implement the Siting Act, the State has
    specifically exempted on-site remedial actions (900 CMR §1.02(2)).
    Chapter 21(d) is thus neither applicable nor relevant and
    appropriate.
    
    EPA is unaware of any impacts on "irreplaceable state resources"
    that would occur during implementation of the remedy, and no such
    impacts were identified in the draft FS. Although the site is
    adjacent to a state park, the park is not heavily utilized and
    access to the site from the park is through heavily wooded areas.
    Measures to minimize any impacts will be factored in to the design
    process. EPA regards any potential for short term impacts as
    outweighed by the long term permanence of the remedy.
    
    Comment 17
    
    Mobile Incineration Will Not Be A Cost-Effective Remedy At The
    Rose Site
    
    A determination that a selected remedy is cost-effective can only
    be determined after (1) cleanup goals are established, (2)
    remedies are identified which can attain those cleanup goals and
    (3) the cost of each such remedy is determined. As noted above,
    EPA did not establish critical cleanup goals (or adopt those
    listed in the draft FS) prior to selecting mobile incineration as
    the preferred remedy. But had EPA done so, it still would not be
    in a position to determine whether other remedial alternatives
    achieve those health goals at a lower cost since data to determine
    the cost of all of the source remedies, particularly mobile
    incineration, are substantially lacking.
    
    Although EPA includes the draft FS estimate of $19.2 million for
    mobile incineration in its Proposed Plan, the accuracy of that
    estimate is highly dependent on the level of cleanup,that
    ultimately is selected. The draft FS estimate is based on the
    assumption that "VOCs would be reduced to insignificant levels"
    and PCBs would be reduced to 50 ppm. Draft FS, p. 6-59. As
    indicated earlier, however, EPA is currently contemplating
    different — and presumably more stringent — level of cleanup for
    PCBs. The quantity of soil at the Rose Site in which PCB levels
    
    32
    
    

    -------
    exceed a 50 ppm cleanup goal could be much smaller than the
    quantity of soil exceeding a lower cleanup level. Accord-
    ingly, by lowering the cleanup goal, EPA could significantly
    increase the quantity of soil required to be excavated and, in
    turn, the cost of mobile incineration.
    
    The failure to recognize that the cost of mobile incineration
    varies greatly with the desired level of cleanup is just one of
    many variables which EPA has failed to consider in its cost
    estimate for mobile incineration. The B&B comments touch on a
    number of these variables which, in addition to not being
    considered or analyzed in terms of technical implementability,
    also were not factored into the $19.2 million estimate. Each of
    these variables could significantly increase the cost of mobile
    incineration.
    
    B&B notes that the cost of mobile incineration can vary greatly
    depending on the composition of the soil matrix. For example,
    soils with high moisture content consume larger quantities of fuel
    and require longer periods to incinerate —as much as 1.5 to 2
    times. In addition, high moisture content soils require special
    and costly handling procedures to avoid exposing personnel and the
    local community to hazardous emissions from the excavated soil.
    Finally, the presence of cobbles, boulders, and other nonuniform
    constituents of the soil matrix can increase the cost of mobile
    incineration significantly. See B&B Comments, pp. 12-14.
    
    Another potentially costly variable relates to the depth of
    contamination. If soils below the water table must be excavated,
    groundwater infiltration and corresponding problems of subsidence
    will greatly increase the time needed to excavate and incinerate
    contaminated soil. B&B notes, for example, that at the Peake Oil
    Site in Brandon, Florida, incineration of only 7,000 cubic yards
    of soil took over a year to complete due to excavation problems
    (below the water table), as well as problems with "debugging" the
    incinerator. B&B Comments, p.13. If the Rose Site water table
    creates the same level of difficulty encountered in excavating the
    Peake Oil Site soils, then the estimated four to five years
    required for incinerating soil at the Rose Site would be far short
    of the actual incineration time.
    
    Response 17
    
    GE is attempting to argue both that there is insufficient data on
    incineration to evaluate cost-effectiveness, and (see Comment 24)
    that there is sufficient data on solidification to evaluate its
    cost effectiveness and select it. GE fails to specify which cost
    data is "substantially lacking" or to provide missing cost data.
    EPA believes that there is sufficient data on both alternatives to
    evaluate cost effectiveness. It is also important to consider the
    accuracy of costs developed for a feasibility study. Typically,
    these cost estimates provide an accuracy of +50 to -30 percent.
    
    33
    
    

    -------
    EPA believes that the only currently available feasible alternative
    - and therefore the most cost-effective - is incineration. Since
    GE estimated the costs of off-site incineration to be greater than
    those for on-site, EPA concludes that for the Rose site mobile
    incineration is a cost effective remedy. The cost estimate used in
    the draft FS of approximately $380 per cubic yard is considered to
    be within the range used for estimating the costs of incineration.
    
    In addition, the ROD sets forth the limits of excavation to 13 ppm
    PCBs to the water table and the free product area, resulting in
    excavation of approximately 15,000 cubic yards of soil, a large
    portion of which is above the water table. Accordingly, EPA
    believes that a 2 year estimate for implementation is reasonable.
    Even if incineration should prove to develop "delays" as the Peake
    Oil site has experienced, EPA believes that the 2 year estimate is
    still conservative.
    
    Appropriate pretreatment and materials handling, such as feed size
    preparation and the reduction of potential emissions, will be an
    integral part of remedial design for any alternative involving soil
    excavation prior to treatment.
    
    Comment 18
    
    Beyond increasing the cost of mobile incineration, certain
    variables could render mobile incineration impracticable. B&B
    points out that there are presently a total of twelve mobile
    incinerator units in the United States. Of these twelve, there
    are no circulating bed variety (the type specified in EPA's
    preferred remedy) available for use at the Rose Site. The
    available units are either rotary kiln or infrared units and cost
    two to three times more than circulating bed units. Moreover,
    most of the vendors contacted by B&B stated that they could not
    guarantee the availability of even a rotary kiln or infrared unit
    for this project, and would likely have to construct a unit for
    the Rose Site. B&B Comments, p.8.
    
    Response 18
    
    EPA's Proposed Plan did not specify circulating bed incineration.
    Rather, the preferred alternative stated "...on-site incineration
    is the preferred alternative for addressing soil and sediment
    
    contamination	Three different types of incinerators were
    
    evaluated: rotary kiln, circulating fluidized bed, and infrared
    processing. The extremely high temperatures in any of these
    thermal destruction facilities would destroy 99.9999% of all of the
    organic contaminants." The ROD states that design will determine
    the most appropriate type of incinerator for use at the Rose site.
    
    The design phase will include examination of the availability of
    existing units appropriate for the site. This information will be
    factored into the overall design and the potential need for
    
    34
    
    

    -------
    construction of a unit. Time frames for design will be sensitive
    to vendor response. Further, Ogden Environmental Services, Inc.
    owns and operates a transportable circulating bed combustor.
    
    Comment 19
    
    B&B also noted that EPA failed to consider the fact that the
    utilities required by incinerators — 7 million gallons of diesel
    oil or 22 million kwh of electricity, and 250 million gallons of
    water — are not currently available at this site or in the
    immediate area. B&B Comments, pp. 10-11. But perhaps the most
    glaring deficiency in EPA's analysis of the cost-effectiveness of
    mobile incineration at the Rose Site is the failure to consider
    the effect of the northern climate on that operation. The
    northern climate will significantly limit, or preclude, operations
    during winter months due to the inability to dewater and otherwise
    prepare materials for incineration. B&B Comments, p.12.
    
    Response 19
    
    Detailed information regarding utility needs was not provided in
    the draft FS. The assumptions used to generate these figures are
    not presented by GE. EPA assumes that the numbers presented in
    this comment have been calculated to reflect extensive excavation
    below the water table. Design work will need to estimate the
    actual utility needs and to make provisions for providing them to
    the site. Certain design items, such as sizing of the incinerator
    and examining the potential for recycling of quench and scrubber
    water, could potentially reduce the utility needs.
    
    Climatic considerations will also need to be factored into the
    design. As previously stated, limiting a large portion of the
    excavation to above the water table will minimize problems
    affiliated with deep saturated soil excavation. (Climatic
    concerns could also be applicable to certain fixation-
    solidification techniques.) For remedial work conducted at other
    sites in northern climates, various techniques have been employed
    to minimize weather-related impacts. Such techniques include
    temporary structures to house equipment and to protect open
    excavation areas.
    
    The Administrative Order on Consent (previously referenced) in
    Appendix B stated that the FS shall include "... a description of
    all special engineering considerations required to implement the
    alternative...". As such, EPA assumed that the cost estimates in
    the draft FS addressed these concerns.
    
    Because EPA has found no other alternative to currently be
    feasible, increases in costs resulting from utility or weather
    considerations will not alter the basis for EPA's selection of
    incineration. These potential cost increases may increase the
    
    35
    
    

    -------
    cost of on-site incineration, but are assumed to still be lower
    than the costs associated with off-site incineration.
    
    Comment 20
    
    The availability of mobile incinerators and utilities to run them,
    and the operability of such units under climatic extremes common in
    the Northeast are central to any determination of whether mobile
    incineration is implementable at the Rose Site, much less how much
    it would cost.
    
    In terms of cost, B&B believes that these variables, together with
    others that it identified — e.g., revision of soil cleanup goals,
    engineering controls for emissions, material handling issues —
    could double or triple the $19.2 million cost estimate for mobile
    incineration in EPA's Proposed Plan. B&B Comments, p. 15. EPA's
    failure to consider these issues belies EPA's claim
    that it has determined mobile incineration to be cost-
    effective.4/
    
    4/ For a more detailed discussion of these and other variables
    
    which potentially would have a significant impact on the cost
    estimate, see B&B Comments, pp. 7-15, and ERM Comments, pp. 3-
    5.
    
    Response 20
    
    Please see previous responses to address the issues that are
    reiterated in the above comment, including Responses 6, 17, 18,
    and 19.
    
    Comment 21
    
    But even assuming, for the sake of argument, that the proffered
    cost estimate of mobile incineration is as accurate as the cost
    estimates of other remedial alternatives listed in the Proposed
    Plan, this information demonstrates conclusively that, contrary to
    EPA's assertion (Proposed Plan, p.13), mobile incineration is not
    cost-effective. Comparison of mobile incineration with the other
    remedial alternatives included in the Proposed Plan is
    instructive. Of the alternatives for which cost has been
    estimated, two are containment alternatives which EPA says do not
    satisfy the statutory preference for permanent solutions. One
    (dechlorination) is reported to range anywhere from $16 to $30
    million. Chemical fixation is a permanent treatment technology
    which protects human health and the environment, 5/ and, at $11.2
    million, nearly halves the $19.2 million cost of mobile
    incineration and clearly is cost-effective. Only the remaining
    two remedial alternatives — off-site landfilling, at $25 million,
    and off-site incineration at $149 million — cost more than mobile
    incineration.
    
    36
    
    

    -------
    Landfilling is not a permanent solution and off-site incineration
    runs counter to the disfavor under § 121 of off-site transport of
    hazardous substances. Thus, EPA's claim that mobile incineration
    is "cost-effective" simply does not comport with the facts as
    stated in the draft FS.
    
    5/ The permanence of chemical fixation/stabilization is
    discussed infra.
    
    Response 21
    
    EPA considers cost-effectiveness only among feasible alternatives
    that achieve equivalent levels of cleanup and degree of
    protectiveness. With the information that EPA has received from
    GE to date, EPA does not consider fixation/stabilization to be
    feasible nor equivalent to incineration in protectiveness nor
    permanence. It is for this reason that EPA did not directly
    compare the costs of incineration to fixation/stabilization and
    compared only the costs of on- and off-site incineration. Cost
    effectiveness also takes into account the total short and long
    term costs of alternatives, including the costs of operation and
    maintenance. See Section XI of the ROD discussion regarding cost
    effectiveness for further detail.
    
    Section 121 of CERCLA does not disfavor off-site transport of
    hazardous substances. Rather, Section 121 disfavors off-site
    disposal. particularly when the remedial action does not involve
    treatment.
    
    Comment 22
    
    Mobile Incineration Will Not Be A Permanent Solution For Metals
    Contamination
    
    The cleanup standards under § 121 (b)(1) mandate in pertinent
    part:
    
    Remedial actions in which treatment which permanently and
    significantly reduces the volume, toxicity or mobility of the
    hazardous substances, pollutants, and contaminants is a
    principal element, are to be preferred over remedial actions
    not involving such treatment.
    
    Even the permanence of mobile incineration is questionable. GE
    would agree that mobile incineration would permanently reduce the
    "toxicity, mobility [°r] volume" of the organic contamination in
    the soil. Proposed Plan, p.7. However, as noted above, mobile
    incineration does not destroy metals. The potential presence of
    high concentrations of several heavy metals is an unresolved
    issue, as ERM notes in its comments. ERM Comments, p.6. If
    
    37
    
    

    -------
    metals have contaminated the site, mobile incineration would not
    reduce the toxicity of the metals contamination. Mobile
    incineration also does not significantly reduce the volume of the
    contaminated soil. Finally, as noted earlier, mobile incineration
    may render metals more leachable and thus mobile incineration would
    not reduce the mobility of the metals. Whether metal-contaminated
    ash is placed in an off-site or on-site secure landfill, the
    statutory preference for permanent solutions would not be
    satisfied.
    
    In sum, EPA has no basis for "preferring" mobile incineration over
    other remedial alternatives. It has not gathered the data which
    would permit it to undertake the detailed comparative assessment of
    remedial alternatives contemplated under CERCLA § 121. As a
    consequence, and notwithstanding EPA's statements to the contrary
    in the Proposed Plan, EPA has not demonstrated, and cannot
    demonstrate, that mobile incineration of the Rose site would
    satisfy CERCLA's remedy selection criteria, i.e., that the remedy
    protects human health and the environment, attains ARARs, is cost-
    effective, and utilizes permanent solutions to the maximum extent
    practicable.
    
    ftespopsg ??
    
    See previous responses to address similar fcomments made
    previously, including Responses 1, 3, 12, 13, and 15.
    
    Comment 23
    
    GE's Proposed Remedy
    
    Congress "encourage[d] the development and implementation of
    innovative permanent treatment technologies . . . whether or not
    they have been achieved in practice at other similar sites or
    facilities." 132 Cong. Rec. §14,926 (daily ed. Oct. 3, 1986)
    (statement of Sen. Chafee). GE believes that innovative
    technology is the key to remediating the soil contamination at the
    Rose Site and is committed to developing, through its Corporate
    Research and Development Program, the appropriate permanent
    treatment technology.
    
    The three technologies that EPA indicated in the Proposed Plan it
    is considering as demonstration projects — in-situ soil flushing
    with leachate treatment, chemical extraction with incineration of
    extracted liquids, and on-site biodegradation— were, among the
    five alternatives which the draft FS identified as ftshow[ing] the
    greatest promise for remediating the disposal area in accordance
    with guidance set forth in SARA." Draft FS, p. 7-3. Mobile
    incineration was not among these alternatives for reasons already
    explained. GE believes EPA should be willing to return to the
    original approach for this site, i.e., providing GE with the time
    and incentive to further develop these innovative PCB treatment
    
    38
    
    

    -------
    technologies, and to demonstrate — through pilot studies, field
    studies and, if warranted, full scale demonstration — the
    feasibility of such alternatives at a Superfund Site.
    
    The development of innovative PCB treatment technology as an
    alternative to mobile incineration would be of national
    significance. PCB contamination is widespread in this country.
    The cost to society of incinerating every PCB-contaminated site
    would be staggering. Clearly, the significance of innovative PCB
    technology would extend far beyond Lanesborough, Massachusetts.
    
    GE proposes that EPA divide groundwater remediation and soil
    remediation into separate operable units, an option expressly
    endorsed in the National Contingency Plan, 40 C.F.R. § 300.68(c)
    (1) (19871) ("Response actions may be separated into operable
    units consistent with achieving a permanent remedyM). EPA could
    immediately issue a ROD on the groundwater operable unit and that
    remedial plan could then be implemented. Air stripping and carbon
    treatment would prevent the spread of contamination through the
    groundwater. GE would, within five years, develop the alternative
    treatment technology for the soil remediation operable unit.
    
    During this five-year period, interim source remedial measures will
    be implemented to manage site soils while these studies are
    underway. GE would propose to:
    
    (1)	remove the existing synthetic membrane cover from the
    disposal area;
    
    (2)	cover the disposal area with a new synthetic cap (such
    as 40-mil Hypalon or HDPE);
    
    (3)	upgrade the existing fence around the disposal area; and
    
    (4)	continue oil removal operations from Well 42-A.
    
    The groundwater collection and treatment system described above
    would be designed and constructed concurrently with the interim
    source control remedy. Thus, during the five-year period all of
    the risks identified in the Endangerment Assessment will have been
    mitigated.
    
    By the end of five years, GE would finalize a new FS for the
    second operable unit, incorporating the results of the CRD
    program. Based on that FS, EPA would select a permanent remedy
    for immediate implementation.
    
    GE cannot overemphasize the benefits of further developing
    innovative PCB treatment technology. Allowing additional time for
    such development makes particular sense at the Rose Site.
    Implementation of the first operable unit will eliminate all of
    the identified risks to human health and the environment. This is
    particularly true given that the primary contaminants of concern —
    PCBs — are immobile. B&B Comments, p.14. In combination with
    
    39
    
    

    -------
    the fact that the data is simply insufficient to select final
    source remediation as part of any current ROD, it makes a
    compelling case for not artificially forcing a remedy selection
    now.
    
    Response 23
    
    There are several reasons EPA does not agree with GE's proposed
    approach. Although the issues have been previously addressed they
    are briefly be reiterated here:
    
    1.	Research and development. EPA believes that the development
    and implementation of innovative technologies was not intended to
    be an open-ended process. While EPA appreciates GE's commitment
    to the development of alternative treatment technologies
    independent of EPA's Superfund Innovative Technology Evaluation
    (SITE) program, the CRD work to date that has been presented to
    EPA is focused on bioremediation which has long (4 to 6 years)
    development time frames. Even longer time frames would be
    required to implement these potential technologies, if they are
    even applicable to the Rose site, considering the site conditions
    and the levels of contamination present. It is extremely
    difficult to predict when technologies under development might be
    ready for scale-up and actual implementation that could achieve
    clean-up goals.
    
    EPA acknowledges the desirability of alternative technologies in
    the ROD. The selected remedy specifically states "In an effort to
    encourage development of alternative technologies for treatment of
    hazardous waste....EPA is considering allowing GE to conduct a
    demonstration project .... this alternative would be considered for
    use if it is demonstrated to meet the criteria for remedy
    selection." Clearly, EPA is receptive to the concept of
    alternative technologies that could be developed, designed, and
    implemented in a time frame equivalent to that needed to design
    and implement on-site incineration. However, EPA will not delay
    implementation of an available remedy for speculative, long term
    research. Studies have been ongoing at the Rose site for
    approximately 7 years. EPA finds the proposal that GE be allowed
    another 5 years to conduct a FS for the site to be unacceptable.
    
    2.	Operable units. EPA does not believe that operable units are
    appropriate because of the direct connection between the source
    disposal area, especially the free product area, and the
    groundwater contamination. Operable units are intended for
    technically distinct portions of a site, which is not the case for
    the Rose site.
    
    3.	Site risks. Although immediate implementation of the
    groundwater treatment system would address the risk posed by
    contaminated groundwater migration, merely "containing" the source
    disposal area would put the groundwater treatment system in a
    
    40
    
    

    -------
    "containment" mode as well rather than beginning active
    remediation of the groundwater. Extremely high free product
    levels of contamination would exist in close proximity to the
    groundwater capture area.
    
    Regarding disposal area soils, the temporary cap is merely a
    temporary measure to limit contact; it is not a permanent remedy
    that is preferred by the statute.
    
    Comment 24
    
    Alternative Proposal
    
    If EPA feels compelled to select a final source remedy now, mobile
    incineration is not the appropriate choice, as demonstrated
    previously, because it does not meet the statutory requirements.
    Based upon current data, the only remedy that meets the statutory
    criteria is chemical fixation/stabilization. Chemical fixation is
    a proven technology which would immobilize PCBs and any inorganic
    contamination in the soil and thus eliminate the identified health
    risks associated with those contaminants. Chemical fixation, under
    this scenario, would be the remedy designated to be implemented at
    the end of the 5-year period for development of innovative
    technologies.
    
    To complement the selection of chemical fixation/stabilization, GE
    would immediately undertake additional assessment and remedial
    activities. First, GE would undertake an extensive soil
    characterization program, focusing on both VOCs and metals.
    
    Second, if VOC contamination is confirmed in the soil
    characterization study, GE would implement a VOC extraction
    procedure. VOCs would be extracted and destroyed prior to
    excavating and immobilizing the contaminated soil. This would
    address the concerns, discussed earlier and in the enclosed B&B
    and ERM Comments, that VOC emissions during excavation activities
    would pose a potential health risk. Further, the remedy would be
    protective of human health and the environment with regard to any
    remedy that involves soil excavation.
    
    Chemical fixation/stabilization would also satisfy the requirement
    under § 121 that the EPA select a permanent remedy. VOCs will be
    destroyed and PCBs and inorganic contaminants will be permanently
    immobilized. In its analysis of chemical fixation/stabilization,
    EPA agrees that it "would greatly reduce the mobility of the
    contaminants, minimizing long-term environmental effects."
    
    Proposed Plan, p. 12. However, the agency asserts that the
    technique would not reduce the volume and toxicity of the
    contaminants and the "stabilized material would still be considered
    hazardous." Id. Curiously, this statement is inconsistent with
    EPA's analysis of chemical fixation/stabilization contained in its
    May 12, 1988 comments on the draft FS (Enclosure 6).
    
    41
    
    

    -------
    It is not clear why alternative SM-8 (chemical
    fixation/stabilization) was given a low institutional
    ranking. This alternative would be completed on-site and
    could significantly reduce the mobility and toxicity of
    contaminants (with resultant increase in volume, however).
    
    Attachments to EPA Comments, p.7 (emphasis added).
    
    Regardless of whether one accepts the May or July version of EPA's
    position, chemical fixation/stabilization would satisfy the
    requirement to "utilize permanent solutions" under § 121. A
    permanent solution is one which employs treatment which
    "permanently and significantly reduces the volume, toxicity or
    mobility" of hazardous substances at the site. CERCLA §
    121(b)(1). It was no accident that Congress used the disjunctive
    "or" rather than the conjunctive "and" in the phrase "volume,
    toxicity or mobility." Based on the plain meaning of the
    statutory phrase, treatment which significantly reduces either
    volume or toxicity or mobility of hazardous substances at a
    Superfund site would satisfy the statutory preference for
    permanence. Representative Dennis Eckart D-Ohio) made this exact
    point during the floor debate which followed passage of SARA:
    
    [T]he statute refers to the significant reduction of volume,
    toxicity or mobility — using the disjunctive "or" rather
    than the conjunctive "and."
    
    132 Cong. Rec. H9589 (daily ed. Oct. 8, 1986). Since chemical
    fixation/stabilization would "permanently and significantly
    reduce" the mobility (and, GE believes, the toxicity) of hazardous
    substances at the F.T. Rose Superfund site, it satisfies the
    statutory preference for permanence.
    
    In this regard, it is important to note that Congress did not
    intend EPA to select the
    
    "most permanent" remedy available; it is not intended that
    EPA spend millions of dollars incinerating vast amounts of
    slightly contaminated materials where other cost-effective
    alternatives would provide a high degree of permanence and
    protection of public health and the environment.
    
    132 Cong. Rec. H9567 (daily ed. Oct. 8, 1986) (statement of Rep.
    Lent). Thus, the fact that mobile incineration destroys PCBs
    whereas chemical fixation/stabilization only immobilizes them
    would not, by itself, justify or require the selection of
    incineration. Both remedies achieve a "high degree of permanence
    and protection of public health and the environment;"
    
    Section 121 also requires that EPA select a cost-effective remedy.
    Assuming, for the sake of argument, that both mobile incineration
    and chemical fixation/stabilization would constitute permanent
    
    42
    
    

    -------
    solutions, be protective of human health and the environment, and
    achieve ARARs, the fact that mobile incineration is far more
    expensive than chemical fixation/stabilization would require the
    selection of chemical fixation/stabilization, since it is the more
    cost-effective remedy.
    
    EPA reached a similar conclusion in the ROD for the Liquid
    Disposal, Inc. (LDI) Site, Utica, Wisconsin (EPA Reg. V) (Sept.
    30, 1987). Chemical fixation was selected to remediate soils
    contaminated with volatile organic compounds (including PCBs) and
    various inorganic metals. Regarding the preference under § 121 for
    remedies involving permanent treatment, EPA notes that the
    selected remedy "uses treatment as a principal element." LDI ROD,
    p. 18. The Agency further notes:
    
    The remedy will reduce the mobility and toxicity of the waste
    by greatly reducing or eliminating the ability for hazardous
    chemicals to leach out of the solidified mass. However,
    hazardous chemicals still remain in that mass.
    
    Id.
    
    Incineration was rejected by the Agency because
    
    [I]t is not cost-effective for the LDI site contaminants.
    The RI concluded that there was no clearly identifiable
    pattern or "hot spots" of contamination at the site. Due to
    the non-uniform and unpredictable waste distribution, the
    cost-effectiveness of selectively incinerating certain types
    of waste types or site areas could not be determined.
    
    Therefore . . . the entire soil/waste volume [125,000 cubic
    yds.] on-site would require incineration.
    
    Id., p. 16.
    
    Similar facts at the Sand Springs Petrochemical Complex Superfund
    Site, Tulsa, Oklahoma (EPA Region VI) (September 29, 1987)
    convinced EPA to scrap a plan to incinerate soils heavily
    contaminated with VOCs and inorganic metals and select "on-site
    solidification" instead. Mobile incineration would have cost
    nearly $67 million, while solidification will cost approximately
    $38 million. In comparing incineration and solidification (using
    the same nine criteria listed in EPA's Proposed Plan for the Rose
    site), EPA concluded that solidification represented the best
    balance among these criteria. In selecting solidification, EPA
    stated that it constitutes a "promising innovative technology," it
    is significantly less costly, and human health and the environment
    would be protected. See "Declaration For the Record of Decision"
    (which precedes the full text of the Sand Springs site ROD). These
    same three factors would justify use of chemical
    fixation/stabilization as the chosen remedy to be implemented at
    the Rose Site at the end of the 5-year period for the development
    
    43
    
    

    -------
    of innovative technology, should such technologies not prove
    effective.
    
    Response 24
    
    Effectiveness of Fixation/Stabilization
    
    GE has not provided any proof that existing fixation or
    stabilization processes are capable of immobilizing PCBs at the
    levels found at the Rose site. EPA is unaware of the use of this
    technology for containing levels of organic contamination as high
    as are documented at this site. Further, GE's EA did not identify
    any health risks associated with any VOC or inorganic
    contamination in the soil.
    
    Contrary to GE's claims, EPA has never concluded that fixation-
    stabilization would permanently immobilize the contaminants since
    EPA has no data on which to base such a conclusion. Fixation-
    stabilization has not been proven effective in containing PCBs or
    other organic chemicals. Although fixation/stabilization has been
    used for over 20 years (primarily for inorganic contamination),
    there is little information on the physical durability and chemical
    stability of the stabilized mass when placed in the ground. Little
    research has been conducted on the long term effects of organic
    contaminants on performance.
    
    Several types of fixation/stabilization technologies are currently
    being tested under EPA's SITE program. Because this program has
    been operating for less than 2 years, little specific information
    is available of the effectiveness of these technologies in
    immobilizing PCBs or other organics. The HAZCON process was
    evaluated at the Douglassville, PA Site in 1987. The process was
    not effective in immobilizing organic chemicals. Similar amounts
    of these chemicals leached from treated and untreated soils during
    short term leachate tests. Further, microscopic analyses of
    treated soils revealed globules of untreated organics, indicating
    that the mixing and treatment process was not completely effective.
    It should be noted that none of the technology demonstrations that
    have been carried out or planned in the near future have involved
    soils with PCB concentrations as high as those found at the Rose
    site. Thus, even if the tests conducted under the SITE program
    show promising results for PCBs, questions will remain concerning
    the applicability of those results to the Rose site.
    
    Effectiveness of Vapor Extraction
    
    GE's reference to implementation of a VOC extraction procedure to
    accompany fixation is speculative since it was never discussed in
    the draft FS prepared by GE's consultants. Further, GE's
    statement that VOCs would be destroyed is unclear. VOC extraction
    does not destroy VOCs but merely separates them from the soil.
    
    44
    
    

    -------
    EPA believes that the effectiveness of this technology may be
    limited by the Rose site soil characteristics. The Rose site
    soils are predominantly glacial till deposits. The till is
    composed of a poorly sorted and nonstratified mixture of gravel,
    sand, clay and silt. The till deposits are overlain by sand,
    silt, top soil or fill. The wide variety of soil types make the
    technical feasibility of vapor extraction questionable. Piiot
    scale study would be required to determine the feasibility of this
    technology for the Rose site.
    
    Because of the variability in the soil, the implementation of
    vapor extraction could be hindered or delayed, particularly due to
    the presence of clay and silt at the site. Depending on the soil
    porosity and moisture content, the amount of vapor present in the
    pore space of the unsaturated zone, and vapor phase contaminant
    concentrations, it could take a significant period of time to
    remove soil vapors. Also, the limited soil VOC data indicates that
    much of the VOC contamination is likely to be found below the water
    table, inaccessible to (in situ) vapor extraction. This could
    result in delay of excavation of soils for subsequent treatment
    (e.g. chemical fixation/stabilization).
    
    In addition, the vapor extraction would have no effect on the free
    product portion of the site.
    
    If vapor extraction was determined to be feasible for the site,
    the costs would need to be added to those for fixation-
    stabilization. Assuming that a vapor phase carbon adsorption
    system would be required to treat the extracted vapors, these
    costs could be quite significant, particularly if vinyl chloride
    is found. This contaminant has been detected at high levels in
    groundwater at the site. These high vinyl chloride concentrations
    resulted in a significant increase in costs for the groundwater
    treatment alternatives that involved air stripping due to the need
    for air emissions control.
    
    Finally, GE's claim that removal of VOCs from soil prior to
    excavation will eliminate health risks due to VOC emissions during
    implementation of fixation/stabilization is unsubstantiated. EPA
    believes this is unlikely for 2 reasons:
    
    1.	Inability to remove all VOCs from soil before beginning the
    fixation/stabilization process. EPA does not believe that vapor
    extraction will be completely effective at the Rose site. Based
    on the limited soil VOC data, much of the VOC contamination is
    likely to be found below the water table, inaccessible to (in
    situ) vapor extraction.
    
    2.	Release of VOCs during and after the fixation/stabilization
    process. Since vapor extraction may not be completely effective
    above the water table and will not be effective below the water
    table, soils to be treated by fixation/stabilization may contain
    VOCs. These VOCs are likely to be released during excavation of
    
    45
    
    

    -------
    contaminated soils (particularly those below the water table),
    during mixing of soil with stabilization agents in the treatment
    process, and during curing of the solidified material. Technical
    evaluations of fixation processes have shown that VOCs are released
    during the mixing stage of the fixation process. Short term (up to
    28 days) tests indicate that VOCs continue to be released at a
    steady rate as the stabilized waste cures. Differences in VOC
    concentrations between untreated and treated soils have been
    attributed to these volatilization mechanisms rather than to
    binding of the VOCs by the fixation/stabilization process.
    
    References to Other Decisions and Intent
    
    GE's reference to Congress* statement that "...it is not intended
    EPA spend millions of dollars incinerating vast amounts of
    slightly contaminated materials..." is curious. Clearly, EPA
    would not characterize the PCB soil contamination at the Rose site
    as "slightly contaminated". To the contrary, EPA Region I is
    unaware of any other NPL site nationwide with PCB levels that
    exceed those documented at the Rose site (up to 440,000 ppm PCBs).
    In addition, the estimated 15,000 cubic yards designated for
    excavation and treatment is not considered to be a "vast amount",
    and the majority of the contaminated material lies within a 1.5
    acre area.
    
    GE's reference to 2 other sites that selected fixation implies
    that the factors that lead to the choice of fixation should lead
    to a similar selection at the Rose site. While there may be some
    common factors, each site is unique and must be evaluated
    accordingly.
    
    In reference to the Liquid Disposal site in Michigan, GE notes
    that "incineration was rejected by the Agency" at this site
    because there was no clearly identifiable pattern or "hot spots"
    of contamination at the site. Clearly, this is not the case at
    the Rose site. The extent of PCB contamination is well defined
    and is localized in a relatively small area approximately 1.5
    acres in size. Further, the location of the free product area (or
    "hot spot") is defined in the western portion of the disposal
    area. As such, incineration should be technically and
    economically feasible due to the uniformly high levels of PCB
    contamination throughout much of the disposal area and the well-
    characterized distribution of this contamination.
    
    Further, although the Liquid Disposal Site ROD selected
    stabilization for soil contaminated with organic chemicals, it
    notes that the hazardous substances will not be permanently
    destroyed. The ROD also states that "...data does not exist...to
    accurately judge the long term reliability of the process. Long
    term leaching and volatilization can be expected for soluble and
    volatile organic wastes..." As a result, the ROD also calls for a
    
    46
    
    

    -------
    slurry wall around and an impermeable cap over the solidified
    material, measures not included in GE's proposal.
    
    Regarding the Sand Springs Petrochemical Complex in Oklahoma,
    
    EPA's original reasons for rejecting solidification are of
    particular interest:
    
    a)	lack of demonstrated permanence;
    
    b)	inability of solidification technologies to permanently bind
    wastes with organic contents up to 50 percent?
    
    c)	doubts about whether the stabilized material would meet RCRA
    requirements in the long term;
    
    d)	potential air emissions; and
    
    e)	the high potential for failure, compared to other remedies.
    
    It should be further noted that this site is also contaminated
    with sludges containing heavy metals, a condition which is not
    believed to exist at the Rose site.
    
    Comment 25
    
    Conclusion
    
    GE is committed to implementing a permanent solution at the Rose
    site. However, it was, and is, premature for EPA to select mobile
    incineration — or any other technology — as the preferred
    remedial solution to soil contamination. £PA does not have at its
    disposal the information that is necessary to select a remedy in
    accordance with the requirements of CERCLA § 121. GE urges EPA to
    proceed with the issuance of a ROD on the groundwater operable
    unit, but to withhold a decision on remediation of the source until
    the soil and site conditions have been more fully characterized.
    GE will proceed with the development of innovative technologies
    which hold promise for this, as well as other, PCB-contaminated
    sites. While GE develops these technologies, interim remedial
    measures will be implemented to fully protect human health and the
    environment.
    
    Response 25
    
    GE's commitment to implementing a permanent solution at the Rose
    site is speculative until GE signs a legally binding Consent
    Decree to implement a Record of Decision signed by EPA that calls
    for a permanent remedy for the Site.
    
    Since this final comment is a reiteration of previous comments,
    see previous responses (including Responses 1 through 5, 11
    through 13, and 23) and the ROD for further discussion.
    
    47
    
    

    -------
    IV. REMAINING CONCERNS
    
    At the public informational meeting held in Lanesborough on July
    20, 1988, and at the informal public hearing held on August .3,
    1988, local residents and officials discussed issues of concern as
    the site moves into the design and implementation phase of EPA's
    selected remedy for the Rose site. These issues and concerns are
    described briefly below along with statements about how EPA intends
    to address these concerns as they arise in the future.
    
    (A)	Noise
    
    Citizens expressed a strong concern that the incineration and
    excavation process be carried out in a manner that would minimize
    adverse impacts upon the community.
    
    At the July 20, 1988 public informational meeting, EPA stated the
    Agency's willingness to work with local officials to minimize the
    adverse impacts of site remediation activities and stated that
    local input will be solicited during the remedial design process
    to address local concerns.
    
    (B)	Other Hazardous Waste Sites in Lanesborough
    
    Citizens asked EPA to investigate other hazardous waste sites
    owned by the contractor who disposed wastes at the Rose site.
    
    EPA stated that the Agency is aware of the location of these
    sites, but since these sites are not on the Federal Superfund list
    (National Priorities List), EPA does not have any direct
    involvement with these sites. Only the Rose site in Lanesborough
    is on the National Priorities List and therefore qualifies for
    federal funding. However, these other sites that are of concern
    are on the Massachusetts DEQE "List of Confirmed Disposal Sites and
    Locations to be Investigated" and are being investigated by the
    State. EPA has relayed citizens1 concerns about these sites to the
    State.
    
    (C)	Groundwater Contamination
    
    Citizens urged EPA to act quickly to prevent groundwater
    contaminants from continuing to migrate from the Rose site.
    
    EPA stated that the site cleanup will be carried out by GE and
    that the EPA will pursue immediate implementation of the
    groundwater cleanup portion of the overall site remedy with GE.
    EPA further stated that the EPA will oversee all cleanup activities
    conducted by GE, including remedial design and actual construction
    activities.
    
    48
    
    

    -------
    EXHIBIT A
    
    COMMUNITY RELATIONS ACTIVITIES CONDUCTED AT THE
    
    ROSE SITE
    
    

    -------
    EXHIBIT A
    
    COMMUNITY RELATION ACTIVITIES
    CONDUCTED AT THE
    ROSE SITE
    IN LANES BOROUGH, MASSACHUSETTS
    
    Community relations activities conducted to date at the Rose
    Superfund site include:
    
    •	February 1988 - EPA conducted community interviews to assess
    community concerns related to the site and to develop specific
    plans to address those concerns.
    
    June 1988 - EPA released a fact sheet to inform the public
    about the results of the Remedial Investigation (RI)
    conducted by GE at the site.
    
    June 1988 - EPA issued a public notice announcing the
    availability of the Administrative Record and the results of
    the RI.
    
    *	July 1988 - EPA released a community relations plan
    describing citizen concerns about the site and outlining a
    program to address these concerns and how EPA intends to keep
    citizens informed about and involved in site activities.
    
    July 1988 - EPA issued a public notice to announce the time
    and place of the public informational meeting for the site and
    to invite public comment on the Feasibility Study (FS) and the
    Proposed Plan.
    
    July 1988 - EPA mailed the Proposed Plan announcing EPA's
    preferred alternative for addressing contamination at the
    site to all those on the site mailing list.
    
    July 20, 1988 - EPA conducted a site visit to familiarize
    interested citizens and local officials with the site and to
    discuss current and future EPA activities at the site.
    
    July 20, 1988 - EPA held a public informational meeting to
    discuss the results of the RI/FS and EPA's Proposed Plan.
    
    July 21 - August 19, 1988 - EPA held a public comment period
    on the Proposed Plan.
    
    August 3, 1988 - EPA held an informal public hearing to
    accept comments on the remedial alternatives evaluated in the
    FS and on the Proposed Plan.
    
    

    -------
    EXHIBIT B
    
    TRANSCRIPT FROM THE INFORMAL PUBLIC HEARING
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    I
    
    1-12
    
    UNITED STATES OF AMERICA
    ENVIRONMENTAL PROTECTION AGENCY
    
    RE: F.T. ROSE SITE SUPERFUND PROGRAM,
    
    A PUBLIC MEETING, held at the Lanesborough
    
    High School Auditorium, on Wednesday,
    August 3, 1988, commencing at 7:13 p.m.
    
    BEFORE: Sam Silverman, EPA, Chairman
    
    Mary Sanderson, Remedial. Project Manager
    
    APEX Reporting
    
    Registered Professional Reporters
    (617) 426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    INDEX
    
    SPEAKERS;	PAGE:
    
    Sam Silverman	3
    
    Mary Sanderson	6
    
    Diane Nichols	7
    
    APEX Reporting
    
    Registered Professional Reporters
    (617)426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    PROCEEDINGS
    
    (7:13 p.m.)
    
    MR. SILVERMAN: We'll begin the meeting now.
    
    Good evening and welcome. My name is Sam Silverman. I'm
    Acting Deputy Director of the Environmental Protection Agency
    -- Deputy Director of the Waste Management Division of the
    Environmental Protection Agency, Region One, in Boston.
    
    My responsibilities include managing the
    Superfund Program in the State of Massachusetts. I will
    serve as Chairman of this meeting and want to welcome you
    all here this evening.
    
    The purpose of this hearing is to formally accept
    comments on the remedial investigation endangerment
    assessment feasibility sutdy and proposed plan for remediation
    of the F.T. Rose Superfund site located here in Lanesborough.
    
    Also present today is Mary Sanderson, who is
    EPA's Site Manager for the F.T. Rose site.
    
    What I would like to do now is to describe" for
    you the format for this hearing. First, Mary will give
    you a brief overview of the proposed plan.
    
    As many of you know, EPA representatives made
    a detailed presentation of the proposed plan at -an
    informational meeting which we held here on July 20th.
    
    Following Mary's overview, we will accept any
    oral comments you may wish to make for the record. Those
    
    APEX Reporting
    
    Registered Professional Reporters
    (617)426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    of you wishing to comment should have already indicated
    your desire to do so by filling out the form we made available
    to you.
    
    Also available, if you don't already have a copy,
    is the proposed plan on the table in the middle of the
    auditorium. If you have not yet completed a form, but do
    wish to make a comment, please do so now or any other time
    during the course of the hearing.
    
    I will call on the people wishing to make statement;
    in the order in which they filled out the form. I will
    reserve the right to limit comments to ten minutes. However,
    given the low turnout, I doubt I'll have to do that.
    
    Following the comments, Mary or I may ask clarifying
    questions regarding the comments just to make sure that
    we're able to fully understand what the issues are that
    you are raising.
    
    After all the comments 4iave been heard, I will
    close the formal hearing. The purpose of tonight's hearing
    is for EPA to receive your comments. As part of the formal
    hearing, Mary and I will not be able to respond to your
    comments or questions tonight.
    
    However, after I close the formal part'of the
    hearing, Mary and I will remain available to answer any
    questions informally which you may have on issues which
    have been raised this evening or in any other aspects of
    
    APEX Reporting
    
    Registered Professional Reporters
    (617) 426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    the feasibility study and proposed plan.
    
    As you may know, the public comment on the proposed
    plan opened on July 21st and runs through August 19th.
    
    If you wish to submit written comments, and I encourage
    you to do so, they must be postmarked no later than August
    19th and mailed to our office in Boston.
    
    The appropriate address can be found on Page 2
    of the proposed plan. At the conclusion of the meeting,
    please see Mary or me if you have any questions on the process
    for making written comments.
    
    All oral comments we receive tonight and those
    we receive in writing during the comment period will be
    responded to in a document we call the Responsiveness Summary.
    
    This summary will be included with the decision
    document or record of decision that EPA prepares at the
    conclusion of the comment period. In the record of decision,
    EPA will explain which clean-up alternatives have been selectc
    for the F.T. Rose site.
    
    Are there any questions, at this time on the format
    for this evening?
    
    (No response.)
    
    Seeing that there are none, I just Wanted to
    encourage you all wishing to comment to do so now orally
    or in writing before August 19th.
    
    If anyone else has decided to make an oral comment
    
    APEX Reporting
    
    Registered Professional Reporters
    (617)426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    b
    
    tonight, please fill out one of those forms on the table
    at this time.
    
    Mary Sanderson will now open with a brief overview
    of the proposed plan for the F.T. Rose site.
    
    MS. SANDERSON: As Sam said, we were here two
    weeks ago, at which time we did a longer presentation reviewin:
    the results of the remedial investigation, the endangerment
    assessment, the feasibility study and EPA's proposed plan.
    
    I won't be doing slides or any other presentation,
    so to speak, tonight. I have brought a map later on for
    questions and answers, if you wish.
    
    What I will just briefly review is the site history,
    the disposal area, approximately one and a half acres in
    the back portion of the Rose property.
    
    The contamination is predominantly PCB's in a
    source disposal area with volatile organic contamination
    migrating from the site into plumete.
    
    The endangerment assessment form, the risks posed
    by the site to be contact with the PCB's in the disposal
    area as well as groundwater consumption in the area where
    the groundwater has become contaminated from the site.
    
    We talked about some of the options that were
    presented in the feasibility study, and EPA has proposed
    a two-part clean-up plan.
    
    We have proposed that for the groundwater treatmen :
    
    APEX Reporting
    
    Registered Professional Reporters
    (617) 426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    7
    
    portion of the contamination at the site, an air stripping
    and carbon treatment system. There would be two interceptor
    wells or trenches installed at the site where the two plumes
    are emanating from the site, and those would be treated
    by an air stripping and carbon treatment system.
    
    For the source area, the one and a half acre
    area, we are proposing excavation and on-site incineration
    of those contaminated soils.
    
    That, in a nutshell, is what several years of
    study has done, and I will leave it at that, unless people
    have questions on the proposed plan being excavation and
    on-site incineration for the source area soils and the
    groundwater, treatment air stripping with carbon treatment
    for the groundwater contamination.
    
    That, in a nutshell, I'll turn it back to Sam
    for comments.
    
    MR. SILVERMAN: Thank y5u, Mary. At this time,
    I'll start taking the comments from the audience. At present,
    the only person who indicated an interest in making an oral
    comment is Diane Nichols. Ms. Nichols, would you please
    go to the microphone and make your comments?
    
    MS. NICHOLS: As an abutter to the Rose site
    and as the owner of the business that functions at that
    site primarily on the telephone, I am opposed to any method
    which would bring excessive noise or excessive construction
    
    APEX Reporting
    
    Registered Professional Reporters
    (617)426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    .19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    disruption.
    
    My husband and I bought the property in 1987
    specifically for my telephone telemarketing business, and
    if I can't do busy, then a noisy clean-up is unacceptable
    to me.
    
    I would also insist that the Environmental
    Protection Agency do everything possible to contain the
    contamination during the clean-up process, and if that
    contamination is found to extend to my property, then that
    contamination be cleaned as well.
    
    My property was found to contain a very small
    insignificant amount of PCB-1260. That's what I understand
    is out in back of the Rose property. Right now, it's --
    we call it an unknown source.
    
    As an employer, I have had to try to keep my
    current employees informed and happy. In this type job
    market situation, I have had to tsy not to stir prospective
    employees, and I've gone through one headache after another
    with testing in my basement, testing on the property.
    
    I would support any method that the EPA would
    want to do that would be, first of all, complete and, second
    of all, permanent.
    
    If we have to go with an incinerator and such
    which is going to generate so much noise at a high cost,
    fine. We'll have to live with it. I would hope that, you
    
    APEX Reporting
    
    Registered Professional Reporters
    (617)426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    know, it could be done so that everybody is happy without
    either noise or disruption.
    
    Whatever you can do that would be the most effectiv
    the most permanent is fine. I do not support most of the
    unproven experimental methods, except probably for SM-10,
    which is the biodegradation.
    
    I do not support any of the methods which would
    not reduce the toxicity of the material. I do not support
    more solvents and more chemicals being pumped into the land
    which has already been unacceptably defiled.
    
    I particularly do not support the proposal at
    the M-6 which proposes to turn the Rose site into a hazardous
    waste site because that opens up a whole can of worms for
    other hazardous waste to be dumped there, for town garbage
    to be dumped there, et cetera.
    
    As property owner that abutts this, we've had
    enough headaches. I, personally, ""don11 want it. I think
    that public health is at stake in this particular instance
    so whatever will contain this mess from being — from more
    public exposure is fine by me.
    
    I think you should do whatever is necessary to
    clean it up for the public's good.
    
    In response to the Berkshire Eagle accounts that
    I've been reading of General Electric's position regarding
    this whole thing, I think that the GE is ultimately responsible
    
    APEX Reporting
    
    Registered Professional Reporters
    (617) 426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    10
    
    for this mess that we have on Balance Pock Road. I'm very
    tired of hearing about Berkshire County high cancer rate,
    Berkshire County's toxic waste dumps here and there that
    somehow are always traced back to a major industry, usually
    General Electric.
    
    I feel that it is General Electric's responsibility
    to do whatever is necessary to restore the land that they
    defiled, not what they find the easiest on their pocketbooks,
    but it's time that GE took full responsibility for their
    actions in regard to this environmental problem.
    
    Lastly, I would hope that the comments that we,
    as abutters, are making and the Rose family's comments weigh
    heaviest on whatever the EPA plans to do. I think that
    our feelings are more important than somebody that, say,
    lives up on North Main Street or Summer Street because we're
    the ones that are ultimately at stake here. It's our property
    and our health.	""
    
    Since the Rose family lives on the land and pays
    the taxes on that land and has had their privacy invaded
    because of all this and since they live with the albatross
    around their neck daily, I think that their opinions should
    weigh the heaviest on EPA's final recommendations.
    
    I think the Rose family has been put through
    all this and after all this deserves a break so I say let's
    give them a break, listen to them, listen to me and do whatever
    
    APEX Reporting
    
    Registered Professional Reporters
    (617) 426-3077
    
    

    -------
    1
    
    2
    
    3
    
    4
    
    5
    
    6
    
    7
    
    8
    
    9
    
    10
    
    11
    
    12
    
    13
    
    14
    
    15
    
    16
    
    17
    
    18
    
    19
    
    20
    
    21
    
    22
    
    23
    
    24
    
    25
    
    11
    
    is necessary. Thank you.
    
    MR. SILVERMAN: Thank you.
    
    (Whereupon, on August 3, 1988, the above matter
    was concluded.)
    
    APEX Reporting
    
    Registered Professional Reporters
    (617) 426-3077
    
    

    -------
    CERTIFICATE OF REPORTER AND TRANSCRIBER
    
    This is to certify that the attached proceedings
    
    before :	TIIS ENVIRONMENTAL PROTECTION flflFMCV	
    
    in the Matter of:
    
    FT ROSE SUPERFUND SITE
    
    Place:	Lanesborough High School
    
    Date:	8/3/S8
    
    were held as herein appears, and that this is the true,
    
    mm
    
    accurate and complete transcript prepared from the notes
    and/or recordings taken of the above titled proceeding.
    
    V. McCann	8/3/88
    
    Reporter	Date
    
    «
    
    S. Hayes	8/16/88
    
    Transcriber	Date
    
    

    -------
    APPENDIX B
    
    ADMINISTRATIVE RECORD INDEX
    
    

    -------
    Rose Disposal Pit
    NPL Site Administrative Record
    
    Index
    
    As of September 23, 1988
    
    Prepared for
    
    Region I
    Waste Management Division
    U.S. Environmental Protection Agency
    
    With Assistance from
    
    AMERICAN MANAGEMENT SYSTEMS, INC.
    
    One Kendall Square, Suite 2200 • Cambridge, Massachusetts 02139 • (617) 577-9915
    
    

    -------
    Introduction
    
    This document is the Index to the Administrative Record for the Rose Disposal Pit National
    Priorities List (NPL) site. Section I of the Index cites site-specific documents, and Section II cites
    guidance documents used by EPA staff in selecting a response action at the site.
    
    The Administrative Record is available for public review at EPA Region I's Office in Boston,
    Massachusetts, and at the Lanesborough Town Library, 83 North Main Street, Lanesborough,
    Massachusetts 02137. Questions concerning the Administrative Record should be addressed to the
    EPA Region I site manager.
    
    The Administrative Record is required by the Comprehensive Environmental Response,
    Compensation, and Liability Act (CERCLA), as amended by the Superfiind Amendments and
    Reauthorization Act (SARA).
    
    

    -------
    Section I
    Site-Specific Documents
    
    

    -------
    Page 1
    
    ADMINISTRATIVE RECORD INDEX
    for the
    
    Rose Disposal Pit NPL Site
    
    1.0 Pre-Remedial
    
    1.2	Preliminary Assessment
    
    1. "Preliminary Site Assessment - Rose Site," Ecology and Environment, Inc.
    (April 13, 1981).
    
    1.3	Site Inspection
    
    1. "Site Inspection Report - Rose Site - Final Report," Ecology and Environment,
    Inc. (March 22,1982).
    
    1.18 FIT Technical Direction Documents (TDDs) and Associated Records
    
    1. "Field Investigation of the Rose Site - Balance Rock Road - Final Report,"
    Ecology and Environment, Inc. (October 15,1982).
    
    2.0 Removal Response
    
    2.1	Correspondence
    
    1.	Cross-Reference: Determinations and Administrative Order, In the Matter
    of General Electric Company for the Rose Site, Docket No. 84-1025
    (May 16,1984) [Filed and cited as entry number 1 in 10.7 Administrative
    Orders].
    
    2.	Memorandum from EPA Region I to File (September 28,1984).
    
    3.0 Remedial Investigation (RI)
    
    3.2	Sampling and Analysis Data
    
    Sampling and Analysis and Contract Laboratory Program (CLP) Data
    
    for the Remedial Investigation (RI) maybe reviewed, by appointment
    
    only, at EPA Region I, Boston, Massachusetts.
    
    1. Letter from Dorothy A. McGlincy and Ellis Koch, Geraghty & Miller, Inc.
    to Grant Bowman, General Electric Company Regarding Oil Recovery
    Chronology and Analytical Results (February 8,1988).
    
    3.4	Interim Deliverables
    
    1.	"Personnel and Field Tasks - Rose Site Sampling Project," Geraghty & Miller,
    Inc. for General Electric Company (November 19, 1986).
    
    2.	"Remedial Investigation Oversight at the F.T. Rose Site - Project Operations
    Plan," Planning Research Corporation for Camp Dresser & McKee Inc.
    (December 11, 1986).
    
    

    -------
    3.6 Remedial Investigation (RI) Reports
    
    1.	"Effect of Waste Oil and Solvent Disposal on Ground-Water Quality at
    
    the Rose Site - General Electric Company," Geraghty & Miller, Inc. for General
    Electric Company (February 1984).
    
    2.	"Volume I-1986 Supplementary Investigation at the Rose Site,
    
    Lanesborough, Massachusetts - General Electric Company,"
    
    Geraghty & Miller, Inc. (February 1987).
    
    3.10 Endangerment Assessments
    
    Endangerment Assessments
    
    1.	"Endangerment Assessment Report for the Frank T. Rose Site,"
    
    Geraghty & Miller, Inc. for General Electric Company (June 1988).
    
    Endangerment Assessments Comments
    
    2.	Comments Dated February 17,1988 from Mary C. Sanderson,
    
    EPA Region I on the June 1988 "Endangerment Assessment Report
    
    for the Frank T. Rose Site," Geraghty & Miller, Inc. for General Electric
    Company.
    
    3.	Comments from EPA on the June 1988 "Endangerment Assessment
    
    Report for the Frank T. Rose Site," Geraghty & Miller, Inc. for General Electric
    Company.
    
    Feasibility Study (FS)
    
    4.1	Correspondence
    
    1. Letter from Maiy C. Sanderson for Richard Cavagnero, EPA
    Region I to Robert Bois, Commonwealth of Massachusetts
    Department of Environmental Quality Engineering Regarding
    Proposed Plan, Site Schedule and ARARs (June 23,1988).
    
    4.2	Sampling and Analysis Data
    Sampling and Analysis Data
    
    1.	"Rose Site Ground-Water Treatability Report," Blasland & Bouck
    Engineers, P.C. for General Electric Company (January 1988).
    
    2.	Cross Reference: Letter from Dorothy A. McGlincy, Geraghty &
    
    Miller, Inc. to Grant Bowman, General Electric Company
    Regarding Oil Recovery Chronology and Analytical Results .
    
    (February 8,1988) [Filed and cited as entry number 1 in 3.2
    Sampling and Analysis Data].
    
    Sampling and Analysis Data Comments
    
    3.	Comments Dated February 17,1988 from Maiy C. Sanderson,
    
    EPA Region I on the January 1988 "Rose Site Ground-Water
    Treatability Report," Blasland & Bouck Engineers, P.C. for
    General Electric Company.
    
    

    -------
    Page 3
    
    4.4	Interim Deliverables
    
    Interim Deliverables
    
    1.	"Ground-Water Treatability Plan," Blasland & Bouck Engineers, P.C.
    for General Electric Company (November 1987).
    
    2.	'Teasibility Study Detailed Analysis of Alternatives
    (Sections 1,2 & 3 only)," Blasland & Bouck Engineers, P.C.
    for General Electric Company (November 1987).
    
    Interim Deliverables Comments
    
    3.	Comments Dated December 11,1987 from Mary C. Sanderson,
    EPA Region I on the November 1987 "Ground-Water Treatability
    Plan," Blasland & Bouck Engineers, P.C. for General Electric
    Company.
    
    4.	Comments Dated December 11,1987 from Mary C. Sanderson,
    EPA Region I on the November 1987 "Feasibility Study Detailed
    Analysis of Alternatives (Sections 1,2 & 3 only)," Blasland & Bouck
    Engineers, P.C. for General Electric Company.
    
    5.	Comments Dated December 30,1987 from Stephen F. Joyce,
    Commonwealth of Massachusetts Department of Environmental
    Quality Engineering on the November 1987 "Feasibility Study
    Detailed Analysis of Alternatives (Sections 1,2 & 3 only),"
    
    Blasland & Bouck Engineers, P.C. for General Electric Company.
    
    4.5	Applicable or Relevant and Appropriate Requirements (ARARs)
    
    1.	Letter from Robert K. Goldman, Blasland & Bouck Engineers,
    
    P.C. for General Electric Company to Mary C. Sanderson, EPA
    Region I (March 17,1988).
    
    2.	Letter from William Walsh-Rogalski, EPA Region I to Ann
    Bingham, Commonwealth of Massachusetts Department of
    Environmental Quality Engineering (August 18,1988).
    
    4.6	Feasibility Study (FS) Reports
    
    Feasibility Study (FS) Reports
    
    1.	"Feasibility Study - Initial Screening of Alternatives (Revision No. 1) - Rose
    Site," Blasland & Bouck Engineers, P.C. for General Electric Company
    (March 1986).
    
    2.	"Feasibility Study - Initial Screening of Alternatives (Revision No. 2) - Rose
    Site," Blasland & Bouck Engineers, P.C. for General Electric Company
    (June 1987).
    
    3.	Draft - "Feasibility Study," Blasland & Bouck Engineers, P.C. for
    General Electric Company (March 1988).
    
    4.	"Feasibility Study," Blasland & Bouck Engineers, P.C. for
    General Electric Company (June 1988).
    
    Feasibility Study (FS) Reports Comments
    
    5.	Cross Reference: Letter from Robert K. Goldman, Blasland &
    
    Bouck Engineers, P.C. for General Electric Company to Mary C.
    
    Sanderson, EPA Region I (March 17,1988) [Filed and cited as
    entry number 1 in 4.5 Applicable or Relevant and Appropriate
    Requirements (ARARs)].
    
    

    -------
    4.6 Feasibility Study (FS) Reports Comments (cont'd.)
    
    6.	Comments Dated May 12,1988 from Mary C. Sanderson, EPA
    Region I on the March 1988 Draft "Feasibility Study," Blasland & Bouck
    Engineers, P.C. for General Electric Company.
    
    7.	Comments from EPA Region I on the June 1988 "Feasibility
    
    Study," Blasland & Bouck Engineers, P.C. for General Electric Company.
    
    4.9 Proposed Plans for Selected Remedial Action
    
    Proposed Plans for Selected Remedial Action
    
    1. "EPA Proposes Cleanup Plan for the F.T. Rose Superfund Site,"
    
    EPA Region I (July 1988).
    
    Proposed Plans for Selected Remedial Action Comments
    
    Comments on the Proposed Plan received by EPA Region I during the formal
    
    public comment period are filed and cited in 5.3 Responsiveness Summaries.
    
    Record of Decision (ROD)
    
    5.1	Correspondence
    
    1. Memorandum from Mary C. Sanderson, EPA Region I to John
    Zipeto, EPA Region I (July 1,1988).
    
    5.2	Applicable or Relevant and Appropriate Requirements (ARARs)
    
    1. Cross Reference: All Applicable or Relevant and Appropriate Requirements
    (ARARs) for the Record of Decision are in Section XI of the Record of
    Decision [Filed and cited as entry number 1 in 5.4 Record of Decision (ROD)].
    
    5.3	Responsiveness Summaries
    
    1.	Cross Reference: Responsiveness Summary is Appendix A of the Record of
    Decision [Filed and cited as entry number 1 in 5.4 Record of Decision (ROD)].
    
    The following citations indicate documents received by EPA Region I during the
    
    formal public comment period.
    
    2.	Comments Dated August 9,1988 from Diane and William Nichols,
    
    Allegro Tech, Inc. on the July 1988 "EPA Proposes Cleanup Plan
    for the F.T. Rose Superfund Site," EPA Region I.
    
    3.	Comments Dated August 16,1988 from Darlene A. White on Jhe
    July 1988 "EPA Proposes Cleanup Plan for the F.T. Rose
    Superfund Site," EPA Region I.
    
    4.	Comments Dated August 18,1988 from Robert A. Matthews and
    Peter L. Gray, McKenna, Conner & Cuneo for General Electric
    Company on the July 1988 "EPA Proposes Cleanup Plan for the
    F.T. Rose Superfund Site," EPA Region L
    
    5.	Errata Sheet to Comments Dated August 18,1988 from Peter L.
    
    Gray, McKenna, Conner & Cuneo for General Electric Company
    on the July 1988 "EPA Proposes Cleanup Plan for the F.T. Rose
    Superfund Site," EPA Region I (September 6,1988).
    
    6.	Transcript, Public Meeting for the F.T. Rose Site (August 3,1988).
    
    

    -------
    ± 05^ ^
    
    5.4 Record of Decision (ROD)
    
    1. Record of Decision, EPA Region I (September 23,1988).
    
    10.0 Enforcement
    
    10.3 State and Local Enforcement Records
    
    1. Letter from Stephen F. Joyce, Commonwealth of Massachusetts Department of
    Environmental Quality Engineering to Ronald Desgroseilliers, General Electric
    Company (April 2,1984).
    
    10.7 EPA Administrative Orders
    
    1.	Determinations and Administrative Order, In the Matter of General Electric
    Company for the Rose Site, Docket No. 84-1025 (May 16,1984).
    
    2.	Determinations and Administrative Order, In the Matter of General Electric
    Company for the Rose Site, Docket No. 84-1059 (November 21,1984).
    
    3.	Administrative Order by Consent, In the Matter of General Electric Company for
    the F.T. Rose Site, Docket No. 88-1010 (March 22,1988).
    
    11.0 Potentially Responsible Party (PRP)
    
    11.9 PRP-Specific Correspondence
    
    1.	Letter from Leslie Carothers, EPA Region I to Peter Traversa (May 14,1982).
    
    2.	Letter from Peter Traversa to RCRA Compliance Clerk, EPA Region I
    (May 24,1982).
    
    13.0 Community Relations
    
    13.2	Community Relations Plans
    
    1. "Final Community Relations Plan," ICF Technology Incorporated for Ebasco
    Services, Inc. (July 1988).
    
    13.3	News Clippings/Press Releases
    
    1.	"Environmental News - EPA Issues Consent Order For F.T. Rose
    Site," EPA Region I (March 23,1988).
    
    2.	News Clipping Announcing the Availability of the Administrative Record for
    Public Review, Berkshire Eagle - Pittsfield, MA (June 14,1988).
    
    3.	"Environmental News - Public Meeting To Explain Proposed
    Cleanup Plan For The F.T. Rose Superfund Site," EPA Region I
    (July 12,1988).
    
    4.	News Clipping Inviting Public Comment on the Feasibility Study and the
    Proposed Plan for the F.T. Rose Site, Berkshire Eagle - Pittsfield, MA
    (July 18,1988).
    
    13.4	Public Meetings
    
    1.	"Summary of the Public Informational Meeting on the Remedial Investigation,
    Feasibility Study, and Proposed Plan for the F.T. Rose Superfund Site," ICF
    Technology Incoiporated (July 20,1988).
    
    2.	Cross Reference: Transcript, Public Meeting for the F.T. Rose Site
    (August 3,1988) [Filed and cited as entry number 6 in 5.3 Responsiveness
    Summaries].
    
    

    -------
    Page 6
    
    13.5 Fact Sheets
    
    1.	"EPA and General Electric Announce Investigation Results for the F.T. Rose
    Site," EPA Region I (June 1988).
    
    2.	Cross Reference: "EPA Proposes Cleanup Plan for the F.T. Rose Superfund
    Site," EPA Region I (July 1988) [Filed and cited as entry number 1 in 4.9
    Proposed Plans for Selected Remedial Action].
    
    17.0 Site Management Records
    17.4 Site Photographs/Maps
    
    The record cited in entry number I may be reviewed, by appointment only, at
    
    EPA Region I, Boston, Massachusetts.
    
    1. "Site Analysis - Lanesborough Sites," U.S. EPA Environmental Monitoring
    Systems Laboratory (April 1985).
    
    17.7 Reference Documents
    
    1.	'Transportable Circulating Bed Hazardous Waste Incinerator for
    Thermal Treatment of Soils, Sludges and Oils," Ogden
    Environmental Services, Inc. for Camp Dresser & McKee Inc.
    
    (June 5,1987).
    
    2.	Letter from Ronald F. Desgroseilliers, General Electric Company
    to Mary C. Sanderson, EPA Region I (June 15, 1988) with
    Attachment Dated June 1,1988 entitled "Research and Development
    Program for the Destruction of PCBs."
    
    3.	Letter from Mark R. Harkness, General Electric Company to
    Ronald F. Desgroseilliers, General Electric Company
    (September 6, 1988).
    
    4.	"Site Demonstration of Hazcon Solidification/Stabilization
    Process," Paul R. de Percin, EPA Hazardous Waste Engineering
    Research Laboratory and Stephen Sawyer, Enviresponse Inc.
    
    5.	"U.S. EPA Research in Solidification/Stabilization of Waste
    Material," Carlton C. Wiles and Hinton K. Howard, EPA
    Hazardous Waste Engineering Research Laboratory.
    
    6.	"Evaluation of Solidification/Stabilization as a Best Demonstrated
    Available Technology," Leo Weitzman and Lawrence E. Hamel,
    
    Acurex Corporation and Edwin Barth, EPA Hazardous Waste
    Engineering Research Laboratory.
    
    7.	"TCLP as a Measure of Treatment Effectiveness: Results of TCLP
    Work Completed on Different Treatment Technologies for
    CERCLA Soils," Robert C. Thurnau, EPA Hazardous Waste
    Engineering Research Laboratory and M. Pat Esposito, PEI
    Associates, Inc.
    
    

    -------
    Section II
    Guidance Documents
    
    

    -------
    Page 7
    
    GUIDANCE DOCUMENTS
    
    EPA guidance documents may be reviewed at EPA Region I, Boston, Massachusetts.
    
    General EPA Guidance Documents
    
    1.	Comprehensive Environmental Response. Compensation, and Liability Act of 1980. amended
    October 17,1986.
    
    2.	Letter from Lee M. Thomas to James J. Florio, Chairman, Subcommittee on Consumer
    Protection and Competitiveness, Committee on Energy and Commerce, U.S. House of
    Representatives, May 21,1987 (discussing EPA's implementation of the Superfund
    Amendments and Reauthorization Act of 1986).
    
    3.	Memorandum from Gene Lucero to the U.S. Environmental Protection Agency,
    
    August 28,1985 (discussing community relations at Superfund Enforcement sites).
    
    4.	Memorandum from J. Winston Porter to Addressees ("Regional Administrators, Regions I-X;
    Regional Counsel, Regions I-X; Director, Waste Management Division, Regions I, IV, V,
    VH,and VIII; Director, Emergency and Remedial Response Division, Region II; Director,
    Hazardous Waste Management Division, Regions HI and VI; Director, Toxics and Waste
    Management Division, Region IX; Director, Hazardous Waste Division, Region X;
    Environmental Services Division Directors, Region I, VI, and VTT), July 9,1987 (discussing
    interim guidance on compliance with applicable or relevant and appropriate requirements).
    
    5.	"National Oil and Hazardous Substances Pollution Contingency Plan," Code of Federal
    Regulations (Title 40, Part 300), 1985.
    
    6.	U.S. Environmental Protection Agency. Office of Emergency and Remedial Response.
    Community Relations in Superfund: A Handbook interim Version^ (EPA/HW-6),
    
    September 1983.
    
    7.	U.S. Environmental Protection Agency. Office of Emergency and Remedial Response. Draft
    Guidance on Remedial Actions for Contaminated Groundwater at Superfund Sites (QSWER
    Directive 9283.1-2), October 1986.
    
    8.	U.S. Environmental Protection Agency. Office of Emergency and Remedial Response. Draft
    Guidance on Remedial Actions for Contaminated Groundwater at Superfund Sites (QSWER
    Directive 9283.1-2), April 1988.
    
    9.	U.S. Environmental Protection Agency. Office of Emergency and Remedial Response.
    Superfund Public Health Evaluation Manual (OSWER Directive 9285.4-1), October 1986.
    
    10.	U.S. Environmental Protection Agency. Office of Emergency and Remedial Response.
    Superfund Remedial Design and Remedial Action Guidance fQSWER Directive 9355.0-4A),
    June 1986.
    
    11.	U.S. Environmental Protection Agency. Office of Ground-Water Protection. Ground-Water
    Protection Strategy. August 1984.
    
    12.	U.S. Environmental Protection Agency. Office of Health and Environmental Assessment. A
    Compendium of Technologies Used in the Treatment of Hazardous Waste
    (EPA7625/8-87/014), September 1987.
    
    13.	U.S. Environmental Protection Agency. Office of Research and Development Environmental
    Research Laboratory. EPA Guide for Minimizing the Adverse Environmental Effects of
    Cleanup of Uncontrolled Hazardous Waste Sites. (EPA-600/8-85/008) June 1985.
    
    

    -------
    Page 8
    
    General EPA Guidance Documents (cont'd.)
    
    14.	U.S. Environmental Protection Agency. Office of Research and Development Hazardous
    Waste Engineering Research Laboratory. Handbook for Stabilization/Solidification of.'
    Hazardous Wastes (EPA/540/2-86/001). June 1986.
    
    15.	U.S. Environmental Protection Agency. Office of Solid Waste and Emergency Response.
    Data Quality Objectives for Remedial Response Activities: Development Process
    (EPA/540/G-87/003), March 1987.
    
    16.	U.S. Environmental Protection Agency. Office of Solid Waste and Emergency Response.
    Guidance on Feasibility Studies under CERCLA (Comprehensive Environmental Response.
    Compensation, and Liability Actt (EPA/540/G-85/003), June 1985.
    
    17.	U.S. Environmental Protection Agency. Office of Solid Waste and Emergency Response.
    Guidance on Remedial Investigations under CERCLA (Comprehensive Environmental
    Response. Compensation, and Liability AcO (EPA/540/G-85/002), June 1985.
    
    18.	U.S. Environmental Protection Agency. Office of Solid Waste and Emergency Response.
    Interim Guidance on Superfund Selection of Remedy (OSWER Directive 9355.0-19),
    December 24,1986.
    
    Rose Disposal Pit NPL Site Specific Guidance Documents
    
    1.	"PCB Spill Cleanup Policy," (40 CFR Part 761), Federal Register. April 2,1987.
    
    2.	U.S. Environmental Protection Agency. Office of Health and Environmental Assessment
    Develonment of Advisory Levels for Polvchlorinated Biphenvis (PCBs) Cleanup
    (OHEA-E-187), May 1986.
    
    3.	U.S. Environmental Protection Agency. Office of Health and Environmental Assessment
    Development of Statistical Distribution or Ranges Standard Factors Used in Exposure
    Assessments (OHEA -E-161), March 1985.
    
    4.	U.S. Environmental Protection Agency. Office of Health and Environmental Assessment
    Drinking Water Criteria Document For Polvchlorinated Biphenvis (PCBsl (ECAO-CIN-414),
    May 1987.
    
    5.	U.S. Environmental Protection Agency. Office of Health and Environmental Assessment
    Risk Analysis of TCDD Contaminated Soil (EPA-600/8-84-03n. 1984.
    
    6.	U.S. Environmental Protection Agency. Office of Solid Waste and Emergency Response.
    The Superfund Innovative Technology Evaluation Program: Progress and Accomplishments
    (EPA/540/5-88/001), February 1988.
    
    7.	Lagoy, P.K., "Estimated Soil Ingestion Rates for Use in Risk Assessment," Risk Analysis
    (7: 355-360), 1987.
    
    

    -------
    APPENDIX C
    
    STATE CORRESPONDENCE
    
    

    -------
    APPENDIX D
    
    CALCULATION OF SOIL VOLUMES TO BE EXCAVATED
    
    

    -------
    ESTIMATED EXCAVATION VOLUME
    
    EPA estimated the volume of soil that would have to be excavated
    from the Rose site disposal area to remove (1) all soil above the
    water table contaminated at PCB levels higher than 13 ppm and (2)
    highly contaminated soil that lies below the water table in the
    western half of the disposal area. The highly contaminated soil
    is located near wells 38A, 42A, and 43A; one well is currently
    being pumped to recover and oil and water mixture from below the
    water table. Removal of PCB-contaminated soil to the water table
    will eliminate risks due to ingestion of and dermal contact with
    PCB-contaminated soil. Removal of the source material below the
    water table will reduce the duration of groundwater treatment.
    
    Volume of PCB-Contaminated Soil Above Water Table
    
    EPA used the following methods and assumptions to estimate the
    amount of soil above the water table with PCB concentrations
    higher than 13 ppm. First, EPA assumed that the areal extent of
    13 ppm PCB contamination was approximately equal to the covered
    disposal area. The basis for this assumption is as follows:
    
    o Review of Figures 9 through 13 of the Rose site EA
    
    (Geraghty & Miller, 1988) indicates that, to a depth of
    10 feet, the areal extent of 50 ppm PCB contamination is
    approximately the same as or slightly smaller than the
    disposal area.
    
    o Examination of PCB concentrations for data points
    
    between the 1 ppm and 50 ppm isopleths on. Figures 9
    through 13 of the Rose EA indicates that the areal
    extent of 13 ppm contamination is not much larger that
    the extent of 50 ppm contamination.
    
    EPA divided each half of the disposal area (eastern and western)
    into three subareas to estimate the areal extent of 13 ppm
    
    

    -------
    contamination. These subareas are shown on Figure 5-1. Next, EPA
    used a planimeter to measure the square footage of each subarea.
    Finally, EPA estimated the depth to the water table for each
    subarea by overlaying topographic and water table maps for the site
    (Geraghty & Miller, 1987, Figures 2 and 5). The depth to the water
    table was estimated as the difference between the topographic
    surface and the shallow groundwater surface. For each subarea, EPA
    multiplied the surface area by the depth to water table to estimate
    the volume of soil to be excavated. This approximation assumes
    that excavation will proceed directly down from the surface to the
    water table; that is, the estimated volume does not consider any
    side slope contingencies. The estimated excavation volumes for the
    eastern and western halves of the disposal area are 3,278 cubic
    yards and 4,554 cubic yards, respectively. Calculations for these
    volumes are included in Table 5-3.
    
    Volume of PCB-Contaminated Soil Below Water Table
    
    EPA used the following methods and assumptions to estimate the
    amount of highly contaminated soil to be excavated below the water
    table. First, EPA reviewed the cross-section of the disposal area
    shown on Figure 19 of the EA (Geraghty & Miller, 1988). This
    cross-section passes through the most highly contaminated part of
    the western half of the disposal area, near wells 38A, 42A, and
    43A. The cross-section is reproduced here as Figure 5-2.
    
    Next, EPA outlined the most highly contaminated portion of the
    cross-section. The highly contaminated portion extends vertically
    from the surface to the bottom of the 5,000 ppm isopleth and
    horizontally from the northern edge of the 5,000 ppm, isopleth to
    the location of boring 45. EPA measured the area of this cross-
    section by planimeter as 1,320 square feet.
    
    Finally, EPA calculated an excavation volume by projecting this
    area over the average linear distance across the western half of
    the disposal area, going from southwest to northeast. EPA
    
    

    -------
    estimated the average linear distance as 110 feet. The surface
    area of this projection is shown on Figure 5-3. This excavation
    volume is based on the conservative assumption that all soil
    across the disposal area will have PCB concentrations equal to
    those in the cross-section. It is more likely that concentrations
    will decrease near the edges of the disposal area. The excavation
    volume can be calculated as
    
    (1,320 ft2) x (110 ft) x (1 yd3 / 27 ft3) - 5,378 yd3
    
    This volume must be corrected to avoid double counting soil above
    the water table that has already been included in the excavation
    volume estimated in Table 5-3. The correction equals the projected
    surface area of the deep excavation from Figure 5-3 times the depth
    to the water table. EPA estimated the projected surface area as
    6,600 square feet and the depth to the water table as 7 feet (a
    weighted average for the western half of the disposal area, based
    on the data presented in Table 5-3). The volume to be subtracted
    is
    
    (6,600 ft2) x (7 ft) x (1 yd3 / 27 ft3) «	1,711 yd3
    
    Thus, the total excavation volume for the western half of the
    disposal area, above and below the water table, is
    
    (4,554 yd3) + (5,378 yd3) - (1,711 yd3) =	8,221 yd3
    
    With the addition of the excavation volume for the eastern half of
    the disposal area (3,278 cubic yards), the total excavation volume
    for the site is 11,499 cubic yards.
    
    EPA repeated this process assuming that excavation below the water
    table will be carried out with 3-to-l side slopes to comply with
    Occupational Safety and Health Administration (OSHA) requirements.
    That is, the excavation must extend three feet horizontally for
    every one foot of depth. Figure 5-2 shows the cross-section
    through the highly contaminated portion of the disposal area,
    
    

    -------
    accounting for 3-to-l side slopes. EPA measured the area of this
    cross-section by planimeter as 2,409 square feet.
    
    EPA then projected this area across the western half of the
    disposal area, going from southwest to northeast. EPA estimated
    the average linear distance of the projection as 143 feet. This
    distance should be sufficient to allow side slopes on all four
    sides of the excavation. The surface area of this projection is
    shown on Figure 5-3. The excavation volume can be calculated as
    
    (2,409 ft2) x (143 ft) x (1 yd3 / 27 ft3) -	12,579 yd3
    
    Again, this volume must be corrected to avoid double counting soil
    above the water table that has already been included in the
    excavation volume estimated in Table 5-3. The correction equals
    the projected surface area of the deep excavation within the
    boundary of the disposal area (Figure 5-3) times the depth to the
    water table. EPA estimated the projected surface area as 11,580
    square feet and the depth to the water table as 7 feet (a weighted
    average for the western half of the disposal area, based on the
    data presented in Table 5-3). The volume to be subtracted is
    
    (11,580 ft2) x (7 ft) x (1 yd3 / 27 ft3) =	3,002 yd3
    
    Thus, the total excavation volume for the western half of the
    disposal area, above and below the water table with 3-to-l side
    slopes, is
    
    (4,554 yd3) + (12,579 yd3) - (3,002 yd3) =	14,131 yd3
    
    With the addition of the excavation volume for the eastern half of
    the disposal area (3,278 cubic yards), the total excavation volume
    for the site is 17,409 cubic yards.
    
    

    -------
    It should be noted that EPA has used an approximate soil volume of
    15,000 cubic yards as an estimate for the ROD and for cost
    estimating purposes. This amount is between the minimum 11,500
    cubic yard volume and the 17,500 cubic yard volume which includes
    additional soil for 3-to-l side slopes during excavation. EPA
    believes that the 15,000 cubic yard volume is a reasonable
    estimate of the soil volume that may actually need to be excavated
    to meet the cleanup goals, including the volume of pond sediments
    that will need to excavated in addition to the disposal area soil.
    
    

    -------
    TABLE 5-3
    
    VOLUME OF PCB-CONTAMINATED SOIL
    TO BE EXCAVATED ABOVE WATER TABLE
    
    Depth to Water	Excavation
    
    Subarea	Surface Area (ft2'!	Table (ft)	Volume (vd3) 1
    
    East — A	700	5	130
    
    East — B	6,967	10	2,580
    
    East — C	1,533	10	568
    
    East — Total	3,278
    
    West — A	1,867	10	691
    
    West — B	11,400	7	2,956
    
    West — C	4,900	5	907
    
    West — Total	4,554
    
    Total -- East + West	7,832
    
    Note: 1 Excavation volume = (Surface area, ft2) x (Depth to water table, ft)
    
    x (1 yd3 / 27 ft3)
    
    

    -------
    i
    
    I
    
    
    
    0	100	200
    
    1	I l l 1
    
    SCALE IN FEET
    
    LEGEND
    
    + WELL LOCATION
    
    	DISPOSAL AREA BOUNDARY
    
    SWAMP
    
    FIGURE 5-1
    SUBAREAS USED TO ESTIMATE
    VOLUMES OF PCB—CONTAMINATED
    SOIL TO BE EXCAVATED ABOVE
    WATER TABLE
    
    9/19/88	ROSEAREA.DWG
    
    PRC ENVIRONMENTAL MANAGEMENT, INC.
    
    

    -------
    NORTH
    
    SOUTH
    
    ¦CROSS-SECTION OF DEEP
    
    2
    
    Ld
    
    <
    LlJ
    CO
    
    £
    o
    m
    <
    
    Ui
    lxl
    
    2
    O
    F=
    <
    >
    LlI
    
    LJ
    
    BORING NUMBER
    LAND SURFACE
    BOREHOLE
    
    UNE OF CONCENTRATION
    _ AROCLORS (PPM)
    
    ADAPTED FROM: GERAGHTY AND MILLER. 1988
    
    FIGURE 5-2
    CROSS-SECTION OF DEEP
    EXCAVATION IN WESTERN
    HALF OF DISPOSAL AREA
    
    9/15/88
    
    ROSECROS.DWG
    
    PRC ENVIRONMENTAL MANAGEMENT. INC.
    
    

    -------
    I
    
    PROJECTED SURFACE AREA OF
    DEEP EXCAVATION, 3-TO-1
    SIDE SLOPES
    
    EAST
    
    DISPOSAL
    
    AREA
    
    CROSS-SECTION
    FROM FIGURE 5-2
    
    WEST
    
    DISPOSAL
    
    AREA
    
    PROJECTED SURFACE AREA
    OF DEEP ZONE EXCAVATION
    
    ADAPTED FROM: GERAGHTY AND MILLER, 1988.
    
    J
    
    50
    
    SCALE IN FEET
    
    100
    
    LEGEND
    
    -f B40 LOCATION AND NUMBER OF
    SOIL BORING
    
    	DISPOSAL AREA BOUNDARY
    
    UNE OF 50 ppm TOTAL
    AROCLOR CONCENTRATION
    
    FIGURE 5-3
    
    SURFACE AREAS OF DEEP
    EXCAVATION IN WESTERN HALF
    OF DISPOSAL AREA
    
    9/19/88
    
    ROSESUR.DWG
    
    PRC ENVIRONMENTAL MANAGEMENT. INC.
    
    

    -------
    APPENDIX E
    
    CALCULATION OF PCB SOIL CLEANUP LEVEL
    
    

    -------
    APPENDIX £
    
    PCB Soil Cleanup Level for Rose Site
    
    The PCB soil cleanup level for the Rose Site is recommended to be
    13 ppm. The calculation is based on the following assumptions
    which are considered to be reasonable by the U.S. Environmental
    Protection Agency (EPA) for the potential land use of the site as
    a residential area.
    
    Based on information in the references listed at the end of this
    Appendix, EPA makes the following assumptions; these assumptions
    
    represent the average over a lifetime:
    
    EPA	GE
    
    Body Weight of exposed person(kg):	70	70
    
    Dermal contact rate (mg/day):	500	43.5
    
    Dermal absorption factor:	0.02	0.02
    
    Soil dermal dose (mg/kg/day):	0.143	0.012
    
    Soil ingestion rate (mg/day):	54	43.5
    
    Ingestion absorption factor:	0.30	1.00
    
    Soil ingestion dose (mg/kg/day):	0.231	0.621
    
    Total soil dose (mg/kg/day):	0.374	0.633
    
    Days of exposure per year:	100	36
    
    Years of exposure per 70 year lifetime:	70	52
    
    Cancer potency factor (CPF) (mg/kg/day)-1:	7.7	4.34
    
    Risk-based soil cleanup level for PCBs (ppm)	13	64
    
    The body weight of 70 kg is EPA's standard assumption for the
    adults for a lifetime of 70 years. Individuals can be exposed
    for 100 days in a year to the contaminated soil in residential
    areas. Based on the conditions of this site, EPA is using 100
    days per year as an assumed annual average exposure over a
    lifetime. (See EPA, 1984 for a discussion of exposure duration.)
    Dermal contact rate is a function of the skin surface area
    available for exposure to soil and the soil deposition rate per
    unit of the surface area. EPA assumes that half of a person's
    upper and lower extremities will be exposed to the contaminated
    soil (EPA, 1985) with a soil deposition rate of 0.5 mg/cm2 (EPA,
    
    

    -------
    1984). The dermal absorption factor for PCBs in soil is assumed
    to be 0.02 (2%) as described in the Endangerment Assessment
    Report for the Rose Site.
    
    Dermal contact rate = Skin surface area x dermal contact rate
    (mg/day)
    
    Soil dermal dose (mg/kg/day) = (Dermal contact rate x dermal
    
    absorption factor)/body weight
    
    Soil ingestion rates vary with the age groups with the average
    ranging from 50 mg/day to 100 mg/day (LaGoy, 1987). It is assumed
    an ingestion rate of 100 mg/day for 5 years and 50 mg/day for the
    remaining of the lifetime (65 years). For the purpose of this
    calculation, EPA is using a calculated average value of 54 mg/day
    for the lifetime exposure. The ingestion absorption factor of 0.3
    (30%) for PCBs in soil is used (EPA, 1986).
    
    Soil ingestion dose = (Soil ingestion rate x ingestion
    (mg/day)	absorption factor)/body weight
    
    The exposure dose from inhalation is considered insignificant.
    
    Total soil dose = soil dermal dose + soil ingestion dose
    
    A CPF of 7.7 (mg/kg/day)-1 currently recommended by the U.S. EPA
    (EPA, 1987) is used.
    
    PCB Cleanup Level base on the lifetime cancer risk of 10~5
    
    = 10~5 / [(total soil dose ) x (1 kg soil/106 mg soil)
    x (days of exposure/365 days) x (years of
    exposure/70 years) x CPF)]
    
    = 10~5 / [0*374 x (1 kg soil/106 mg soil) x (100 /365)
    X (70 /70) X 7-7]
    
    = 13 ppm
    
    REFERENCES:
    
    LaGoy, P. K. (1987) Estimated Soil Ingestion Rates for Use in
    Risk Assessment, Risk Analysis, 7: 355-360.
    
    U.S. EPA (1984) Risk Analysis of TCDD Contaminated Soil, Exposure
    Assessment Group, Office of Health and Environmental Assess-
    ment, Washington, D.C., EPA-600/8-84-031
    
    U.S. EPA (1985) Development of Statistical Distribution or Ranges
    Standard Factors Used in Exposure Assessments, Office of
    Health and Environmental Assessment, Washington, D.C., March
    1985, OHEA-E-161.
    
    

    -------
    U.S. EPA (1986) Development of Advisory Levels for Poly-
    
    chlorinated Biphenyls (PCBs) Cleanup, Exposure Assessment
    Group, Office of Health and Environmental Assessment,
    Washington, D.C., May 1986, OHEA-E-187.
    
    U.S. EPA (1987) Drinking Water Criteria Document for Poly-
    
    chlorinated Biphenyls (PCBs), Office of Health and Environ-
    mental Assessment, ECAO-CIN-414.
    
    

    -------
    APPENDIX F
    
    CALCULATION OF ADJUSTED COST ESTIMATES
    
    

    -------
    Alternatives GW-1 and GW-1A (Air-Stripping/Activated Carbon):
    
    Capital Costs
    
    Item
    
    Estimated Cost
    
    GW-1
    
    1.	Groundwater Collecion System	$ 145,000
    
    2.	Air Stipper, 30" diameter	45,000
    
    3.	Liquid Phase
    
    Activated Carbon Units (2)	24,000
    
    4.	Backwash Pump and Controls	5,000
    
    5.	Prefabricated Building	18,000
    
    6.	Site Preparation	5,000
    
    7.	Electrical Supply	15,000
    
    8.	Pumps, Piping and Instrumentation	9,000
    
    9.	Receiving Tanks (2)	3,000
    
    10.	H2O2 Metering Pumps (2) and Controls	-
    
    11.	Baffled Tank (Pretreatment)
    
    12.	Green Sand Filter
    
    13.	Oil/Water Separator (10 gpm)	5,000
    
    14.	Vapor Phase
    
    Activated Carbon Unit (1)	50.000
    
    Subtotal	$ 324,000
    
    Administrative &
    
    Engineering (15%)	48,600
    
    Subtotal	372,600
    
    Contingency (25%)	93.150
    
    Total	$ 465,750
    
    Rounded to	$ 466,000
    
    GW-1A
    $ 145,000
    40,000
    
    24,000
    5,000
    18,000
    5,000
    15,000
    13,000
    3,000
    6,000
    8,000
    13,000
    5,000
    
    50.000
    $ 350,000
    
    52,500
    402,500
    100.625
    $ 503,000
    $ 503,000
    
    

    -------
    Alternatives GW-1 and GW-lA (Air Stripping/Activated Carbon):
    
    O&K Costs
    
    Item
    
    1.	Energy
    
    GW-1 (19,300 kwh/yr at 7.5c/kwh) $
    GW-la (22,800 kwh/yr at 7.5c/kwh)
    
    2.	Liquid Phase Activated Carbon
    Replacement (200 lb/year)
    
    3.	Vapor Phase Activated Carbon System*
    
    4.	Hydrogen Peroxide
    (40 lb/day § 65c/lb)
    
    5.	Labor
    
    a)	Treatment System (8 hrs/week)
    
    b)	Collection System (1.1 hr/week)
    
    6.	Maintenance Supplies (3% of capital)
    
    7.	Monitoring
    
    a) Groundwater/Surface Water
    
    b) Treatment System
    (24 samples)
    
    Total Annual Cost
    
    Present Worth Factor
    (10 years § 10% interest)
    
    Total Present Worth of O&M
    
    Rounded to
    
    Estimated Annual Cost
    
    GW-1 A
    
    
    -------
    Alternative GW-2 (UV-Ozonation):
    
    Capital Costs
    
    Item	Estimated Cost
    
    1.	Groundwater Collection System	$ 145,000
    
    2.	H202 Metering Pumps (2) and Controls	6,000
    
    3.	Baffled Tank (pretreatment)	8,000
    
    4.	Green Sand Filter	13,000
    
    5.	UV-Ozone Reactor (750 gal) with
    
    19 lb/day ozone generator	170,000
    
    6.	Prefabricated Building (16* x 24')	25,000
    
    7.	Electrical Supply	17,000
    
    8.	Site Preparation	5,000
    
    9.	Instrumentation	6,000
    
    10.	Receiving Tanks	3,000
    
    11.	Backwash Pump & Controls	5,000
    
    12.	Oil/Water Separator (10 gpm)	5.000
    
    Subtotal	$ 408,000
    
    Administrative & Engineering (15%)	61.200
    
    Subtotal	$ 469,200
    
    Contingency (25%)	117.300
    
    Total	$ 586,500
    
    Rounded to	$ 585,000
    
    

    -------
    Alternative GW-2 (UV-Ozonation):
    O&M Costs
    
    Item	Estimated Annual Cost
    
    1.	Energy
    
    a)	Pumps (5300 kwh/yr at 7.5c/kwh)	$ 400
    
    b)	UV (53,400 kwh/yr at 7.5c/kwh)	4,000
    
    c)	Ozone Generator (61,300 kwh/yr at 7.5c/kwh)	4,600
    
    2.	Hydrogen Peroxide (110 lb/day § 65c/lb)	26,100
    
    3.	UV Replacement Bulbs	4,400
    
    4.	Other Maintenance Supplies (2% of capital)	11,600
    
    5.	Labor
    
    a)	Treatment System (5hr/week)	12,000
    
    b)	Collection System (1.1 hr/week)	2,500
    
    6.	Monitoring
    
    a)	Ground Water/Surface Water
    
    17,400
    
    b)	Treatment System (24 samples)	8,000
    
    Total Annual Cost	$ 91,000
    
    Present Worth Factor
    
    (10 years § 10% interest)	x 6.145
    
    Total Present Worth	$ 559,195
    
    Rounded to	$ 560,000
    
    

    -------
    Alternative GW-3 (Hydrogen Peroxide/Activated Carbon):
    
    Capital Costs
    
    Item	Estimated Cost
    
    1.	Ground Water Collection System	$ 145,000
    
    2.	H2O2 Metering Pumps (2) and Controls	6,000
    
    3.	Baffled Tank (pretreatment)	8,000
    
    4.	Activated Carbon Units	32,000
    
    5.	Green Sand Filter	13,000
    
    6.	Backwash Pump and Controls	5,000
    
    7.	Piping	3,000
    
    8.	Storage Structure	10,000
    
    9.	Site Preparation	5,000
    
    10.	Electrical Supply	15,000
    
    11.	Receiving Tanks	3,000
    
    12.	Instrumentation	6,000
    
    13.	Oil/Water Separator	5.000
    
    Subtotal	$ 256,000
    
    Administration & Engineering (15%)	38.400
    
    Subtotal	294,400
    
    Contingency (25%)	73.600
    
    Total	$ 368,000
    
    Rounded to	$ 370,000
    
    

    -------
    Alternative GW-3 (Hydrogen Peroxide/Activated Carbon):
    
    O&M Costs
    
    Item	Estimated Annual Cost
    
    1.	Energy
    
    (10,500 kwh/year at 7.5c/kwh)	$ 800
    
    2.	Hydrogen Peroxide
    
    (110 lb/day at 65c/lb)	26,100
    
    3.	Activated Carbon
    
    (200 lb/day at 90c/lb)	65,700
    
    4.	Labor
    
    a)	Treatment System (5 hr/week)	12,000
    
    b)	Collection System (1.1 hr/week)	2,500
    
    5.	Other Maintenance Supplies
    
    (3% of capital costs)	10,800
    
    6.	Monitoring
    
    a)	Groundwater/Surface Water	17,400
    
    b)	Treatment system (24 samples)	8.000
    
    Total Annual Cost	$ 143,300
    
    Present Worth Factor	x 6.145
    (10 years at 10% interest)
    
    Total Present Worth of O&M	880,578
    
    Rounded to	880,000
    
    

    -------
    Alternative SM-0 (No Action Alternative)
    
    O&M Costs
    
    Item	Estimated AnnualCost
    
    1.	Maintenance of cap and fence	$ 500
    
    2.	Operation of Oil Recovery System	2,500
    
    3.	Incineration of Collection Oils	1,500
    (600 gal § $2.50/gal)
    
    4.	Ground Water and Surface Water Monitoring
    
    a)	Sample collection	$ 2,500
    (25 samples)
    
    b)	Analysis (PCB, VOC)	9,600
    
    c)	Data review	400
    
    d)	QA/QC	900
    
    e)	Maintenance of Wells	4,000
    
    Subtotal	$ 17,400
    
    $ 17,400
    
    Total Annual Cost	$ 21,900
    
    Present Work Factor
    (30 years § 10% interest)	x 9.427
    
    Total	$ 207,100
    
    Rounded to	$ 210,000
    
    

    -------
    Alternative SM-1 (Containment):
    Estimated Costs
    
    
    
    Capital Costs
    
    
    
    1.
    
    Synthetic membrane
    
    cap (52,000 ft2)
    
    2.
    
    Vegetative cover
    
    
    
    3.
    
    Fencing (1,200')
    
    
    
    4.
    
    Slurry wall (1,000
    
    ¦ X 30' X 30")
    
    5.
    
    Recovery wells (3)
    
    
    
    Subtotal
    
    Administration & Engineering (15%)
    
    Subtotal
    Contingency (25%)
    Total Capital Costs
    Rounded to
    
    1.
    
    O&M Costs
    
    Maintenance of cap
    
    Present Worth Factor (30 years, 10%)
    Present Worth of Cap Maintenance
    
    Total Costs
    $ 210,000
    25,000
    18,000
    210,000
    30,000
    $ 493,000
    73,950
    556,950
    141.737
    $ 708,687
    710,000
    
    Annual Costs
    
    $ 15,000
    
    x 9.427
    $ 141,405
    
    2.
    
    Additional ground water/surface water monitoring
    beyond 10-year duration assumed for ground-water
    treatment system (Annual Cost «= $ 17,400)
    
    Present Worth (30 years, 10%)
    Present Worth (10 years, 10%)
    Net Difference
    Total Present Worth of O&M
    
    Rounded to
    
    $ 164,030
    106,??3
    $• 57,107
    $ 198,512
    $ 200,000
    
    

    -------
    Alternative SM-3 (KOHPEG Dechlorination):
    Preliminary Cost Range
    
    Item
    
    Estimated Cost
    
    1.	Estimated Treatment Cost
    
    2.	Excavation and Handling
    
    Ependitures
    
    3.	Miscellaneous Expenditures
    
    Subtotal
    
    Administration &
    Engineering (15%)
    
    Subtotal
    
    Contingency (35%)
    
    Minimum
    $ 135/cy
    
    30/cy
    
    10/cy
    
    $ 175/cy
    
    x 15.OOOcv
    2,625,000
    
    393.750
    3,018,750
    1.056.550
    
    Maximum
    $ 270/cy
    
    30/cy
    
    10/cv
    
    $ 310/cy
    
    x 15.OOOcv
    4,650,000
    
    697.500
    5,347,500
    1.871.625
    
    Total
    Rounded to
    
    4,075,300
    $ 4 million
    
    7,219,125
    $ 7.2 million
    
    

    -------
    Alternate SM-4 (On-site Incineration):
    Estimated Costs
    
    Capital
    
    1.	Utility Connection
    
    2.	Temporary Building
    
    3.	Preliminary test burns/approval
    
    Subtotal
    
    Administration & Engineering (15*)
    
    Subtotal
    Contingency (25%)
    
    Total
    
    Operation & Maintenance
    
    1.	Excavation/soil preparation
    
    2.	Incineration
    
    a.	Fuel
    
    b.	Equipment rental
    
    c.	Analytical services
    
    d.	Other
    
    Subtotal
    
    Administration & Engineering (15%)
    
    Subtotal
    Contingency (25%)
    
    Total
    
    Assuming 7,500 c.y. per year incinerated
    
    Total Annual Cost
    
    Present Worth Factor
    (2 years at 10% interest)
    
    Total Present Worth of O+M
    
    Grand Total
    
    Rounded to
    
    $
    $
    $
    $.
    $
    
    Cost
    $ 25,000
    40,000
    80.000
    ; 145,000
    21.800
    
    ; 160,000
    41,500
    [ 208,400
    
    t 40/cy
    
    45/cy
    100/cy
    20/cy
    60/cv
    
    265/cy
    
    40/cy
    
    305/cy
    
    381/cy
    = 7,500 X 381
    2,857,500
    X 1.736
    
    $ 4,960,620
    5,169,020
    $ 5.2 million
    
    

    -------
    Alternate SM-5 (Off-Site Incineration):
    Estimated Costs
    ifcein	Cost ($/cv)
    
    1.	Excavation	25
    
    2.	Replacement with Clean Fill	5
    
    3.	Transportation	550
    
    4.	Incineration Fees (including sampling
    and analysis), based on $0.67 per lb and
    
    1.5 ton/cy	2.000
    
    Subtotal	2,580
    
    Administration (5%)	129
    
    Subtotal	2,709
    
    Contingency (25%) 	677
    
    Total	3,386
    
    Assume 7,500 cy incinerated per year:
    
    Total Annual Cost = $3,386 x 7,500 = $ 25,395,000
    
    Present Worth Factor
    
    (2 yrs. § 10%)	x 1.736
    
    TOTAL 44,085,720
    Rounded to $ 44 million
    
    

    -------
    Alternative SM-6 (On-site Landfill):
    Estimated Costs
    
    Capital
    
    1. Construction of Landfill include liners,
    
    leachate collection, etc. ($125/c.y.)
    3. Excavation and Placement of soils
    into landfill ($35/c.y.)
    
    Subtotal
    
    Administration & Engineering (15%)
    
    Subtotal
    Contingency (25%)
    Total
    
    Total Cost
    $ 1,875,000
    
    525,000
    
    2,400,000
    360,000
    2,760,000
    690.000
    3,450,000
    
    O&M
    
    1.	Maintenance of Cap
    
    2.	Leachate Treatment
    
    Total (Items 1 & 2)
    Present Worth Factor (30 years, 10% interest)
    
    Present Worth (Items 1 & 2)
    
    3.	Additional ground water monitoring (beyond
    that required for ground water treatment
    system)
    
    Total O&M Present Worth
    
    Estimated
    Annual Cost
    
    $ 15,000
    6.000
    $ 21,000
    X 9-427
    $ 197,967
    
    $ 57.107
    
    255,074
    
    GRAND TOTAL (Present Worth)
    
    Rounded to
    
    3,705,074
    3.7 million
    
    

    -------
    Alternative SM-7 (Off-Site Landfill):
    Estimated Costs
    
    
    
    Jtem
    
    Cost.S/c.v.
    
    1.
    
    Excavation (and dewatering, if necessary)
    
    25
    
    2.
    
    Transport to Niagara Falls
    
    150
    
    3.
    
    Landfilling Fee
    
    200
    
    4.
    
    Replacement with Clean Fill
    
    5
    
    
    
    Subtotal
    
    380
    
    
    
    Administration (5%)
    
    19
    
    
    
    Subtotal
    
    399
    
    
    
    Contingency (35%)
    
    140
    
    
    
    Total
    
    $ 539/c.y.
    
    
    
    Assume 7,500 c.y. removed per year
    
    
    
    
    
    Annual Cost = $539 x 7,500 =
    
    4,042,500
    
    
    
    Present Worth Factor (2 years § 10%)
    
    X 1.736
    
    
    
    Total Landfilling Present Worth
    
    7,017,780
    
    
    
    Rounded to
    
    $ 7 million
    
    

    -------
    Alternate SH-8 (Chemical Fixation/Stabilization):
    Preliminary Cost Estimate*
    
    Item	Cost
    
    1.	Excavation ($30/cy)	$ 450,000
    
    2.	Soil Preparation ($5/cy)	75,000
    
    3.	Treatment ($100/cy)	1,500,000
    
    4.	Pilot Testing	50.000
    
    Subtotal	$ 2,075,000
    
    Administration & Engineering (15%)	311,250
    
    Subtotal	2,386,250
    
    Contingency (25%)	596.550
    
    Total Present Worth	2,982,800
    
    Rounded to	$ 3 million
    
    * Note that this estimate does not include any costs for VOC
    extraction.
    
    

    -------
    COSTS FOR AIR STRIPPER AIR EMISSIONS CONTROL
    
    Three control technologies are commonly used to reduce VOC
    emissions from air strippers. These technologies include vapor
    phase granular activated carbon (GAC) treatment, thermal
    incineration, and catalytic incineration. Among these three
    technologies, both capital and operation and maintenance (O&M)
    costs for either type of incineration are generally higher than
    for vapor phase GAC. U.S. EPA (1987b) compared capital and O&M
    costs for vapor phase GAC and thermal and catalytic incineration
    for removing VOCs from air stripping off-gases at four hazardous
    waste sites. This comparison indicates that (1) capital costs for
    thermal and catalytic incineration are significantly higher than
    for vapor phase GAC and (2) differences in O&M costs are even more
    pronounced. From this limited review, it appears that vapor phase
    GAC would be the most cost-effective VOC emission control
    alternative for the proposed air stripper at the Rose site.
    
    GE's FS report recommended groundwater treatment by air stripping,
    followed by liquid phase GAC, as the preferred remedial alternative
    (alternative GW-1). However, the FS report also evaluated an air
    stripping-GAC system that included pretreatment of groundwater by
    hydrogen peroxide (H202) (alternative GW-1A). Data collected
    during the November 1987 groundwater treatability study at the Rose
    site indicate that H202 pretreatment (at a dose of 62 ing/L H202)
    can remove approximately 75 percent of the VOCs in groundwater
    before treatment by air stripping (Blasland & Bouck, 1988b, Table
    10). It is possible that the added costs of H202 pretreatment will
    be offset by the reduction in VOC concentrations reaching the air
    stripper and the vapor phase GAC system. Thus, this section
    presents vapor phase GAC cost estimates for both alternatives GW-
    1 and GW-1A.
    
    COST ESTIMATE FOR VAPOR PHASE GAC
    
    A variety of VOCs are present in contaminated groundwater at the
    Rose site; however, the design of a vapor phase GAC system will be
    controlled by the presence of high concentrations of vinyl
    chloride, a poorly adsorbed compound. Based on information
    obtained from vendors of carbon systems, the capacity of vapor
    phase GAC to remove vinyl chloride (VC) is not likely to exceed 1
    percent by weight (0.01 pounds VC per pound of GAC) (Stratico,
    1988; Peschman, 1988).
    
    Table 3-4 of the FS report estimates average and maximum VC
    concentrations in ground water as 1,040 and 2,000 ppb,
    respectively (Blasland & Bouck, 1988a). EPA used these
    concentrations, along with the following assumptions, to estimate
    vapor phase GAC requirements and GAC replacement costs for
    groundwater treatment alternatives GW-1 and GW-1A:
    
    

    -------
    o Air stripper design parameters — EPA used the values
    presented in the FS report for both groundwater
    treatment rate (50 gpm) and gas-to-liquid ratio (80).
    and assumed that the air stripper would operate
    continuously.
    
    o Treatment efficiency — EPA assumed that H2Q2
    
    pretreatment efficiency for VC will be 75 percent and
    that all remaining VC will be removed by the air
    stripper; that is, all VC in ground water entering the
    air stripper is stripped to the air.
    
    o Capacity of vapor phase GAC — EPA used a value of 0.01
    pounds of VC per pound of GAC (or 1 percent by weight)
    to estimate the capacity of vapor phase GAC (Stratico,
    1988; Peschman, 1988).
    
    o GAC replacement costs — EPA used a typical value of
    $1.75 per pound for the cost of fresh GAC (Stratico,
    1988; Peschman, 1988).
    
    Table 3-1 shows vapor phase GAC requirements and GAC replacement
    costs for alternatives GW-1 and GW-1A. Based on these
    calculations, annual GAC replacement costs for alternative GW-1
    would be approximately $44,700 to $86,200. In a vessel containing
    10,000 pounds of GAC, the GAC would need to be replaced every 2.5
    to 5 months. Annual GAC replacement costs for alternative GW-1A,
    with H202 pretreatment, would be reduced to approximately $11,200
    to $21,600. GAC replacement would be required every 10 to 19
    months.
    
    Several additional factors would contribute to operating costs of
    the vapor phase GAC system. Additional power would be needed to
    overcome pressure drop across the GAC bed and to heat the air
    stripper off-gas to reduce relative humidity. Adsorption capacity
    of air stripped VOCs can be increased if relative humidity is
    reduced below 40 percent; this is usually accomplished by
    increasing the temperature of the air stream with an in-line heater
    (Stenzel and Gupta, 1985). EPA estimates that added power costs
    would increase annual O&M
    
    costs by $15,000 to $20,000 for alternatives GW-l and GW-1A.
    
    EPA assumed that spent GAC would not be regenerated but would be
    collected and replaced by the carbon vendor. Based on
    conversations with vendors, EPA estimated transportation costs to
    be approximately $3,000 per replacement. Annual transportation
    costs for alternative GW-1 could range from $7,700 to $14,800,
    assuming 2.55 to 4.93 bed replacements per year. Annual
    transportation costs for alternative GW-1A could range from $1,900
    to $3,700, assuming 0.64 to 1.23 bed replacements per year.
    
    From the factors considered above (carbon replacement, power
    requirements, and transportation costs), annual O&M costs for vapor
    phase GAC control of air stripper emissions could range from
    
    

    -------
    $67,4 00 to $121,000 for alternative GW-1. For alternative GW-1A,
    with hydrogen peroxide pretreatment before air stripping, annual
    O&M costs for vapor phase GAC could range from $28,100 to $45,300.
    
    Capital costs for the vapor phase GAC system are expected to be
    approximately $50,000. This estimate includes costs for (1) a
    10,000-pound vapor phase GAC vessel 8 feet in diameter with a
    carbon bed depth of approximately 7 feet; (2) an in-line air
    heater; and (3) associated ductwork. To be consistent with the
    cost estimates presented in the FS report, EPA increased the
    $50,000 capital cost estimate by 15 percent to allow for
    administrative and engineering expenses and by another 25 percent
    to account for contingencies. Thus, the total estimated capital
    cost for the vapor phase GAC system is approximately $72,000.
    
    Table 3-2 summarizes total costs for VOC air emissions control
    systems for both alternatives GW-1 and GW-1A.
    
    POTENTIAL COST REDUCTIONS
    
    It may be possible to reduce O&M costs of a vapor phase GAC system
    by reducing the concentration of VC in the ground water to be
    treated. VC is often formed as a degradation product when
    chlorine atoms are removed from more highly chlorinated compounds,
    such as di-, tri-, and tetra-chlorinated ethanes and ethenes. By
    collecting ground water for treatment at a location closer to the
    disposal area, it may be possible to intercept the contaminated
    plume before significant amounts of VC have formed.
    
    A comparison of limited data from wells in the disposal area and
    wells south of the disposal area supports the idea that VC
    concentrations increase with distance from the disposal area. (VC
    has not been detected in ground water from the eastern plume). VC
    has been detected in only two of four samples collected from wells
    in the disposal area. The average VC concentration for these four
    samples is 215 ppb, and the maximum concentration is 500 ppb
    (Blasland & Bouck, 1988a, Table 3-4; Geraghty & Miller, 1988,
    Appendix A; McGlincy and Koch, 1988). One sample has been analyzed
    from well 47A, approximately 120 feet south of the disposal area
    perimeter. The VC concentration in this sample was 1,000 ppb
    (Blasland & Bouck, 1988b, Table 1). Eight samples (including three
    duplicates) from well 12A, approximately 150 feet south of the
    disposal area perimeter, have been analyzed. The average VC
    concentration for these samples is 3,375 ppb, with a maximum
    concentration of 6,000 ppb (Blasland & Bouck, 1988bf Table 1;
    Geraghty & Miller, 1988).
    
    These data suggest that collection of groundwater at a location
    between wells 12A and 47A and the disposal area may result in lower
    VC concentrations. In the long term, O&M costs for the vapor phase
    GAC system on the air stripper could be reduced by collecting and
    treating groundwater with lower VC concentrations. However, in
    
    

    -------
    the short term, treatment of groundwater near wells 12A and 47A
    will be required since VC concentrations in these wells greatly
    exceed the proposed VC cleanup goal of 2 ppb.
    
    

    -------
    TABLE 3-1
    
    VAPOR PHASE GAC REQUIREMENTS AND
    GAC REPLACEMENT COSTS FOR
    ALTERNATIVES GW-1 AND GW-1A
    
    
    
    Alternative
    
    GW-1
    
    Alternative GW-1A
    
    Parameter
    
    Average
    
    Maximum
    
    Average
    
    Maximum
    
    VC concentration in ground water
    
    1040 ppb
    
    2000 ppb
    
    1040 ppb
    
    2000 ppb
    
    Pretreatment efficiency
    
    NA1
    
    NA
    
    75 %
    
    75%
    
    VC concentration in water entering air stripper
    
    1040 ppb
    
    2000 ppb
    
    260 ppb
    
    600 ppb
    
    VC concentration in air leaving *ir stripper
    
    13.0 mg/m®
    
    25.0 mg/m'
    
    3.25 mg/tn8
    
    6.25 mg/mS
    
    VC loading rate to vapor phase GAC
    
    0.70 lb/day
    
    1.35 lb/day
    
    0.175 lb/day
    
    0.338 lb/day
    
    Vapor phase GAC use rate
    
    70 lb/day
    
    135 lb/day
    
    17.S lb/day
    
    33.8 lb/day
    
    Annual GAC replacement costs (rounded)
    
    $44,700
    
    $86,200
    
    $11,200
    
    $21,600
    
    Lifetime of GAC in 10,000-pound bed
    
    143 days
    
    74 days
    
    571 days
    
    296 days
    
    Number of bed replacements per year
    
    2.55
    
    4.03
    
    0.64
    
    1.23
    
    Note:	Not applicable, since alternative GW-1 doe* not include ground-water pretrcatment prior to air
    
    stripping.
    
    

    -------
    TABLE 3-2
    
    COSTS FOR VAPOR PHASE GRANULAR
    ACTIVATED CARBON SYSTEM
    
    Alternative GW-1
    
    Capital Cost1
    
    Includes 8-foot-diameter x 7-foot-depth
    carbon adsorber, including carbon,
    
    heater, and ductwork	$ 72,000
    
    Annual O&M Cost2
    
    Carbon replacement	$ 44,700	to	$ 86,200
    
    Additional power requirements	15,000	to	20,000
    
    Transportation costs	7.700	to	14.800
    
    Total	$67,400	to	$121,000
    
    Alternative GW-1 A
    
    Capital Cost1
    
    Includes 8-foot-diameter x 7-foot-depth
    carbon adsorber, including carbon,
    
    heater, and ductwork	$ 72,000
    
    Annual O&M Cost2
    
    Carbon replacement
    Additional power requirements
    Transportation costs
    
    Total
    
    $ 11,200	to	$21,600
    
    15,000	to	20,000
    
    1,900	to	3.700
    
    $ 28,100	to	$ 45,300
    
    Notes: 1 For consistency with FS report, cost estimate includes additional 15
    percent for administrative and engineering expenses and additional 25
    percent for contingencies.
    
    * Cost estimates are presented as ranges based on average and maximum
    VC concentrations in ground water.
    
    

    -------
    COST SENSITIVITY ANALYSIS
    
    EPA evaluated the sensitivity of groundwater treatment costs to
    interest (or discount) rate and duration of groundwater
    treatment. GE's FS report assumed that groundwater treatment
    would occur for a period of 6 to 12 years, but calculated total
    costs only for a 10-year operating period. EPA calculated costs
    for 7-, 10-, and 30-year operating periods to produce data for
    the sensitivity analysis. The 7-year period was chosen as a
    minimum possible duration of groundwater treatment. The 30-year
    operating period is based on the assumption of typical duration
    for post-closure care following closure of a hazardous waste
    site. The FS report discounted future O&M costs using an
    interest rate of 10 percent. In addition to this rate, EPA used
    interest rates of 5 and 15 percent for the sensitivity analysis.
    
    Capital and annual O&M costs for the four groundwater treatment
    alternatives were presented in Tables 6-3 through 6-8 of the FS
    report (Blasland & Bouck, 1988a) and are summarized here in Table
    4-1. EPA also looked at the costs for both air stripping and
    carbon adsorption alternatives (GW-l and GW-lA) after the
    addition of vapor phase GAC for air emissions control. Capital
    and OStM costs for vapor phase GAC were added to the groundwater
    treatment costs for alternatives GW-l and GW-lA. Costs for GW-l
    and GW-lA with air emissions control are also included in Table
    4-1.
    
    EPA calculated the present worth of total costs (capital plus
    O&M) for each alternative for interest rates of 5, 10, and 15
    percent over operating periods of 7, 10, and 30 years. Thus,
    nine separate calculations were made for each alternative. The
    results of these calculations are shown in Table 4-2.
    
    Relative costs for the four alternatives evaluated in the FS
    report do not appear to be sensitive to either interest rate or
    duration of groundwater treatment. The FS report found that at
    a 10 percent interest rate over 10 years, the alternatives were
    ranked GW-l, GW-lA, GW-2, and GW-3, going from lowest to highest
    total present worth costs. This ranking holds for all
    combinations of interest rates and operating periods evaluated in
    Table 4-2.
    
    When the costs of air emissions control are considered for
    alternatives GW-l and GW-lA, the total present worth costs are
    greatly increased compared to the costs of these alternatives
    without control. In evaluating the effects of air emissions
    control costs in Tables 4-1 and 4-2, EPA considered both the
    average and the maximum annual O&M cost estimates ($67,400 versus
    $121,000 for alternative GW-l(GAC) and $28,100 versus $45,300 for
    alternative GW-IA(GAC)). These average and maximum O&M cost
    estimates are based on average and maximum vinyl chloride
    concentrations in groundwater, respectively.
    
    

    -------
    During the actual treatment of groundwater at the Rose site, it
    is more likely that vinyl chloride concentrations will be closer
    to the average value. This average is based on a composite
    concentration for vinyl chloride in the eastern and southern
    groundwater plumes. Current plans are to combine groundwater
    from both plumes and to treat this combined stream. Thus, for
    groundwater treatment alternatives GW-l(GAC) and GW-IA(GAC),
    total present worth costs are likely to be closer to the lower
    values presented in Table 4-2.
    
    With the addition of air emissions control, costs for
    alternatives GW-l(GAC) and GW-IA(GAC) (Table 4-2) are similar to
    or slightly higher than costs for alternatives GW-2 (hydrogen
    peroxide pretreatment with UV-ozonation) and GW-3 (hydrogen
    peroxide pretreatment with carbon adsorption). For example, at a
    10 percent interest rate and a 10-year treatment duration, there
    is only a 12 percent difference between the highest and lowest
    costs. Furthermore, cost estimates developed for feasibility
    studies conducted under CERCLA are typically accurate only to
    within -30 to +50 percent of actual remediation costs (U.S. EPA,
    1988). Of the cost estimates for the four alternatives, the
    estimate for alternative GW-l(GAC) is likely to be most accurate.
    The technology used in alternative GW-l(GAC) has been tested and
    implemented in full-scale at several Superfund sites and is
    considered a demonstrated and proven method of groundwater
    treatment. Alternative GW-2 employs a technology that has not
    been used extensively at Superfund sites. This technology is
    currently being evaluated on a pilot-scale under U.S. EPA's
    Superfund Innovative Technology Evaluation (SITE) program.
    Alternatives GW-IA(GAC) and GW-3 both require hydrogen peroxide
    pretreatment, which also has not been widely used to treat
    contaminated groundwater. Thus, cost estimates for alternatives
    GW-IA(GAC), GW-2, and GW-3 are subject to greater uncertainty
    than the estimate for GW-l(GAC). Given these uncertainties and
    the relatively small range of costs shown in Table 4-2, no
    groundwater treatment alternative stands out as the most cost-
    effective.
    
    EPA was not able to conduct a similar sensitivity analysis for
    source management remedial alternatives. Cost estimates were
    not presented for the three potential alternatives recommended by
    GE for futher study in the FS report — in-situ soil flushing,
    chemical extraction, and biodegradation — due to the
    developmental nature of these technologies.
    
    Costs for most of the source management alternatives are
    presented in the FS report as lump sums and are not broken into
    capital and annual O&M costs. Furthermore, the assumptions
    behind the cost estimates are not presented. Thus, EPA is not
    able to evaluate the sensitivity of the costs to factors such as
    interest rate or operating period or to comment on the costs in
    detail. However, EPA has identified several factors that may
    impact costs for the incineration and fixation-stabilization
    source management alternatives.
    
    

    -------
    The cost estimate for on-site incineration (Blasland & Bouck,
    1988a, Table 6-11) is based on a nominal incineration cost of
    $225 per cubic yard (cy) of contaminated soil. The FS report
    does not discuss the BTU value of the soil that will be treated.
    This factor will have a significant impact on fuel costs and may
    vary considerably for soils from different parts of the disposal
    area. Fuel costs are estimated to be 45 percent of the equipment
    rental costs and represent a significant portion of the
    incinerator O&M costs (Blasland & Bouck, 1988a). Overall costs
    of incineration may be particularly sensitive to soil BTU
    content.
    
    The proposed soil preparation method for chemical fixation-
    stabilization (screen out large objects such as rocks before
    treatment) is similar to the method described for on-site
    incineration. However, the soil preparation costs for the two
    alternatives are different. The unit cost for soil preparation
    prior to chemical stabilization/fixation is $5/cy, whereas the
    unit soil preparation cost prior to incineration appears to be
    $10/cy ($4 0/cy for excavation/soil preparation minus $30/cy for
    excavation). This difference of $5/cy, if incorporated into the
    costs for chemical stabilization/fixation, would add
    approximately $500,000 to total costs as presented in the FS.
    
    

    -------
    TABLE 4-1
    
    CAPITAL AND ANNUAL O&M COSTS
    FOR GROUNDWATER TREATMENT ALTERNATIVES
    
    Costs-
    
    GW-1
    
    GW-1A
    
    GW-1(GAC)2
    
    Alternative
    
    Air stripping followed
    by carbon adsorption
    
    Hydrogen peroxide
    pretreatment, filtration,
    air stripping, and
    carbon adsorption
    
    GW-1 with vapor phase
    GAC added for air
    emissions control
    
    Capital Costs1 O&M
    f$ * 10QQ)	f$xlOQO)
    
    395.0
    
    430.0
    
    467.0
    
    61.1
    
    2.1
    
    128.5
    to
    182.1
    
    GW-1A(GAC)2
    
    GW-2
    
    GW-3
    
    GW-1A with vapor phase
    GAC added for air
    emissions control
    
    Hydrogen peroxide
    pretreatment, filtration,
    and UV-ozonation
    
    Hydrogen peroxide
    pretreatment, filtration,
    and carbon adsorption
    
    502.0
    
    585.0
    
    370.0
    
    100.2
    to
    117.4
    
    91.0
    
    143.3
    
    Notes:
    
    1	Costs obtained from Tables 6-3 through 6-8 of FS report
    (Blasland & Bouck, 1988a).
    
    2	Costs obtained by adding vapor phase GAC capital and O&M
    costs to costs presented in Tables 6-3 and 6-4 of FS report
    (Blasland & Bouck, 1988a). The lower and higher O&M costs
    are based on average and maximum vinyl chloride
    concentrations in groundwater, respectively.
    
    

    -------
    TABLE 4-2
    
    SENSITIVITY ANALYSIS FOR GROUND-WATER REMEDIAL ALTERNATIVE COSTS
    
    Duration		Present Worth of Total Costs fin >1000)^'^
    
    Interest Rate	of Ground-Water	Present Worth
    
    percent)
    
    Treatment (vears)
    
    Factor
    
    GW-1
    
    GW-1A
    
    GW-
    
    1 (GAC)
    
    GW-1A (GAC)3
    
    GW-2
    
    GW-3
    
    5
    
    7
    
    5.79
    
    749
    
    847
    
    1211
    
    to
    
    1521
    
    1082
    
    to
    
    1182
    
    1112
    
    1199
    
    
    
    10
    
    7.72
    
    867
    
    987
    
    1459
    
    to
    
    1873
    
    1276
    
    to
    
    1408
    
    1288
    
    1477
    
    
    
    30
    
    15.37
    
    1334
    
    1538
    
    2442
    
    to
    
    3266
    
    2042
    
    to
    
    2306
    
    1984
    
    2573
    
    10
    
    7
    
    *.87
    
    693
    
    781
    
    1093
    
    to
    
    1354
    
    990
    
    to
    
    1074
    
    1028
    
    1068
    
    
    
    10
    
    6.14
    
    770
    
    873
    
    1256
    
    to
    
    1585
    
    1117
    
    to
    
    1223
    
    1144
    
    1251
    
    
    
    30
    
    9.43
    
    971
    
    1110
    
    1679
    
    to
    
    2184
    
    1447
    
    to
    
    1609
    
    1443
    
    1721
    
    15
    
    7
    
    4.16
    
    649
    
    730
    
    1002
    
    to
    
    1225
    
    919
    
    to
    
    990
    
    964
    
    966
    
    
    
    10
    
    5.02
    
    702
    
    792
    
    1112
    
    to
    
    1381
    
    1005
    
    to
    
    1091
    
    1042
    
    1089
    
    
    
    30
    
    6.57
    
    796
    
    903
    
    1311
    
    to
    
    1663
    
    1160
    
    to
    
    1273
    
    1183
    
    1311
    
    Notes:
    
    1	Costs calculated from values In Table 4-2 using the following formula:
    
    Present uorth of total costs * (Capital costs) ~ (Present worth factor x Annual 0M costs)
    
    2	All costs are rounded to the nearest 11,000.
    
    ' %
    
    3	Range of costs is based on the range of OtM costs in Table 4'1.
    
    

    -------
    U.S. Environmental Protection Agency, 1970. Workbook of Atmospheric Dispersion
    Estimates, Office of Air Programs, Research Triangle Park, N.C. (AP-26).
    
    U.S. Environmental Protection Agency, 1986. Superfund Public Health Evaluation
    
    Manual, Office of Emergency and Remedial Response (OSWER Directive 9285.4-1),
    Washington, DC, October.
    
    U.S. Environmental Protection Agency, 1987a. Final Draft Superfund Exposure
    Assessment Manual, Office of Solid Waste and Emergency Response (OSWER
    Directive 9285.5-1), Washington, DC, September 22.
    
    U.S. Environmental Protection Agency, 1987b. Air Stripping of Contaminated Water
    Sources — Air Emissions and Controls, Air Toxics Control Technology Center,
    Research Triangle Park, NC (EPA-450/3-87-017), August.
    
    

    -------