United States

Environmental Protection Agency

September 1997

Office of Air Quality Planning & Standards (MD-13)

mEPA	New Regulation Controlling

Air Emissions from Aerospace
Manufacturing and Rework Facilities

40 CFR 63, Subpart GG

Printed on recycled paper


-------
COMPLIANCE SCHEDULE

[ Sources with "1
¦ initial startup |
I before .
I September 1, 1995 I

I Sources with ^
i initial startup |
' after	i

| September 1, 19951

whichever is
later

60 days after
performance
test, whichever
is earlier

GENERAL INFORMATION (The information in this pamphlet is intended for general reference only; it is not a full
and complete statement of the technical or legal requirements associated with the regulation.)

Applicability: This rule applies to facilities engaged in original equipment manufacture and/or rework of
aerospace vehicles components and assemblies and that are major sources.

Over 2,800 facilities are expected to be affected by the rule. Applicable SIC codes include 3720, 3721, 3724,
3728, 3760, 3761, 3764, 3769, 4512, 4581, and 9711.

Major sources are required to obtain an operating permit in the State where the facility is located.

The following apply to all affected sources:

Standards

1.	Table 1-General Provisions Applicability to Subpart GG. [63.743(a)] shows how aerospace sources
are affected by the General Provisions of 40 CFR part 63, subpart A.

2.	Requirement to submit a startup, shutdown, and malfunction plan, except for dry particulate filter
systems operated per manufacturer's instructions. [63.743(b)]

3.	Requirement to obtain approval to use control device or equipment not listed in the regulation. [63.743(c)]

4.	Wastes subject to RCRA are exempt. [63.741(e)]

5.	Space vehicles are exempt from the requirements, except for depainting operations. [63.741(h).

6.	Rework operations performed on antique aerospace vehicles or components are exempt.

[63.7410)].

Test Methods and Procedures

See individual requirements. Also, comply with §63.7 of the General Provisions. [63.749 & 63.750]

Monitoring Requirements

See individual requirements. Also, comply with §63.8(f) and (g) of the General Provisions. [63.751(e) and (f)]

Recordkeeping Requirements

See individual requirements. Also, comply with certain parts of §63.10 of the General Provisions. [63.752(a)]

Reporting Requirements

1.	See individual requirements. Also, comply with certain parts of §63.9 and §63.10 of the General
Provisions.

2.	State approved operating permit application can be used for initial notification if submitted by September 1,
1997. [63.753(a)(2)]

Shaded areas with bold italics indicate final amendments to the NESHAP as of September 1997.

2


-------
Requirements

Cleaning Operations

Standards

Handwioc

1.	Except for cleaning of spray gun equipment, all hand-wipe cleaning solvents must meet a
composition requirement (see Table 1 of § 63.744), have a composite vapor pressure less than
or equal to 45 mm Hg at 20 C, or meet the 60 percent volume reduction requirements specified
in an alternative compliance plan. [63.744(b)]

2.	Note the list of 13 cleaning operations exempt from composition, vapor pressure, and volume
reduction requirements. [63.744(e)]

Sorav sun cleanine

1.	Use one of four specified techniques or their equivalent. [63.744(c)]

2.	For enclosed spray gun cleaners, if leaks are found during the required monthly inspection,
repair as soon as practicable, but within 15 days. [63.744(c)(l)(ii)]

Flush cleanine

Operating procedures specify emptying used cleaning solvent into enclosed container, collection

system, or system with equivalent emission control. [63.744(d)]

Performance
Test Periods and
Tests

N/A

Test Methods
and Procedures

Handwioc

1.	Composition determination using manufacturer's data. [63.750(a)]

2.	Vapor pressure determination using readily available sources such as MSDS if single
component; composite vapor pressure determined by manufacturer's supplied data or
ASTM E 260-91 and by equation provided for multiple component solvents. [63.750(b)]

Sorav sun cleanine
None.

Flush cleanine
None.

Monitoring

Handwioc
None.

Sorav eun cleanine

Monthly visual leak inspection. [63.751(a)]

Flush cleanine

None.

Recordkeeping

Handwioc

1.	If complying with composition requirements, the name, data/calculations, and annual volumes.
[63.752(b)(2)]

2.	If complying with vapor pressure limit, the name, vapor pressure, data/calculations/test results,
and monthly volumes. [63.752(b)(3)]

3.	For noncompliant cleaning solvents used in exempt operations, the name, monthly volumes by
operation, and master list of processes. [63.752(b)(4)]

Sorav eun cleanine

Record all leaks, including source identification and dates leaks found and repaired.

[63.752(b)(5)]

Flush cleanine

For semi-aqueous cleaning solvents, the name, data/calculations, and annual volumes.
[63.752(b)(2)]

Reporting

All aoolicablc cleanine operations

Semiannual report: Statement certifying compliance. [63.753(b)(l)(v)]

Ha ndw idc—Scm iannua 1 (6 months from the date of notification of compliance status)

1.	Noncompliant cleaning solvent used. [63.753(b)(l)(i)]

2.	New cleaning solvents and their composite vapor pressure or notification of compliance with
composition requirements. [63.753(b)(1)(h)]

Sorav eun cleanine-Semiannual (6 months from the date of notification of compliance status)

1.	Noncompliant spray gun cleaning method used. [63,753(b)( l)(iii)]

2.	Leaks from enclosed spray gun cleaners not repaired within 15 days. [63.753(b)(l)(iv)]

Shaded areas with bold italics indicate final amendments to the NESHAP as of September 1997.

3


-------
Requirements

Primer and Topcoat Application Operations

Standards

Uncontrolled Primers

1.	Organic HAP and VOC content limit: 350 g/1 (2.9 lb/gal) (less water) as applied.
[63.745(c)(l)-(2)]

2.	Achieve compliance through: (1) using coatings below content limits, or (2) using monthly
volume-weighted averaging (primers only) to meet content limits. [63.745(e)]

Uncontrolled Toocoats (including self-vrimins topcoats)

3.	Organic HAP and VOC content limit: 420 g/1 (3.5 lb/gal)(less water) as applied.
[63.745(c)(3)-(4)]

4.	Same as No. 2 (above) except for topcoats only.

Controlled Primers and Toocoats (includins self-vrimins topcoats)

5.	Control system must reduce organic HAP and VOC emissions to the atmosphere >81%, using
capture and destruction/removal efficiencies. [63.745(d)]

All Primers and Toocoats

6.	Minimize spills during handling and transfer. [63.745(b)]

7.	Specific application techniques must be used. [63.745(f)(1)]

8.	Exemptions from No. 7 (above) provided for certain situations. [63.745(f)(3)]

9.	All application equipment must be operated according to manufacturer's specifications,
company procedures, or locally specified operating procedures (whichever is most stringent).
[63.745(f)(2)]

10.	Operating requirements for the application of primers or topcoats that contain inorganic HAP,
including control with either particulate filters (see Tables 1 through 4 of § 63.745) or
waterwash system. Painting operation(s) must be shutdown if operated outside manufacturer's
specified limits. [63.745(g)(1) through (3)]

11.	Exemptions from No. 10 (above) provided for certain application operations. [63.745(g)(4)]

Performance Test
Periods and Tests

Uncontrolled

1.	Performance Test Period for coatings not averaged: each 24 hour period; for "averaged"
coatings: each 30-day period. [63.749(d)(1)]

Controlled

2.	Performance Test Period for noncarbon adsorber: three 1-hour runs; for carbon adsorber:
each rolling material balance period. [63.749(d)(1)]

3.	Initial performance test required for all control devices to demonstrate compliance with
overall control efficiency requirement. [63.749(d)(2)]

Test Methods and
Procedures

Oreanic HAP

1.	Organic HAP level determination procedures. [63.750(c) and (d)]

2.	VOC level determination procedures. [63.750(e) and (f)]

3.	Overall control efficiency of carbon adsorber system determined using provided procedures;
for other control devices, determine capture efficiency and destruction efficiency. For capture
efficiency, use Procedure T in Appendix B to 40 CFR 52.741 for total enclosures and 40 CFR
52.741(a)(4)(iii) procedures for all other enclosures. [63.750(g) and (h)]

4.	For alternative application methods, first determine emission levels for initial 30-day period
or five aircraft using only HVLP or electrostatic, or a time period specified by the permitting
agency. Then use alternative application method for period of time necessary to coat
equivalent amount of parts with same coatings. Alternative application method may be used
when emissions generated during the test period are less than or equal to the emissions
generated during the initial 30-day period or five aircraft. Dried film thickness must be
within specification for initial 30-day period or five aircraft as demonstrated under actual
production conditions. [63.750(i)]

Inorsanic HAP

5.	Dry particulate filter certification: use Method 319 to meet or exceed the efficiency data
points in Tables 1 and 2 of § 63.745for existing sources, or Tables 3 and 4 of § 63.745for
new sources [63.750(o)]

Shaded areas with bold italics indicate final amendments to the NESHAP as of September 1997.

4


-------
Requirements

Primer and Topcoat Application Operations

Monitoring

1.	Carbon adsorbers. [63.751(b)(1) through (7)]

2.	Temperature monitoring equipment to be installed, calibrated, maintained, and operated -
according to manufacturer's specifications. Use CEMS as an alternative. [63.751(b)(8)]

3.	Incinerators. [63.751(b)(9) through (12)]

4.	Dry particulate filters and waterwash systems. [63.751(c)]

5.	Alternate monitoring method. [63.751(e)]

Recordkeeping

1.	Name and VOC content as received and as applied for all primers and topcoats.
[63.752(c)(1)]

Uncontrolled

2.	For "compliant" coatings, organic HAP and VOC contents as applied, data/calculations and
test results used to determine HAP/VOC contents (H and G,). and monthly usage.
[63.752(c)(2)]

3.	For "low-HAP content" primers, annual purchase records, and data/calculations and test
results used to determine H or HAP/VOC content as applied. [63.752(c)(3)]

4.	For "averaged" coatings, monthly values of VOC content (Ha and Ga), and data/calculations
and test results used to calculate Ha and Ga. [63.752(c)(4)]

Controlled

5.	For incinerators, overall control efficiency test results/data/calculations used in determining
the overall control efficiency; and continuous records of incinerator temperature(s).
[63.752(c)(5)]

6.	For carbon adsorbers, overall control efficiency and length of rolling period and all
supporting test results/data/calculations used in determining the overall control efficiency.
[63.752(c)(6)]

Inoreanic HAP Particulate

7.	Pressure drop across filter or water flow rate through waterwash system once per shift, and
acceptable limits. [63.752(d)(1) through (3)]

Reporting

Semiannual (6 months from the date of notification of compliance status)

1.	All instances where organic HAP/VOC limits were exceeded. [63.753(c)(l)(i) and (ii)]

2.	Control device exceedances (out-of-compliance). [63.753(c)(l)(iii), (iv), and (v)]

3.	Periods when operation not immediately shut down when the pressure drop or water flow rate
was outside limits. [63.753(c)(l)(vi)]

4.	Statement certifying compliance. [63.753(c)(l)(vii)]

Annual (12 months from the date of notification of compliance status)

5.	Number of times the pressure drop or water flow rate limits were exceeded. [63.753(c)(2)]



Requirements

Depainting Operations

Exemptions

1.	Facilities depainting 6 or less completed aerospace vehicles per calendar year. [63.746(a)]

2.	Depainting of parts or units normally removed from the plane for depainting (except wings
and stabilizers). [63.746(a)(1)]

3.	Aerospace vehicles or components intended for public display, no longer operational, and not
easily capable of being moved. [63.746(a)(2)]

4.	Depainting of radomes and parts, subassemblies, and assemblies normally removed from the
primary aircraft before depainting. [63.746(a)(3)]

Standards

1.	Zero organic HAP emissions from chemical strippers or softeners. [63.746(b)(1)]

2.	Minimize inorganic HAP emissions when equipment malfunctions. [63.746(b)(2)]

3.	Facility (average) allowance for spot stripping and decal removal: 26 gallons of strippers or
190 pounds of HAP per commercial aircraft per year; and 50 gallons of strippers or 365
pounds of HAP per military aircraft per year. [63.746(b)(3)]

4.	Follow operating requirements for depainting operations generating airborne inorganic HAP.
[63.746(b)(4)]

5.	Mechanical and hand sanding are exempt from requirements of §63.746(b)(4).

[63.746(b)(5)]

6.	Control HAP emissions at 81% efficiency for systems installed before effective date
(September 1, 1995), and 95% efficiency for newer systems. [63.746(c)]

5


-------
Requirements

Depainting Operations

Shaded areas with bold italics indicate final amendments to the NESHAP as of September 1997.

Performance
Test Periods and
Tests

Organic HAP

1.	Initial performance test of all control devices is required to demonstrate compliance with
overall control efficiency requirement. [63.749(f)(1), (f)(2), and (f)(3)]

2.	Performance Test Period for noncarbon adsorber, three 1-hour test runs; for carbon adsorber,
each rolling material balance period. [63.749(f)(1)]

3.	Test period for spot stripping and decal removal usage limits: each calendar year.
[63.749(f)(1)]

Inorganic HAP

4.	Operating requirements specified in § 63.746(b)(4). [63.749(g)]	

Test Methods
and Procedures

Organic HAP

1.	Overall control efficiency of carbon adsorber system may be determined using specified
procedures and equations 9 through 14; for other control devices, must determine capture and
destruction efficiencies (use equations 15 through 18 to calculate overall control efficiency).
For capture efficiency, use Procedure T in Appendix B to 40 CFR 52.741 for total enclosures
and 40 CFR 52.741(a)(4)(iii) procedures for all other enclosures. [63.750(g) and (h)]

2.	Spot stripping and decal removal: Procedures are provided for determining volume of
chemical strippers (equation 20) or weight of organic HAP used per aircraft (equation 21).
[63.750(j)]

Inorsanic HAP

3.	Dry particulate filter certification: use Method 319 to meet or exceed the efficiency data
points in Tables 1 and 2 of 63.745for existing sources or Tables 3 and 4 of § 63.745for
new sources. [63.750(o)]

Monitoring

Continuously monitor pressure drop across filter; read and record pressure drop or water flow rate
through waterwash system, once per shift. [63.751(d)]	

Recordkeeping

1.

2.

3.

4.

5.

6.

7.

Name and monthly volumes of each chemical stripper used or monthly weight of organic
HAP used in chemical strippers. [63.752(e)(1)]

For controlled chemical strippers (carbon adsorber), overall control efficiency and length of
rolling period and all supporting test results/data/calculations; certification of the accuracy of
the device. [63.752(e)(2)]

For controlled chemical strippers (other control devices), overall control efficiency and
supporting test results/data/calculations. [63.752(e)(3)]

List of parts/assemblies normally removed. [63.752(e)(4)]

For nonchemical based equipment, name and type, and malfunction information including
dates, description, and alternative methods used. [63.752(e)(5)]

For spot stripping and decal removal, volume of stripper or weight of organic HAP used,
annual number of aircraft stripped, annual average volume or weight per aircraft, and all
data/calculations used to calculate volume or weight per aircraft. [63.752(e)(6)]

Pressure drop across filter or water flow rate through waterwash system, once per shift and
acceptable limits. [63.752(e)(7)]	

Reporting

Semiannual (6 months from the date of notification of compliance status)

1.	24-hour periods where organic HAP were emitted from depainting operations.
[63.753(d)(l)(i)]

2.	New/reformulated chemical strippers and HAP contents. [63.753(d)(1)(h), (iii), and (iv)]

3.	New nonchemical depainting techniques. [63.753(d)(l)(v)]

4.	Malfunction information on nonchemical depainting techniques including dates, description,
and alternative methods used. [63.753(d)(l)(vi)]

5.	Periods when operation not immediately shut down when the pressure drop or water flow rate
was outside limits. [63.753(d)(l)(vii)]

6.	List of new/discontinued aircraft models and, for new models, list of parts normally removed
for depainting. [63.753(d)(l)(viii)]

7.	Organic HAP control device exceedances. [63.753(d)(3)]

8.	Statement certifying compliance. [63.753(d)(l)(ix)]

Annual (12 months from the date of notification of compliance status)

9.	Exceedances of average annual volume or weight allowance for spot stripping and decal
removal. [63.753(d)(2)(i)]

10.	Number of times the pressure drop or water flow rate limits were exceeded. [63.753(d)(2)(h)]

Shaded areas with bold italics indicate final amendments to the NESHAP as of September 1997.

6


-------
Requirements

Maskant Operations

Standards

Minimize spills during handling and transfer. [63.747(b)]

Uncontrolled Maskants

1.	Organic HAP emissions: <622 g/l (5.2 lb/gal) (less water) as applied for Type /; < 160 g/1
(1.3 lb/gal) (less water) as applied for Type II. [63.747(c)(1)]

2.	VOC emissions: <622 g/l (5.2 lb/gal) (less water and exempt solvents) as applied for
Tvpe /, < 160 g/l (1.3 lb/gal) (less water and exempt solvents) as applied for Type II.
[63.747(c)(2)]

3.	Exemption for touch-up of scratched surfaces, damaged maskant, and trimmed edges.
[63.747(c)(3)]

4.	Comply by either: (1) using maskants below content limits, or (2) using monthly volume-
weighted averaging to meet content limits. [63.747(e)]

Controlled Maskants

5.	If control device is used, system must capture and control all emissions from maskant
operation and must achieve an overall control efficiency of at least 81%. [63.747(d)]

Performance Test
Periods and Tests

Uncontrolled

1.	Performance Test Period for maskants that are not averaged, each 24-hour period; for
maskants that are averaged, each 30-day period (unless otherwise specified). [63.749(h)(1)]

Controlled

2.	Performance Test Period for noncarbon adsorber, three 1-hour test runs; for carbon adsorber,
each rolling material balance period. [63.749(h)(1)]

3.	Initial performance test required for all control devices to demonstrate compliance with
overall control efficiency requirement. [63.749(h)(2)]

Test Methods and
Procedures

1.	Organic HAP level determination procedures. [63.750(k) and (1)]

2.	VOC level determination procedures. [63.750(m) and (n)]

3.	Overall control efficiency of carbon adsorber system determined using specified procedures
and equations 9 through 14; for other control devices, determine capture and destruction
efficiencies (use equations 15 through 18 to calculate overall control efficiency). For capture
efficiency, use Procedure T in Appendix B to 40 CFR 52.741 for total enclosures and 40
CFR 52.74l(a)(4)(iii) procedures for all other enclosures. [63.750(g) and (h)]

Monitoring

1. Incinerators and carbon adsorbers: temperature sensors with continuous recorders for

incinerators; and install, calibrate, maintain, and operate temperature monitors according to
manufacturer's specifications. Use CEMS as an alternative. [63.751(b)]

Recordkeeping

Uncontrolled Maskants

1.	For maskants not averaged, mass of organic HAP and VOC emitted per unit volume of
chemical milling maskant (less water) (H and G,): all data, calculations, and test results;
monthly volumes of each maskant.. [63.752(f)(1)]

2.	For "averaged" maskants, monthly volume-weighted average mass of organic HAP or VOC
emitted per unit volume of chemical milling maskant as applied (less water) (Ha and Ga); all
data, calculations, and test results. [63.752(f)(2)]

Controlled Maskants

3.	For carbon adsorbers, overall control efficiency and length of rolling period and all
supporting test results/data/calculations used in determining the overall control efficiency;
certification of the accuracy of the device that measures the amount of HAP or VOC
recovered. [63.752(f)(3)]

4.	For incinerators, overall control efficiency; test results, data, and calculations used in
determining the overall control efficiency; length of rolling material balance period with data
and calculations; record of certification of the accuracy of the device that measures amount
of HAP or VOC recovered; or record of carbon replacement time for nonregenerative carbon
adsorbers; and incinerator temperature(s). [63.752(f)(4)]

Reporting

Semiannual (6 months from the date of notification of compliance status)

1.	Exceedances of organic HAP/VOC limits. [63.753(e)(1) and (2)]

2.	Control device exceedances (out of compliance). [63.753(e)(3)]

3.	New maskants. [63.753(e)(4)]

4.	New control devices. [63.753(e)(5)]

5.	Statement certifying compliance. [63.753(e)(6)]

Shaded areas with bold italics indicate final amendments to the NESHAP as of September 1997.

7


-------
Questions & Answers

If I am a small aerospace facility, how do I
know if I need to comply with the NESHAP?

If your potential HAP emissions from a]i sources are
greater than the 10/25 tons/yr cutoffs, you are
considered a major source and therefore subject to
the NESHAP requirements. We recommend that
you conduct an emissions inventory of your annual
HAP emissions and carefully evaluate what your
current and future "potential to emit" really is.

If a facility manufactures many different
products that are used by many different
industries (including aerospace), how do I
determine if the facility is subject to the
NESHAP? The major source determination
involves the total of all HAP emissions from all
sources within a contiguous facility (regardless of
types of products or end-users). If the facility is a
major source, only those operations involving
aerospace components would be subject to the
aerospace NESHAP requirements.

What are the NESHAP de minimis and/or
low usage exemptions? De minimis exemption -
the NESHAP does not apply to primers, topcoats,
chemical milling maskants, strippers, and cleaning
solvents containing HAP and VOC at a
concentration less than 0.1 percent for carcinogens
or 1.0 percent for noncarcinogens, as determined
from manufacturer's representations-see 63.741(f).
Low usage exemption - the requirements for
primers, topcoats, and chemical milling maskants in
§ 63.745 and § 63.747 do not apply to separate
formulations whose usages are less than 50 gal/yr;
the combined annual total of all such coatings has
to be less than 200 gal/yr-see 63.741(g).

How can I certify paint filters for a coating
spray booth? Test method 319 was developed to
determine the filtration efficiency of paint overspray
arrestors (filters). The recently amended NESHAP
contains filtration efficiency requirements fortwo-
and three-stage arrestors.

When do I have to run performance tests
on control equipment? Per the General
Provisions, performance testing must be completed
within 180 days of the compliance date. You then
have 60 days to report the results of the testing. For
the Aerospace NESHAP the compliance date is
September 1, 1998. Therefore, performance testing
must be completed by March 1, 1999 and the
notification of compliance status is due May 1,

1999.

Who is responsible for complying with the
NESHAP if the aerospace activities are
conducted at a leased facility owned by a

local government or Airport Authority? The

owner or operator of the "affected source" should
conduct an emissions inventory to determine major
source status based on aggregate air emissions of
all HAP material. If it is determined that the facility
is a major source, any details involving compliance
demonstration and/or reporting would have to be
worked with the appropriate enforcement agency.

If the NESHAP limits for certain operations
(i.e., coating or maskant HAPA/OC content
limits) are more stringent than my State
limits, do I have to meet both limits? Yes, but
the limits are not likely to be identical or even have
similar units in all cases. The NESHAP
requirements are intended to reduce HAP emissions
and in some cases, such as the coating limits, VOC
can be used as a surrogate. Most State limits are
specific to VOC and/or their own list or air toxics.

In the NESHAP depainting requirements
there is an allowance for spot stripping and
decal removal; how big is a "spot"? The only
guidance we can provide comes from the NESHAP
definition of "spot stripping" which means the
depainting of an area where it is not technically
feasible to use a nonchemical depainting technique.
That area or spot can vary depending on the type of
aircraft being depainted and the circumstances
associated the coating(s) being removed.

What kind of cleaning solvents can be
used for cleaning non-aerospace related
equipment or materials? The NESHAP
requirements do not apply to non-aerospace
activities. However, the owner or operator of a
facility is not restricted from voluntarily extending to
other operations the use of compliant cleaning
solvents to simplify purchasing and recordkeeping.

Which is more stringent, the NESHAP or
the CTG? The CTG is not a regulation, but it does
provide guidelines for States to use in developing
their own VOC rules. The CTG coating (VOC
content) limits and equipment requirements are
identical to the NESHAP for primers and topcoats.
However, the NESHAP does not include any limits
for specialty coatings while the CTG does.

8


-------
~Whom can you contact for additional information?

A copy of the regulation and the amendments to the final regulation can be obtained
from the Federal Register or the EPA's Technology Transfer Network (TTN). The TTN
can be accessed via modem by dialing (919) 541 -5742 or via TELNET at the Internet
website addresses: http//www.epa.gov/ttn and/or http//www.epa.gov/ttn/oarpg.

Your State or local agency should be your first point of contact for any additional
information on how to comply with this regulation. State and local agencies who require
additional information about this regulation should contact the appropriate EPA Regional
Office.

The EPA is divided into 10 geographic regions. The following list identifies the
appropriate contact, address, and phone number for each of the EPA Regional offices:

Region I:

For submitting forms:

Air Compliance Clerk

U. S. EPA Region I (SEA)

John F. Kennedy Federal Building

One Congress Street

Boston, MA 02203-001

For applicability determinations:

Janet Bowen

(617) 565-3595

Region II:

Umesh Dholakia or Yue-On Chiu
U. S. EPA Region II
290 Broadway Street
New York, NY 10007-1866
(212) 637-4023 (Umesh)
(212) 637-4065 (Yue-On)

Region III:

Walter K. Wilkie
U. S. EPA Region III
841 Chestnut Building
Philadelphia, PA 19107
(215) 566-2150

Region IV:

Leonardo Ceron
U. S. EPA Region IV
Atlanta Federal Center
61 Forsyth Street SW
Atlanta, GA 30303-3104
(404) 562-9129

Region V:

Emmett Keegan
U. S. EPA Region V
77 West Jackson Boulevard
Chicago, IL 60604-3507
(312) 886-0678

Region VI:

Elvia Evering
U. S. EPA Region VI
First Interstate Bank Tower
@ Fountain Place
1445 Ross Avenue
12th Floor, Suite 1200
Dallas, TX 75202-2733
(214) 665-7575

Region VII:

Richard Tripp
U. S. EPA Region VII
Air Toxics Coordinator
726 Minnesota Avenue
Kansas City, KS 66101
(913) 551-7566

Region VIII:

Heather Rooney
U. S. EPA Region VIII
Air Toxics Coordinator
999 18th Street, Suite 500
Denver, CO 80202-2466
(303) 312-6971

Region IX:

Nikole Reaksecker
U. S. EPA Region IX
Air Division

75 Hawthorne Street/Air-6
San Francisco, CA 94105
(415) 744-1187

Region X:

Doug Hardesty
U. S. EPA Region X
Air Toxics Coordinator
1200 Sixth Avenue
Seattle, WA 98101
(206) 553-6641

The information in this pamphlet is intended for general reference only; it is not a full and complete
statement of the technical or legal requirements associated with the regulation.