v>EPA

United States
Environmental Protection
Agency

Site Redevelopment Profile

Battery Tech (Duracell-Lexington) Site

305 New U.S. Highway 64 East
Lexington, North Carolina 27292

Property Overview

Size

145 acres

Current Site Uses

•	Piedmont Candy currently uses the Former Plant 3 building and asphalt
parking area for warehousing and distribution of candy products.

Use Restrictions

•	A 2002 Declaration of Restrictive Covenants prohibits residential land use
and any significant disturbance of the surface or subsurface soil.

•	In 2017, the 2002 Declaration of Restrictive Covenants was removed from
the parcel containing Former Plant 3, as this parcel was deemed free of
residual contamination.

NORTH

A map of the site in North Carolina.

Surrounding Population

2,351	22,417

1 MILE	3 MILES

36,505

5 MILES

Site History and Redevelopment Timeline

1960s

P.R. Mallory began operating a battery
manufacturing facility at the site.

1980

Duracell acquired P.R. Mallory and
reported contamination at the site to EPA.

1982

Duracell started remedial investigation
and feasibility studies (RI/FS) at the site.

1999

EPA selected a cleanup plan for
contaminated soil and sediment (OU1).

2002

EPA selected a cleanup plan for
contaminated groundwater (OU2).

PRP began cleaning up OU1; site owners
recorded a Declaration of Restrictive
Covenants for OU1.

2003

PRP designed the cleanup; PRP began
cleaning up OU2.

2004

PRP finished cleaning up OU1.

2006

Duracell ended battery manufacturing
operations at the facility.

2007-2008

Demolition of Plant 1 and Plant 4 completed.
Tower Investments bought the parcel
containing the Former Plant 3.

2015

Piedmont Candy Company bought
property at the site for warehousing and
distribution of candy products.

2017

EPA issued an Explanation
of Significant Differences to rescind the
2002 Declaration of Restrictive Covenants
from the parcel containing Former Plant 3,
where Piedmont Candy operates.

Present

Piedmont Candy continues to operate on
the Former Plant 3 parcel. JCR Investment
Properties is considering additional
redevelopment of adjacent parcels.

October 2020

o


-------
History and Cleanup

Since the 1980s, EPA has worked together with the North
Carolina Department of Environmental Quality (NCDEQ)
and the site's potentially responsible parties (PRPs) to
clean up the Battery Tech (Duracell-Lexington) site and
return it to use. Today, it supports commercial reuse, and
discussions are underway regarding redevelopment of
additional site areas.

Beginning in the 1960s, operations at the facility included
production of mercury compounds for battery cells and
operation of a mercury retort furnace that released an
estimated 10,000 pounds of mercury into the air.

Former operations at the site used solvents to clean tools,
dies, presses and battery cells, and then discharged these
solvents into a seepage pit. The battery manufacturing
operations resulted in mercury and volatile organic
compound (VOC) contamination in soil and groundwater
at the site. Runoff from the facility area also resulted
in mercury contamination in the sediment of a nearby
tributary.

In the 1980s and 1990s, Duracell conducted a series of
investigations and removal actions under the guidance
of the state and EPA. EPA and the PRPs signed a Unilateral
Administrative Order (UAO) in 1995 to perform the site's
remedial investigation and feasibility study (RI/FS). The

PRPs agreed to conduct the RI/FS and pay associated
costs as outlined in the UAO. Although the site was not
listed on the Superfund program's National Priorities
List, EPA addressed the site in a similar manner. Due
to the site's complexity, EPA divided the site into two
operable units (OUs). OU1 consists of contaminated
soil and sediment. OU2 consists of contaminated
groundwater.

From 2002 to 2004, the PRPs worked with EPA and
NCDEQ to clean up OU1, including excavation and
treatment of contaminated soil and sediment, capping
of some excavated areas, and long-term monitoring.
The PRPs are addressing OU2 contaminated
groundwater with a groundwater treatment system.
Groundwater treatment started in 1983. Installation
of additional recovery wells and expansion of the
treatment system has occurred several times, with the
last expansion taking place as part of OU2 cleanup
activities. Duracell stopped battery manufacturing
operations at the facility in 2006. Demolition of Plant
1 and Plant 4 at the facility took place in 2007 and
2008. In 2015, the PRPs performed a study to evaluate
whether in-situ chemical oxidation techniques in the
contamination source areas could reduce the amount
of time it takes to achieve cleanup levels.

The former Duracell facility at the site (left), demolition of on-site
buildings (center), view of the site following demolition (right).

o


-------
Redevelopment

Duracell sold three parcels totaling 38 acres, including
the 10-acre parcel containing the Former Plant 3, toTower
investments in 2007.Tower Investments then sold these
three site parcels to JCR Investment Properties in 2015.
JCR Investment Properties is owned by the President-
CEO of Piedmont Candy Company. Piedmont Candy
Company expanded its operations in 2015, allowing
the company to expand its product line, hire new
employees and create jobs in the community. Piedmont
Candy currently uses the Former Plant 3 building and
asphalt parking area for warehousing and distribution of
candy products. JCR Investment Properties is exploring
possible additional redevelopment opportunities on
surrounding parcels.

The site's successful cleanup and reuse shows how
effective partnerships and collaboration between diverse
site stakeholders can transform formerly contaminated
Superfund sites into areas that provide opportunities
and economic benefits for the surrounding community.

40

million gallons
of contaminated
groundwater treated

1,500

pounds of VOCs
removed from
contaminated water

160

pounds of mercury
removed from
contaminated sediment

30,000

pounds of soil
containing mercury
removed

Contacts

For more information, please contact:

Chelsea Sebetich | (202) 566-1151
sebetich.chelsea@epa.gov

Scott Miller | (404) 562-9120
miller.scott(5)epa.aov

Plant #3

A historic aerial view of the site.

For more information see: www.epa.gov/superfund-redevelopment


-------